- Description
- CONSTRUCTION OF TWO (2) STOREY-SIX (6) CLASSROOM SCHOOL BUILDING, (100158) TABUCBUC ELEMENTARY SCHOOL MARCOS, ILOCOS NORTE
- Category
- Buildings and Facilities
- Component categories
- Buildings and Facilities
- Category group
- Buildings and Facilities
- Province / DEO
- Ilocos Norte 2nd DEO
- Program
- Outside Infra
- Source of funds
- Outside Infra - GAA 2020 DepEd BEFF
- Infrastructure year
- 2020
- Start date
- Aug 11, 2020
- Completion date
- Mar 18, 2021
- Effective end date
- Mar 18, 2021
- Duration
- 219 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 18.00821, 120.69890