- Description
- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS/CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL, SAN MIGUEL SECTION, STA. 0+700-STA. 2+234, SOGOD, SOUTHERN LEYTE (CONSTRUCTION OF FLOOD MITIGATION STRUCTURE), SOGOD, SOUTHERN LEYTE
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Southern Leyte 1st DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2018 OO-2
- Infrastructure year
- 2018
- Start date
- Mar 26, 2018
- Completion date
- Sep 30, 2018
- Effective end date
- Sep 30, 2018
- Duration
- 188 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 10.13200, 124.86001