- Description
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET_PRESERVATION_PROGRAM - PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG SANTANDER-BARILI-TOLEDO ROAD; SECTION 1: K0189+000 - K0190+000; SECTION 2: K0197+000- K0197+751; SECTION
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Cebu 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2018 OO-1
- Infrastructure year
- 2018
- Start date
- Feb 27, 2018
- Completion date
- Jun 5, 2018
- Effective end date
- Jun 5, 2018
- Duration
- 98 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 9.91510, 123.40203