57 projects on file, including joint ventures this contractor is part of.
Total projects
57
Total budget
₱1.1B
Average progress
99.3%
Completion rate
96.5%
Average risk score
29.2
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 57 | ₱1.1B | 29.2 | 0 | 99.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 28 | ₱356.4M | 27.2 | 0 | 99.9% |
| Flood Control and Drainage | 20 | ₱637.1M | 30.5 | 0 | 98.2% |
| Buildings and Facilities | 4 | ₱28.7M | 32.6 | 0 | 100.0% |
| Bridges | 4 | ₱19.8M | 18.1 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱29.4M | 88.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CH0020CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BARANGAY SAN ANTONIO (PHASE II), FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.4M | 100% | High risk89 | —-0.030 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 25CH0022CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CAULAMAN RIVER, BARANGAY DAMPE, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.7M | 100% | Low risk30 | —-0.090 |
| 27 | 20CH0071CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONTROL AND DRAINAGE - DRAINAGE/PROTECTION WORKS - CONSTRUCTION OF SLOPE PROTECTION ALONG CAULAMAN RIVE, GUTAD SECTION, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.4M | 100% | Low risk30 | —-0.090 |
| 28 | 23CH0036FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION ALONG GPDC. SAN PABLO-SANTA RITA, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.4M | 100% | Low risk30 | —-0.090 |
| 29 | 19CH0080CONSTRUCTION OF SLOPE PROTECTION ALONG PORAC RIVER, PULUNGMASLE, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.7M | 100% | Low risk30 | —-0.090 |
| 30 | 21CH0090FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION ALONG PORAC RIVER, PAGUIRUAN SECTION, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱19.6M | 100% | Low risk29 | —-0.091 |
| 31 | 20CH0007CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION ALONG PORAC RIVER, STA. 0+000 - STA. 0+343, BRGY. CALANTAS, FLORIDABLANCA, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.9M | 100% | Low risk29 | —-0.089 |
| 32 | 21CH0003FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION ALONG PORAC RIVER, STA. 00+000-STA. 0+320 BRGY. CALANTAS, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.4M | 100% | Low risk29 | —-0.090 |
| 33 | 20CH0047CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONTROL AND DRAINAGE - DRAINAGE/PROTECTION WORKS - CONSTRUCTION OF SLOPE PROTECTION ALONG SANTOL CREEK, SAN JOSE SECTION, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱29.4M | 100% | Low risk29 | —-0.090 |
| 34 | 25CH0038CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PORAC RIVER, ASCOMO SECTION, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | On-Going | ₱24.5M | 64% | Low risk29 | —-0.042 |
| 35 | 20CH0005LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE/PROTECTION WORKS - CONSTRUCTION OF SLOPE PROTECTION ALONG GPDC DIVERSION CHANNEL GUMI, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱18.9M | 100% | Low risk29 | —-0.090 |
| 36 | 23CH0059CONSTRUCTION OF SLOPE PROTECTION AT SAPANG MATUA, STA. MONICA-DON IGNATIO DIMSON, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱19.6M | 100% | Low risk29 | —-0.091 |
| 37 | 21CH0022FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYTEMS - CONSTRUCTION OF SLOPE PROTECTION ALONG GUMI RIVER, STA. 0+000-STA.0+116.26 (LEFT SIDE), STA. 0+010 - STA. 0+116.26 (RIGHT SIDE), BARANGAY STA. CATAL | Region III | Pampanga 2nd DEO | Completed | ₱19.6M | 100% | Low risk29 | —-0.091 |
| 38 | 17CH0060ROAD CONCRETING IN SAN NICOLAS 1ST, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱1.9M | 100% | Low risk28 | —-0.064 |
| 39 | 17CH0083ROAD CONCRETING IN MANIBAUG PARALAYA, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱1.9M | 100% | Low risk28 | —-0.064 |
| 40 | 17CH0093REPAIR OF DIKE IN MANUALI, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱1.9M | 100% | Low risk27 | —-0.060 |
| 41 | 19CH0164CONCRETING OF BRGY. BABO SACAN, - BRGY. PULONG SANTOL FMR, BRGY. BABO SACAN AND BRGY. PULONG SANTOL, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱11.5M | 100% | Low risk25 | —-0.043 |
| 42 | 20CH0088CONCRETING OF BRGY. PULONGMASLE FMR, BRGY. PULONGMASLE, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱9.6M | 100% | Low risk24 | —-0.041 |
| 43 | 20CH0080CONCRETING OF PUROK 1, BRGY. PALAT FMR, BRGY. PALAT, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱11.9M | 100% | Low risk24 | —-0.043 |
| 44 | 18CH0137CONCRETING OF BRGY. STA. CRUZ FMR, BRGY. PORAC, BRGY. STA. CRUZ, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱6.6M | 100% | Low risk24 | —-0.041 |
| 45 | 24CH0120IMPROVEMENT/UPGRADING OF BRGY. HACIENDA DOLORES FMR, BRGY. HACIENDA DOLORES, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱5M | 100% | Low risk24 | —-0.044 |
| 46 | 24CH0112IMPROVEMENT/UPGRADING OF PUROK 2, BRGY. SAN AGUSTIN BETIS FMR, BRGY. SAN AGUSTIN BETIS, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱5M | 100% | Low risk24 | —-0.045 |
| 47 | 17CH0111CONCRETING OF BRGY. SINURA FMR, BRGY. SINURA, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.007 |
| 48 | 17CH0113CONCRETING OF BRGY. PULONG SANTOL FMR, BRGY. PULONG SANTOL, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.007 |
| 49 | 18CH0112CONSTRUCTION OF LINE CANAL BARANGAY SINURA, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.6M | 100% | Low risk15 | —-0.087 |
| 50 | 19CH0062REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE LAUC PAO BR. (B01508LZ) ALONG JOSE ABAD SANTOS AVE. (JASA), LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.6M | 100% | Low risk14 | —-0.062 |