- Description
- FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION/IMPROVEMENT OF NARANGASAN RIVER CONTROL, STA.2+887 - STA.3+001 (UPSTREAM, RIGHT SIDE), STA.2+893 - STA.3+001 (UPSTREAM, LEFT SIDE), MI
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Masbate 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 OO-2
- Infrastructure year
- 2022
- Start date
- Feb 8, 2022
- Completion date
- Aug 16, 2022
- Effective end date
- Aug 16, 2022
- Duration
- 189 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 12.22628, 123.45216