- Description
- CLUSTER IV-CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMS(RWCS) 1.NGUB PS,BRGY. MABINI,MALALAG 2. LAPULAPU ES,BRGY.LAPULAPU,MALALAG 3. TAGANSULE ES,BRGY.TAGANSULE,MALALAG 4. LAPERAS ES,BRGY.LAPERAS, SULOP 5. PARAMI PS,BRGY.PARAMI,SULOP 6. KIMLAWIS NHS,BRGY.K
- Category
- Water Provision and Storage
- Component categories
- Water Provision and Storage
- Category group
- Water Provision and Storage
- Province / DEO
- Davao del Sur DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2019 CSSP
- Infrastructure year
- 2019
- Start date
- Aug 13, 2019
- Completion date
- Oct 11, 2019
- Effective end date
- Oct 11, 2019
- Duration
- 59 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 6.52611, 125.33241