- Description
- COMPLETION OF GUSANE BRIDGE (BOUNDARY BRGY. DICOYONG-BRGY. DUMALOGDUG), SINDANGAN, ZAMBO. DEL NORTE. (CONSTRUCTION OF ONE LANE BRIDGE: ABUTMENT A AND B, APPROACHES A AND B, PIER 3, PIER 4 AND BRIDGE SUPERSTRUCTURES)
- Category
- Bridges
- Component categories
- Bridges
- Category group
- Bridges
- Province / DEO
- Zamboanga del Norte 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2016 Locally Funded Projects
- Infrastructure year
- 2016
- Start date
- May 8, 2017
- Completion date
- Apr 11, 2018
- Effective end date
- Apr 11, 2018
- Duration
- 338 days
- Is live
- No
- Is completed
- Yes