- Description
- CLUSTER 3: 1. CONST. OF (3) UNITS RAIN WATER COLLECTOR @ LUTAY IS; 2. CONST. OF (3) UNITS RAIN WATER COLLECTOR @ MALINIS ES, ALL OF MALUNGON SAR PRO.; 3. CONST OF (3) UNITS RAIN WATER COLLECTOR @PANGOLEEL IS; 4. CONST. OF (3) UNITS RAIN WATER COLLECTOR @
- Category
- Water Provision and Storage
- Component categories
- Water Provision and Storage
- Category group
- Water Provision and Storage
- Province / DEO
- Sarangani DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2017 MFO-3
- Infrastructure year
- 2017
- Start date
- Jul 3, 2017
- Completion date
- Aug 31, 2017
- Effective end date
- Aug 31, 2017
- Duration
- 59 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- No
- Citizen reports
- 0
- Coordinates
- 5.96589, 125.28635