- Description
- PREVENTIVE MAINTENANCE SECONDARY ROADS, JCT. BUENAVISTA - LAWAAN - MARABUT ROAD, K0982+000 - K0982+178; K0982+194 - K0987+367;K0987+382 - K0989+457; K0989+467.22 - K0991+290, QUINAPONDAN, EASTERN SAMAR
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Eastern Samar DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 OO-1
- Infrastructure year
- 2022
- Start date
- Feb 13, 2022
- Completion date
- Jul 6, 2022
- Effective end date
- Jul 6, 2022
- Duration
- 143 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 11.11285, 125.50652