- Description
- NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CONSTRUCTION OF MASALASA CREEK SERVICE ROAD/ BY-PASS/ DIVERSION ROAD INCLUDING SLOPE PROTECTION STRUCTURE (SEGMENT A), TARLAC CITY, TARLAC
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Tarlac DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2024 OO-1
- Infrastructure year
- 2024
- Start date
- Feb 27, 2024
- Completion date
- Oct 18, 2024
- Effective end date
- Oct 18, 2024
- Duration
- 234 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 15.47429, 120.62464