- Description
- CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) PITOGO CONSOLACION
- Category
- Buildings and Facilities
- Component categories
- Buildings and Facilities
- Category group
- Buildings and Facilities
- Province / DEO
- Cebu 6th DEO
- Program
- Outside Infra
- Source of funds
- Outside Infra - Unprogrammed Appropriations 2023
- Infrastructure year
- 2023
- Start date
- Dec 13, 2023
- Completion date
- Jul 8, 2024
- Effective end date
- Jul 8, 2024
- Duration
- 208 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 10.37946, 123.96515