- ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - SECONDARY ROADS NASUGBU-LIAN-CALATAGAN RD - K0099 + 456 - K0100 + 500, K101 + 269 - K0102 + 000
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Batangas 1st DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2023 OO-1
- Infrastructure year
- 2023
- Start date
- Mar 23, 2023
- Completion date
- May 5, 2023
- Effective end date
- May 5, 2023
- Duration
- 43 days
- Is live
- No
- Is completed
- Yes