Contractor dossier
142 projects on file, including joint ventures this contractor is part of.
Total projects
142
Total budget
₱2.7B
Average progress
98.9%
Completion rate
95.8%
Average risk score
20.7
Low risk on average, out of 100
Flagged as unusual
4
2.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 142 | ₱2.7B | 20.7 | 4 | 98.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 76 | ₱518.3M | 10.1 | 0 | 100.0% |
| Roads | 26 | ₱891.9M | 29.2 | 0 | 100.0% |
| Bridges | 20 | ₱524.8M | 28.0 | 0 | 100.0% |
| Flood Control and Drainage | 12 | ₱490.5M | 36.0 | 1 | 99.7% |
| Water Provision and Storage | 4 | ₱14.6M | 15.6 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱49.4M | 93.5 | 1 | 12.5% |
| GAA 2025 OO-1 | 1 | ₱32.2M | 91.0 | 1 | 36.4% |
| GAA 2025 OO-2 | 1 | ₱144.6M | 91.0 | 0 | 100.0% |
| OTHER | 1 | ₱54.7M | 79.2 | 1 | 96.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MF0024COMPLETION OF MULTI PURPOSE BUILDING (AMPITHEATER BUILDING), BARANGAY KALAWAG II, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱49.4M | 13% | High risk93 | Flagged0.042 |
| 25MC0011CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PACO - ROXAS - ARAKAN VALLEY - JCT DAVAO - BUKIDNON RD - K1642 + 416 - K1642 + 546 | Region XII | Cotabato 2nd DEO | On-Going | ₱32.2M | 36% | High risk91 | Flagged0.021 |
| 25MF0009CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, ALA RIVER, TAGA SECTION - UPSTREAM (L/S),LAMBAYONG, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱144.6M | 100% | High risk91 | —-0.002 |
| 24MC0024ROAD WIDENING ALONG PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1645+ 570 - K1646+413, ANTIPAS, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱54.7M | 96% | High risk79 | Flagged0.005 |
| 24M00073CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER (PHASE IV), STA. 44+186.63 - STA. 44+611.63, BARANGAY ALEGRIA, PRES. ROXAS, COTABATO | Region XII | Region XII | On-Going | ₱96M | 96% | High risk67 | Flagged0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MF0024COMPLETION OF MULTI PURPOSE BUILDING (AMPITHEATER BUILDING), BARANGAY KALAWAG II, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱49.4M | 13% | High risk93 | Flagged0.042 |
| 25MC0011CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PACO - ROXAS - ARAKAN VALLEY - JCT DAVAO - BUKIDNON RD - K1642 + 416 - K1642 + 546 | Region XII | Cotabato 2nd DEO | On-Going | ₱32.2M | 36% | High risk91 | Flagged0.021 |
| 24MC0024ROAD WIDENING ALONG PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1645+ 570 - K1646+413, ANTIPAS, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱54.7M | 96% | High risk79 | Flagged0.005 |
| 24M00073CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER (PHASE IV), STA. 44+186.63 - STA. 44+611.63, BARANGAY ALEGRIA, PRES. ROXAS, COTABATO | Region XII | Region XII | On-Going | ₱96M | 96% | High risk67 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24MF0004KIDAPAWAN-ALLAH JUNCTION RD - K1679 +359 - K1680 + 105, K1680 + 152 - K1680 + 349 | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱25.3M | 100% | Low risk28 | —-0.050 |
| 27 | 18MH0069REHABILITATION OF PAVED ROAD ALONG AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI ROAD, K1946+000 - K1946+503 KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱14.1M | 100% | Low risk28 | —-0.089 |
| 28 | 23MF0003KIDAPAWAN-ALLAH JUNCTION RD - K1673 + 935 - K1674 + 959, K1675 + 340 - K1676 + 095 | Region XII | Sultan Kudarat 1st DEO | Completed | ₱30.2M | 100% | Low risk27 | —-0.078 |
| 29 | 19MF0023ROAD WIDENING ALONG KIDAPAWAN - ALLAH JUNCTION ROAD, K1675 + 480 - K1676 + 777, TACURONG CITY, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱33.9M | 100% | Low risk27 | —-0.088 |
| 30 | 25MF0021CONSTRUCTION OF ROAD, BARANGAY KALAWAG II, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱13.7M | 100% | Low risk27 | —-0.089 |
| 31 | 23MF0004KIDAPAWAN-ALLAH JUNCTION RD - K1680 + 153.60 - K1680 + 832, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱21.4M | 100% | Low risk27 | —-0.089 |
| 32 | 23MF0051CONSTRUCTION OF MULTI-PURPOSE BUILDING, SULTAN KUDARAT CONVENTION CENTER, BRGY. EJC MONTILLA, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱19.8M | 100% | Low risk27 | —-0.084 |
| 33 | 23MF0060CONSTRUCTION OF MULTI PURPOSE BUILDING (SENATOR RAMON REVILLA, SR. AMPITHEATER), PROVINCIAL GOVERNMENT SITE, BRGY. KALAWAG II, ISULAN, SULTAN KUDARAT (PHASE 2) | Region XII | Sultan Kudarat 1st DEO | Completed | ₱19.7M | 100% | Low risk27 | —-0.084 |
| 34 | 23MF0058CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL LIBRARY), PROVINCIAL CAPITOL, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱19.7M | 100% | Low risk27 | —-0.085 |
| 35 | 21MF0019SAMPAO BRIDGE (B00288MN) ALONG KIDAPAWAN - ALLAH JUNCTION ROAD, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱47.6M | 100% | Low risk27 | —-0.050 |
| 36 | 18MC0105CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER (STA.43+590-STA. 43+920 LEFT SIDE), BRGY. POBLACION, PRES. ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱39.5M | 100% | Low risk27 | —-0.074 |
| 37 | 18MC0042NRJ LEADING TO HOLY CROSS SHRINE, BRGY. NUEVA VIDA, M'LANG, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱34.3M | 100% | Low risk27 | —-0.087 |
| 38 | 23MF0009KIDAPAWAN-ALLAH JUNCTION RD - K1665 + 290 - K1666 + 284, PRESIDENT QUIRINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱11.8M | 100% | Low risk27 | —-0.089 |
| 39 | 19MC0056ROAD WIDENING ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) K1640+645 TO K1641+551), MATALAM, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱39.2M | 100% | Low risk26 | —-0.088 |
| 40 | 21MC0063ROAD WIDENING DAVAO - COTABATO RD (JCT DIGOS - COTABATO SECT) - K1611+000 - K1611+267, K1611+293 - K1611+600, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱22.5M | 100% | Low risk26 | —-0.085 |
| 41 | 20MH0080CONCRETING OF LOCAL ROAD, SITIO DINAGAAN TO UPPER ALAS-AS, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱19.8M | 100% | Low risk26 | —-0.085 |
| 42 | 18MH0038PAVING OF UNPAVED ROADS ALONG SNA-LEBAK-KALAMANSIG ROAD, K1905+185 - K1905+686; K1905+695 - K1905+734 KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱18M | 100% | Low risk26 | —-0.089 |
| 43 | 18MC0114CONSTRUCTION OF BUAL RIVER FLOOD CONTROL TULUNAN, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱29.4M | 100% | Low risk26 | —-0.073 |
| 44 | 20M00151NRJ LEADING TO HOLY CROSS SHRINE, BRGY. NUEVA VIDA, MLANG, NORTH COTABATO | Region XII | Region XII | Completed | ₱15.3M | 100% | Low risk26 | —-0.087 |
| 45 | 19MC0012CONSTRUCTION OF CONCRETE ROAD-NRJ LEADING TO HOLY CROSS SHRINE, BRGY. NUEVA VIDA, M'LANG, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱20M | 100% | Low risk26 | —-0.089 |
| 46 | 24MF0023CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BANGA RIVER (SAMPAO SECTION), ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱44.9M | 100% | Low risk26 | —-0.075 |
| 47 | 19MH0085CONSTRUCTION OF FLOOD CONTROL (ALA RIVER BASIN) ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱46.4M | 100% | Low risk25 | —-0.077 |
| 48 | 17MF0038CONSTRUCTION OF 17 UNITS RAIN WATER COLLECTION SYSTEM REIFORCED CONCRETE GROUND STORAGE TANK | Region XII | Sultan Kudarat 1st DEO | Completed | ₱3.3M | 100% | Low risk25 | —-0.029 |
| 49 | 24MF0018CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ALA RIVER (D'LOTILLA - BUAL), ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱45M | 100% | Low risk25 | —-0.076 |
| 50 | 24MF0019CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ALA RIVER (IMPAO - ALLAH BRIDGE), ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱45M | 100% | Low risk25 | —-0.077 |