Contractor dossier
55 projects on file, including joint ventures this contractor is part of.
Total projects
55
Total budget
₱329.2M
Average progress
94.1%
Completion rate
81.8%
Average risk score
41.5
Medium risk on average, out of 100
Flagged as unusual
1
1.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 54 | ₱309.5M | 41.3 | 0 | 95.8% |
| Region III | 1 | ₱19.7M | 53.3 | 1 | 2.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 37 | ₱199.3M | 35.3 | 1 | 96.1% |
| Roads | 12 | ₱94.3M | 40.4 | 0 | 85.7% |
| GAA 2025 SSP | 5 | ₱32.2M | 93.4 | 0 | 97.6% |
| Water Provision and Storage | 1 | ₱3.4M | 25.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DH0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MUNTING KAWAYAN, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 88% | High risk95 | —-0.003 |
| 25DH0041CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAAGAHAN, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.009 |
| 25DH0032CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.009 |
| 25DH0022CONSTRUCTION OF ROAD, BARANGAY SANTO ANGEL NORTE, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | High risk93 | —-0.033 |
| 25DH0046CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY KAYHACAT, SANTA MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱13M | 100% | High risk92 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24C00614STATE UNIVERSITIES AND COLLEGES (SUCS)-THREE STOREY HIGHER EDUCATION BUILDING (PHASE 3), PAMPANGA STATE AGRICULTURAL UNIVERSITY, PROVINCE OF PAMPANGA | Region III | Region III | On-Going | ₱19.7M | 2% | Medium risk53 | Flagged0.034 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24DH0087INSTALLATION OF ROADWAY LIGHTING STRUCTURES, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.9M | 3% | Medium risk46 | —-0.040 |
| 27 | 25DH0059CONSTRUCTION OF ROAD, BARANGAY SAN MIGUEL-BARANGAY ORIGUEL, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱9.6M | 25% | Medium risk46 | —-0.054 |
| 28 | 24DH0063INSTALLATION/ APPLICATION/CONSTRUCTION OF SIGNAGE, PAVEMENT MARKINGS, STREET LIGHTS ALONG CALAMBA-STA. CRUZ-FAMY JCT. RD K0105+500-K0105+740, PAKIL, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱8M | 100% | Medium risk46 | —-0.108 |
| 29 | 23DH0107CONSTRUCTION OF COVERED COURT AT SITIO BAGONG SIBOL, BRGY. MASICO, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9M | 100% | Medium risk44 | —-0.059 |
| 30 | 23DP0102CONSTRUCTION OF 4STY12CL, NANHAYA NATIONAL HIGH SCHOOL (PHASE 1 - 1STY2CL) | Region IV-A | Laguna 3rd DEO | Completed | ₱9.6M | 100% | Medium risk44 | —-0.061 |
| 31 | 24DH0088CONCRETING OF BRGY. TAYTAY FMR, BRGY. TAYTAY, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.056 |
| 32 | 20DH0093CONCRETING OF BRGY. MAGSAYSAY FMR, BRGY. MAGSAYSAY, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱11.6M | 100% | Medium risk42 | —-0.056 |
| 33 | 21DH0085CONCRETING OF BRGY. LONGOS TO BRGY. SAN JUAN FMR, BRGY. LONGOS AND BRGY. SAN JUAN, KALAYAAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱12.1M | 100% | Medium risk42 | —-0.055 |
| 34 | 21DH0082CONCRETING OF SITIO PAPATAHAN, BRGY. IBABA DEL NORTE FMR, BRGY. IBABA DEL NORTE, PAETE, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱12.1M | 100% | Medium risk42 | —-0.056 |
| 35 | 22DH0078CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-RAIN WATER COLLECTOR SYSTEM (9 UNITS) | Region IV-A | Laguna 1st DEO | Completed | ₱3.4M | 100% | Low risk25 | —-0.068 |
| 36 | 20DH0069CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI PURPOSE BUILDING, BRGY. MAGDALENA, MAGDALENA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.106 |
| 37 | 22DH0070COMPLETION OF MULTI PURPOSE COVERED COURT AT BARANGAY KANLURAN TALONGAN, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4M | 100% | Low risk25 | —-0.103 |
| 38 | 20DH0067CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI PURPOSE BUILDING, BRGY. SULIB, PANGIL, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.105 |
| 39 | 22DH0010CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY SAN ISIDRO, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.104 |
| 40 | 21DH0026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MAGDALO, FAMY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.104 |
| 41 | 21DH0011CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NANGUMA, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.5M | 100% | Low risk24 | —-0.105 |
| 42 | 21DH0037CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN JUAN, KALAYAAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.7M | 100% | Low risk24 | —-0.105 |
| 43 | 23DH0032REHABILITATION (COMPLETION) OF ADMINISTRATIVE/ PLANNING BUILDING, DPWH LAGUNA 1ST DEO, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.2M | 100% | Low risk24 | —-0.105 |
| 44 | 21DH0025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAYASIN, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.7M | 100% | Low risk24 | —-0.105 |
| 45 | 23DH0030CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING (COVERED COURT), PHASE 2 AT BARANGAY BUENAVISTA, MAGDALENA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2M | 100% | Low risk24 | —-0.103 |
| 46 | 24DH0036CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING (COVERED COURT) AT BARANGAY BANGCO, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱1.9M | 100% | Low risk23 | —-0.103 |
| 47 | 25DH0021INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG STA. CRUZ POB. RD K0086+233-K0087+271, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱861.8K | 100% | Low risk19 | —-0.101 |
| 48 | 25DH0020INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG CALAMBA-STA. CRUZ-FAMY JCT. RD K0086+449-K0087+452, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱785.4K | 100% | Low risk19 | —-0.101 |
| 49 | 20DH0101CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. GENERAL LUNA, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.6M | 100% | Low risk16 | —-0.059 |
| 50 | 20DH0048REHABILITATION OF EXISTING MULTI PURPOSE BUILDING BRGY. DAMBO, PANGIL, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱999.1K | 100% | Low risk16 | —-0.105 |