- Description
- CLUSTER A CONSTRUCTION OF RAINWATER COLLECTOR (RWCS) IN 1) 2 UNITS, DPWH COTABATO CITY DISTRICT ENGINEERING OFFICE; 2) 3 UNITS AT BRGY. ROSARY HEIGHTS 7; 3) 2 UNITS AT BRGY MROSARY HEIGHTS 8: 4) 1 UNIT AT BRGY ROSARY HEIGHTS 9; 5) 4 UNITS AT BRGY ROSARY
- Category
- Water Provision and Storage
- Component categories
- Water Provision and Storage
- Category group
- Water Provision and Storage
- Province / DEO
- Cotabato City DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2019 CSSP
- Infrastructure year
- 2019
- Start date
- Dec 2, 2019
- Completion date
- Feb 3, 2020
- Effective end date
- Feb 3, 2020
- Duration
- 63 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 7.19397, 124.19582