- Description
- REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MALIHAW RIVER (PHASE I), BARANGAY VI-A AND BARANGAY IX, VICTORIAS CITY, NEGROS OCCIDENTAL
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Negros Occidental 1st DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2023 CSSP
- Infrastructure year
- 2023
- Start date
- Feb 14, 2023
- Completion date
- Nov 24, 2023
- Effective end date
- Nov 24, 2023
- Duration
- 283 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 10.90932, 123.05996