- Description
- ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION, REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS, BATANGAS-TABANGAO-LOBO RD K0128+252 - K0128+384, K0137+400 -
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Batangas 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2018 OO-1
- Infrastructure year
- 2018
- Start date
- Apr 10, 2018
- Completion date
- Oct 15, 2018
- Effective end date
- Oct 15, 2018
- Duration
- 188 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 13.63490, 121.05350