- Description
- NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS, CAPALAYAN-PLACER ROAD, SURIGAO DEL NORTE / BRGY.HIMAMAUG, TAGANA-AN, SURIGAO DEL NORTE STA.1+604.00 - STA.2+244.00 (ROAD), STA.3+295.00 - STA.3+315.00 (BRIDGE)
- Category
- GAA 2020 OO-1
- Component categories
- Bridges, Roads
- Category group
- OTHER
- Province / DEO
- Surigao del Norte 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2020 OO-1
- Infrastructure year
- 2020
- Start date
- Mar 23, 2020
- Completion date
- Mar 31, 2021
- Effective end date
- Mar 31, 2021
- Duration
- 373 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- No
- Citizen reports
- 0
- Coordinates
- 9.69811, 125.58193