- Description
- CLUSTER XXIV: 1. LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, SIQUIJOR, SIQUIJOR; 2. LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - M
- Category
- Buildings and Facilities
- Component categories
- Buildings and Facilities
- Category group
- Buildings and Facilities
- Province / DEO
- Siquijor DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2021 LP
- Infrastructure year
- 2021
- Start date
- Mar 26, 2021
- Completion date
- Aug 17, 2021
- Effective end date
- Aug 17, 2021
- Duration
- 144 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 9.21592, 123.51403