- Description
- COMPLETION OF TWO(2) STOREY FOUR(4) CLASSROOM SCHOOL BUILDING AT CARIDAD ES, DUMINGAG, ZAMBOANGA DEL SUR
- Category
- Buildings and Facilities
- Component categories
- Buildings and Facilities
- Category group
- Buildings and Facilities
- Province / DEO
- Zamboanga del Sur 1st DEO
- Program
- Outside Infra
- Source of funds
- Outside Infra - GAA 2018 DepEd BEFF
- Infrastructure year
- 2018
- Start date
- Dec 27, 2018
- Completion date
- Feb 9, 2019
- Effective end date
- Feb 9, 2019
- Duration
- 44 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 8.14979, 123.36428