- Description
- BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD AND DRAINAGE CANAL AT BARANGAY, SAN MIGUEL, TARLAC CITY, TARLAC
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Tarlac DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 CSSP
- Infrastructure year
- 2022
- Start date
- Mar 30, 2022
- Completion date
- Jun 6, 2022
- Effective end date
- Jun 6, 2022
- Duration
- 68 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 15.42902, 120.59575