Contractor dossier
163 projects on file, including joint ventures this contractor is part of.
Total projects
163
Total budget
₱8.9B
Average progress
97.2%
Completion rate
91.4%
Average risk score
46.8
Medium risk on average, out of 100
Flagged as unusual
9
5.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 134 | ₱6.5B | 43.5 | 1 | 100.0% |
| Region IX | 22 | ₱1.8B | 64.9 | 8 | 79.2% |
| Region XIII | 5 | ₱357.2M | 51.4 | 0 | 100.0% |
| Region XI | 2 | ₱184M | 57.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 72 | ₱4.3B | 50.0 | 0 | 100.0% |
| Buildings and Facilities | 35 | ₱361.8M | 20.0 | 0 | 100.0% |
| Flood Control and Drainage | 30 | ₱2.4B | 56.4 | 5 | 87.2% |
| OTHER | 17 | ₱1.7B | 76.9 | 4 | 95.7% |
| Bridges | 6 | ₱142M | 45.6 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱7.4M | 18.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23J00140CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 2, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 88% | High risk84 | Flagged0.036 |
| 22J00126PREVENTIVE MAINTENANCE - PRIMARY ROADS PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱98.6M | 76% | High risk82 | Flagged0.038 |
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | Region IX | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | Region IX | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 24JA0174CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER (TETUAN SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱96.6M | 0% | High risk80 | Flagged0.052 |
| 22K00371OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS, SAYRE HIGHWAY K1480 + 940.000 - K1482 + 048.776, K1482 + 911.490 - K1483 +661.420, K1512 + 000 - K1515 + 000 | Region X | Region X | Completed | ₱142.6M | 100% | High risk79 | —-0.011 |
| 22KA0088OFF-CARRIAGEWAY IMPROVEMENT ALONG JCT SH-AGLAYAN-ALANIB-TICALAAN RD (AGLAYAN-BASAK)-K1528+000 - K1536+507, LANTAPAN, BUKIDNON, BANTUANON-BACLAYON, LANTAPAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.021 |
| 23K00185CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MANTICAO RIVER (DOWNSTREAM OF MANTICAO BRIDGE) MANTICAO, MISAMIS ORIENTAL | Region X | Region X | Completed | ₱198M | 100% | High risk79 | —-0.009 |
| 22K00370ROAD WIDENING-TERTIARY ROADS, JCT. SH AGLAYAN-ZAMBOANGUITA RD.K1520 + 988.549-K1521 + 284.490, K1521 + 325.000-K1522 + 504.000, K1522 + 890.00, K1522 +943.750, K1522+977.000 - K1523 +847.402, K1542 + 500-K1544 + 500 | Region X | Region X | Completed | ₱116M | 100% | High risk78 | —-0.016 |
| 18K00257CLUSTER 57 CONST./IMPRVT. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES & PAVING OF | Region X | Region X | Completed | ₱262.7M | 100% | High risk78 | Flagged0.000 |
| 23J00139CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 1, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 62% | High risk78 | Flagged0.025 |
| 22NG0091CONSTRUCTION OF ROAD, BARANGAY CAMP EDUARD, ALEGRIA, SURIGAO DEL NORTE / BARANGAY CAMP EDUARD, ALEGRIA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱77.2M | 100% | High risk77 | —-0.012 |
| 23J00138CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.3M | 61% | High risk76 | Flagged0.005 |
| 24J00017CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (TUGBUNGAN SECTION) PHASE II, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱145.4M | 20% | High risk76 | Flagged0.010 |
| 24J00018CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (TUGBUNGAN SECTION) PHASE III, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱145.4M | 72% | High risk76 | —-0.004 |
| 22KB0083CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF MANUTO BRIDGE (B01380MN) ALONG BUKIDNON-DAVAO CITY ROAD, MANUTO BRIDGE, BRGY SALAWAGAN, QUEZON, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱67.6M | 100% | High risk75 | —-0.030 |
| 22KB0086CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF APOLANG BRIDGE (B01389MN) ALONG KIBAWE-KADINGILAN-KALILANGAN ROAD, APOLANG BRIDGE, BRGY WEST KIBAWE, KIBAWE, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱57.9M | 100% | High risk75 | —-0.031 |
| 24K00034CONST. OF BY-PASS AND DIVERSION ROADS,OPOL DIVERSION ROAD(OPOL-CANITOAN), PACKAGE 17, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱47.8M | 100% | High risk75 | —-0.006 |
| 22KB0072CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF RAWARI BRIDGE (B01384MN) ALONG BUKIDNON-DAVAO CITY ROAD, RAWARI BRIDGE, SITIO RAWARI, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱67.6M | 100% | High risk75 | —-0.026 |
| 22KB0073CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF SAN MIGUEL BRIDGE (B01432MN) ALONG MARAMAG-MARADUGAO ROAD, SAN MIGUEL BRIDGE, SAN MIGUEL, MARAMAG, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱67.6M | 100% | High risk75 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | Region IX | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | Region IX | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 24JA0174CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER (TETUAN SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱96.6M | 0% | High risk80 | Flagged0.052 |
| 22J00126PREVENTIVE MAINTENANCE - PRIMARY ROADS PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱98.6M | 76% | High risk82 | Flagged0.038 |
| 23J00140CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 2, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 88% | High risk84 | Flagged0.036 |
| 23J00139CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 1, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.2M | 62% | High risk78 | Flagged0.025 |
| 24J00017CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (TUGBUNGAN SECTION) PHASE II, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱145.4M | 20% | High risk76 | Flagged0.010 |
| 23J00138CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱143.3M | 61% | High risk76 | Flagged0.005 |
| 18K00257CLUSTER 57 CONST./IMPRVT. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES & PAVING OF | Region X | Region X | Completed | ₱262.7M | 100% | High risk78 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21JG0063ROAD WIDENING - PRIMARY ROADS PAGADIAN CITY - ZAMBOANGA CITY RD - K1696 + 183 - K1699 + 052, TIGBAO, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱93.1M | 100% | High risk69 | —-0.059 |
| 27 | 18L00141CONSTRUCTION OF ROAD NETWORK INCLUDING FACILITIES, UP MINDANAO, MINTAL, DAVAO CITY | Region XI | Region XI | Completed | ₱139.3M | 100% | High risk65 | —-0.068 |
| 28 | 20J00011ROAD WIDENING - TERTIARY ROAD - JCT. DUMALINAO - MARGOSATUBIG ROAD | Region IX | Region IX | Completed | ₱89.1M | 100% | High risk64 | —-0.070 |
| 29 | 24K00179CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IPONAN RIVER, PACKAGE 10, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱148M | 100% | High risk63 | —-0.023 |
| 30 | 24K00196CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANTICAO RIVER (DOWNSTREAM OF MANTICAO BRIDGE), MANTICAO, MISAMIS ORIENTAL | Region X | Region X | On-Going | ₱195.9M | 100% | High risk63 | —-0.016 |
| 31 | 20K00392CONST. OF FLOOD CONTROL STRUCTURE ALONG SAGUIARAN RIVER PACKAGE 4, KALILANGAN, BUKIDNON | Region X | Region X | Completed | ₱139.9M | 100% | High risk63 | —-0.057 |
| 32 | 22J00039NETWORK DEVELOPMENT PROGRAM ROAD WIDENING - PRIMARY ROADS PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | Region IX | Completed | ₱69.9M | 100% | High risk63 | —-0.076 |
| 33 | 19K00080ROAD WIDENING, BARANDIAS-DOMINOROG ROAD, K1600+485 - K1605+292, BUKIDNON | Region X | Region X | Completed | ₱157M | 100% | High risk62 | —-0.069 |
| 34 | 18K00141ROAD WIDENING OF GINGOOG-CLAVERIA-VILLANUEVA RD.-K1327+000-K1330+360,K1330+440-K1333+000,K1340+600-K | Region X | Region X | Completed | ₱146.7M | 100% | High risk62 | —-0.071 |
| 35 | 22JG0014PAVING OF UNPAVED ROADS - TERTIARY ROADS ALONG ZAMBOANGA DEL SUR COASTAL RD - (S01186MN), V. SAGUN, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱58.6M | 100% | High risk61 | —-0.065 |
| 36 | 22K00029CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAGUIARAN RIVER, PACKAGE 5, KALILANGAN, BUKIDNON (STA.1+830.00-STA.2+355.956) | Region X | Region X | Completed | ₱96.5M | 100% | High risk61 | —-0.063 |
| 37 | 24KB0034CONSTRUCTION OF REVETMENT, DOWNSTREAM AND UPSTREAM OF STEEL BRIDGE ALONG PULANGI RIVER, BARANGAY NATULONGAN, KIBAWE, BUKIDNON PACKAGE 3 | Region X | Bukidnon 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.063 |
| 38 | 21K00195CONST. OF BYPASS & DIVERSION ROADS, CONST. OF CDO-NEW WESTERN DIVERSION ROAD (CANITO-AN-CDO COASTAL ROAD SECTION) PACKAGE 7 | Region X | Region X | Completed | ₱130.6M | 100% | Medium risk58 | —-0.063 |
| 39 | 20K00011CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD FROM CAGAYAN DE ORO CITY LEADING TO ULTRA WINDS MOUNTAIN RESORT, PUALAS, BAUNGON, BUKIDNON | Region X | Region X | Completed | ₱126.9M | 100% | Medium risk57 | —-0.065 |
| 40 | 23K00342CONSTRUCTION OF ROAD, CDOC-ILIGAN HINTERLAND ROAD, JCT. CDO-CAMP KIBARITAN/DANSOLIHON-JCT. BCIR/LAGUINDINGAN AIRPORT ROAD EXTENSION SECTION 2, CAGAYAN DE ORO CITY | Region X | Region X | Completed | ₱95.5M | 100% | Medium risk57 | —-0.078 |
| 41 | 18K00091ROAD WIDENING OF KALILANGAN-LAMPANUSAN RD-K1600+(-330)-K1603+056,K1603+083-K1603+1425, BUKIDNON | Region X | Region X | Completed | ₱111.7M | 100% | Medium risk57 | —-0.078 |
| 42 | 19KB0023ROAD WIDENING ON SPECIFIC LOCATION ALONG BUKIDNON-DAVAO CITY ROAD, K1614+000-K1615+238, K1615+280-K1616+558, SINUDA, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱96.5M | 100% | Medium risk57 | —-0.074 |
| 43 | 20KB0042REHAB/RECONST OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BUKIDNON-DAVAO CITY ROAD, K1607+250-K1607+310, K1607+585-K1607+700, PALACAPAO, QUEZON, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱96.5M | 100% | Medium risk57 | —-0.079 |
| 44 | 18KC0006CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD LEADING TO DAHILAYAN ADVENTURE PARK, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.082 |
| 45 | 19K00033CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, OPOL DIVERSION ROAD (OPOL-CANITOAN), (CANITOAN, CAGAYAN DE ORO SECTION), CAGAYAN DE ORO CITY | Region X | Region X | Completed | ₱104.3M | 100% | Medium risk56 | —-0.076 |
| 46 | 18K00139CONST. OF BYPASS/DIVERSION RD., OPOL DIVERSION RD. (OPOL-CANITOAN), INCL. ROW, MISAMIS ORIENTAL | Region X | Region X | Completed | ₱92.1M | 100% | Medium risk55 | —-0.082 |
| 47 | 22JG0044ROAD WIDENING ALONG JCT. DUMALINAO - MARGOSATUBIG RD - K1686+130 - K1686+1738, GUIPOS, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱30.4M | 100% | Medium risk55 | —-0.081 |
| 48 | 22JG0043ROAD WIDENING ALONG PAGADIAN CITY - ZAMBOANGA CITY RD - K1716+350 - K1718+000, DIPLO, KUMALARANG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱44.6M | 100% | Medium risk55 | —-0.071 |
| 49 | 22JG0048CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG NRJ BOGAYO-KITAAN DAGAT-SUMINALOM RD, KUMALARANG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | On-Going | ₱30.4M | 100% | Medium risk55 | —-0.030 |
| 50 | 22JG0013ROAD WIDENING - PRIMARY ROADS ALONG PAGADIAN CITY - ZAMBOANGA CITY RD - K1708+660 - K1710+000, KUMALARANG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱31M | 100% | Medium risk55 | —-0.079 |