- Description
- CONSTRUCTION OF ALAKAN FLOOD CONTROL STA. 0+155 - STA. 0+386 (L.S.), STA. 0+261 - STA. 0+323 (R.S.), STA. 0+356 - STA. 0+443 (R.S.), STA. 0+692 - STA. 0+745 (L.S.), STA. 0+958 - STA. 1+000 (B.S.) BUGUIAS, BENGUET
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Benguet 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2021 OO-2
- Infrastructure year
- 2021
- Start date
- Jan 16, 2022
- Completion date
- Jun 12, 2022
- Effective end date
- Jun 12, 2022
- Duration
- 147 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 16.78942, 120.83364