Opening the dossier…
Opening the dossier…
Contractor dossier
116 projects on file, including joint ventures this contractor is part of.
Total projects
116
Total budget
₱2.8B
Average progress
98.2%
Completion rate
94.0%
Average risk score
41.9
Medium risk on average, out of 100
Flagged as unusual
3
2.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 112 | ₱2.7B | 41.8 | 3 | 98.1% |
| Negros Island Region | 4 | ₱105.4M | 45.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 52 | ₱1.6B | 46.7 | 0 | 97.9% |
| Buildings and Facilities | 34 | ₱349M | 23.6 | 0 | 99.7% |
| Flood Control and Drainage | 19 | ₱611.6M | 49.2 | 0 | 95.2% |
| OTHER | 10 | ₱274.9M | 65.3 | 3 | 99.9% |
| Water Provision and Storage | 1 | ₱10.4M | 47.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18HB0157CONCRETING OF BRGY. CANTAGAY FMR, BRGY. CANTAGAY, JAGNA, BOHOL, STA. 0+000.00 - STA. 0+793.26, STA. 0+834.96 - STA. 1+040.00, JAGNA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱9.5M | 100% | High risk78 | Flagged0.012 |
| 24HB0019ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - LOAY INTERIOR RD - K0168 + 839 - K0169 + 865 | Region VII | Bohol 3rd DEO | On-Going | ₱87.3M | 99% | High risk72 | Flagged0.012 |
| 21HB0158CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM- ROLL IT)-JCT.(TER) GABAYAN-ANOLING (CANDIJAY)-INAGH | Region VII | Bohol 3rd DEO | Completed | ₱67M | 100% | High risk71 | —-0.027 |
| 18HB0156CONCRETING OF BRGY. MALBOG FMR, BRGY. MALBOG, JAGNA, BOHOL STA. 0+000.00-STA. 0+498.12 | Region VII | Bohol 3rd DEO | Completed | ₱4.8M | 100% | High risk66 | Flagged0.013 |
| 17HA0039CONSTRUCTION OF LIBORON RIVER FLOOD CONTROL, CALAPE, BOHOL. STA. 1+065-STA. 1+700.00 PROJECT COMPONE | Region VII | Bohol 1st DEO | Completed | ₱22.7M | 100% | High risk63 | —-0.050 |
| 18HB0087CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, JCT. (LIR) QUINOGUITAN-SEVILLA-HANOPOL-TAGUSTUSAN (BALILIHAN) ROAD IN SUPPORT OF THE FURNITURE AND GARMENTS AND TOURISM INDUSTRIES, SEVILLA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱18.6M | 100% | High risk63 | —-0.030 |
| 18HB0062CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-CORBADA-INAHAGAN-CABAHIS-LA HACIENDA (ALICIA)BARANGAY ROAD LEADING TO BIRHEN SA BARANGAY NATURE RESORT AND CAGONGCAGONG, BRGY. LA HACIENDA, ALICIA, BOHOL KO0+000.00-KO1+039. | Region VII | Bohol 3rd DEO | Completed | ₱13.9M | 100% | High risk62 | —-0.030 |
| 20HB0154LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROADS SITIO CABUNGAN, BRGY. CADAPDAPAN, CANDIJAY TO BRGY. INAGHUBAN, PILAR, BOHOL, ST | Region VII | Bohol 3rd DEO | Completed | ₱39.2M | 100% | High risk62 | —-0.030 |
| 18HB0086CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, JCT. (LIR) BUENOS AIRES-NUEVA VIDA (CARMEN)-OMJON (VALENCIA) ROAD IN SUPPORT OF THE AGRIBUSINESS INDUSTRY | Region VII | Bohol 3rd DEO | Completed | ₱15.7M | 100% | High risk61 | —-0.030 |
| 19HB0113CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS -CABUNGAAN - LONOY ROAD LEADING TO KINAHUGAN FALLS AND LONOY SPRING, BRGY. CABUNGAAN, JAGNA, BOHOL STA. 000+800 - STA. 001+200 | Region VII | Bohol 3rd DEO | Completed | ₱9.4M | 100% | High risk60 | —-0.030 |
| 25HA0044ROAD WIDENING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0055+922 - K0057+000 | Region VII | Bohol 1st DEO | On-Going | ₱49.2M | 52% | High risk60 | —-0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18HB0156CONCRETING OF BRGY. MALBOG FMR, BRGY. MALBOG, JAGNA, BOHOL STA. 0+000.00-STA. 0+498.12 | Region VII | Bohol 3rd DEO | Completed | ₱4.8M | 100% | High risk66 | Flagged0.013 |
| 18HB0157CONCRETING OF BRGY. CANTAGAY FMR, BRGY. CANTAGAY, JAGNA, BOHOL, STA. 0+000.00 - STA. 0+793.26, STA. 0+834.96 - STA. 1+040.00, JAGNA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱9.5M | 100% | High risk78 | Flagged0.012 |
| 24HB0019ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - LOAY INTERIOR RD - K0168 + 839 - K0169 + 865 | Region VII | Bohol 3rd DEO | On-Going | ₱87.3M | 99% | High risk72 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23HB0002CONVERGENCE & SPECIAL SUPPORT PROGRAM/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT), JCT. (TER) GABAYAN-ANOLING (CANDIJAY)-INAGHUBAN-PILAR RO | Region VII | Bohol 3rd DEO | Completed | ₱84.9M | 100% | Medium risk52 | —-0.085 |
| 27 | 22HA0038CONSTRUCTION OF ROAD FROM NATIONAL HIGHWAY TO SITIO LAMAK, SITIO HANDIG AND SITIO BADIANG, BRGY. BONBON, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱48.5M | 100% | Medium risk51 | —-0.088 |
| 28 | 21HA0069CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - BENTIG - TINIBGAN - SAMPOANGON ROAD CONNECTING TAGBILARAN NORTH ROAD IN SUPPORT TO FURNITURES AND AGRIBUSINESS INDUSTRIES, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱47.2M | 100% | Medium risk51 | —-0.094 |
| 29 | 21HA0085CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - TANDAY - CORELLA PROVINCIAL ROAD CONNECTING TCSR IN SUPPORT TO ANGRIBUSINESS INDUSTRIES, CORELLA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱49M | 100% | Medium risk50 | —-0.093 |
| 30 | 23HA0071CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LABUON FLOOD CONTROL, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱51M | 100% | Medium risk50 | —-0.075 |
| 31 | 22HA0076CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY SANTO ROSARIO (ANTEQUERA) ALONG RIVER LEADING TO TUBIG DAKO LEADING TO INAMBACAN CAVE AND SPRING, STA. 000+000.00 - STA. | Region VII | Bohol 1st DEO | Completed | ₱48.9M | 100% | Medium risk50 | —-0.071 |
| 32 | 19HA0150CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF BATERIA RIVER FLOOD CONTROL (SUBA TINAGO), TINANGNAN, TUBIGON, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱47.4M | 100% | Medium risk50 | —-0.077 |
| 33 | 24GO0024CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRA STRUCTURE PROGRAM-ROLL IT) JUNCTION HERNAEZ ST. TO BANGGA VISTA ALEGRE ROAD IN SUPPORT OF MICRO FOOD PROCESSI | Negros Island Region | Bacolod City DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.090 |
| 34 | 23HB0118CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (IMPROVEMENT) OF MALBOG- BALILI-BUYOG ROAD, JAGNA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱49.4M | 100% | Medium risk48 | —-0.092 |
| 35 | 25HB0133CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (COMPLETION) OF ROAD, BRGY. BOYOAN TO BRGY ABIHILAN, CAND | Region VII | Bohol 3rd DEO | On-Going | ₱48.5M | 48% | Medium risk48 | —-0.043 |
| 36 | 24HB0142CONVERGENCE & SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, BENTIG, CALINGINAN SUR, SEVILLA, BOHOL, STA.0 | Region VII | Bohol 3rd DEO | Completed | ₱49.4M | 100% | Medium risk48 | —-0.093 |
| 37 | 22HB0014CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY & TRADE INFRASTRUCTURE PROGRAM - ROLL-IT)-JCT. (TER) GABAYAN-ANOLING (CANDIJAY)-INA | Region VII | Bohol 3rd DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.092 |
| 38 | 22HB0035CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRURE PROGRAM-TRIP) - JCT.(TER) GABAYAN-CANAWA (CANDIJAY)-INAGHUBAN-PILAR ROAD LEADING TO CANAWA SPRING AND CAN-U | Region VII | Bohol 3rd DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.092 |
| 39 | 22HB0085CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - JCT.(TER) LUNGSODAAN-TAMBONGAN-CADAPDAPAN ROAD (CANDIJAY) LEADING TO CAN-UMANTAD FALLS, | Region VII | Bohol 3rd DEO | Completed | ₱47.3M | 100% | Medium risk48 | —-0.092 |
| 40 | 22HA0057CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEM AT ALEGRIA, STA. 000+000.00 - STA. 000+625.00, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.077 |
| 41 | 18HA0078CONSTRUCTION OF WATER SUPPLY LEVEL III, BARANGAY POBLACION-ALEGRIA-CANDUMAYAO-BAANG-LIBORON-TRIPLE UNION, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱10.4M | 100% | Medium risk47 | —-0.060 |
| 42 | 19HA0005CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LIBORON FLOOD CONTROL, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱28.5M | 100% | Medium risk47 | —-0.078 |
| 43 | 25HA0023CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, CALUNASAN SRIP, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱14.6M | 100% | Medium risk47 | —-0.077 |
| 44 | 25HA0050CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS - CONSTRUCTION OF FLOOD PROTECTION DIKE, CAHAYAG CIS, TUBIGON, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱14.6M | 100% | Medium risk47 | —-0.077 |
| 45 | 24HA0062CONSTRUCTION OF ABUCAYAN NORTE FLOOD CONTROL, ABUCAYAN NORTE, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱19.5M | 100% | Medium risk47 | —-0.078 |
| 46 | 20HA0014CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION TULTUGAN FLOOD CONTROL, TULTUGAN, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱9.5M | 100% | Medium risk47 | —-0.077 |
| 47 | 19HA0074CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEM - CONSTRUCTION OF CAHAYAG FLOOD CONTROL, CAHAYAG, TUBIGON, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱19M | 100% | Medium risk47 | —-0.078 |
| 48 | 20HA0004CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF ABUCAYAN NORTE FLOOD CONTROL (PACKAGE 2), ABUCAYAN NORTE, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱17.1M | 100% | Medium risk47 | —-0.078 |
| 49 | 18HA0009CONSTRUCTION OF DPWH ANNEX BUILDING BOHOL 1ST DISTRICT ENGINEERING OFFICE, DAO, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱14.4M | 100% | Medium risk47 | —-0.093 |
| 50 | 21HB0147LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, ALICIA MUNICIPAL COLLEGE, ALICIA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱39.6M | 100% | Medium risk47 | —-0.084 |