- Description
- CONSTRUCTION AND COMPLETION OF A SCHOOL BUILDINGS IN THE ELEMENTARY AND SECONDARY CLASSROOMS, VILLAHERMOSA ELEMENTARY SCHOOL, DARAGA(LOCSIN) (9.5M X 32.00M)
- Category
- Buildings and Facilities
- Component categories
- Buildings and Facilities
- Category group
- Buildings and Facilities
- Province / DEO
- Albay 2nd DEO
- Program
- Outside Infra
- Source of funds
- Outside Infra - GAA 2018 DepEd BEFF
- Infrastructure year
- 2018
- Start date
- Jul 9, 2018
- Completion date
- Nov 25, 2018
- Effective end date
- Nov 25, 2018
- Duration
- 139 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 13.04311, 123.71229