- Description
- ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, BUCANDALA SECTION, SEGMENT 2, CAVITE
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Cavite 1st DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2024 OO-1
- Infrastructure year
- 2024
- Start date
- Feb 27, 2024
- Completion date
- Apr 15, 2025
- Effective end date
- Apr 15, 2025
- Duration
- 413 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 14.41114, 120.92400