- Description
- OO2:CONST./REHAB./IMPROVEMENT OF FLOOD MITIGATION STRUCTURE MAGARAO FLOOD CONTROL(BELL-CASURAY-FUNDADO CREEK MAGARAO CAMARINES SUR) BOTH SIDES
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Camarines Sur 3rd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 OO-2
- Infrastructure year
- 2022
- Start date
- Apr 1, 2022
- Completion date
- Dec 5, 2022
- Effective end date
- Dec 5, 2022
- Duration
- 248 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 13.66036, 123.17044