- Description
- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, 21ST ST., RIZAL AVENUE TO JOHNSON ST., EAST BAJAC-BAJAC, OLONG
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Zambales 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 CSSP
- Infrastructure year
- 2022
- Start date
- Mar 24, 2022
- Completion date
- Jun 21, 2022
- Effective end date
- Jun 21, 2022
- Duration
- 89 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 14.83989, 120.28824