- Description
- PASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 4A RIVER IMPROVEMENT WORKS ALONG MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE), STA. 15+450 TO STA. 15+600, RIGHT BANK, MARIKINA CITY
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Metro Manila 1st DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2021 OO-2
- Infrastructure year
- 2021
- Start date
- Feb 8, 2022
- Completion date
- Dec 4, 2022
- Effective end date
- Dec 4, 2022
- Duration
- 299 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 14.65372, 121.09277