Contractor dossier
85 projects on file, including joint ventures this contractor is part of.
Total projects
85
Total budget
₱2.5B
Average progress
92.6%
Completion rate
76.5%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
3
3.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 81 | ₱2.5B | 51.6 | 3 | 92.3% |
| Region IV-A | 4 | ₱51.3M | 45.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 39 | ₱1.6B | 51.5 | 0 | 90.2% |
| Buildings and Facilities | 30 | ₱300.7M | 48.1 | 0 | 96.3% |
| Flood Control and Drainage | 8 | ₱467.8M | 51.2 | 0 | 99.2% |
| Water Provision and Storage | 3 | ₱21.9M | 43.0 | 0 | 100.0% |
| OTHER | 2 | ₱68.8M | 85.9 | 2 | 73.5% |
| Bridges | 2 | ₱43M | 51.6 | 0 | 97.2% |
| GAA 2025 OO-1 | 1 | ₱35.3M | 93.2 | 1 | 31.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00211ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0402+874-K0404+000, K0404+202-K0404+352, K0404+586-K0405+856, LIBMANAN, CAMARINES SUR (2ND LE | Region V | Region V | On-Going | ₱35.3M | 31% | High risk93 | Flagged0.007 |
| 24F00437CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-LGU HOSPITALS-EASTERN BICOL MEDICAL CENTER, CATANDUANES, VIRAC, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱29.4M | 47% | High risk87 | Flagged0.051 |
| 24FN0093REHABILITATION OF DISASTER-RELATED INFRASTRACTURE AND OTHER FACILITIES - RELEASE OF FUNDS FOR THE REPAIR/REHABILITATION AND MAINTENANCE OF NABUA-BALATAN ROAD, ROAD SLIP K0489+000 - K0489+200 (R/S) | Region V | Camarines Sur 5th DEO | Completed | ₱39.4M | 100% | High risk85 | Flagged0.010 |
| 20F00060LOCAL PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONSTRUCTION/IMPROVEMENT OF MANAPO RIVER FLOOD MITIGATION STRUCTURES (SALVACION- | Region V | Region V | On-Going | ₱140.8M | 93% | High risk70 | —-0.008 |
| 20F00018OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAMARINES SUR EXPRESSWAY PROJECT(SAN FERNANDO-PILI), PACKAGE 3, CAMARINES SUR, MANAPAO-MATAOROC, MINALABAC, CAMARINES SUR (2ND LEGI | Region V | Region V | Completed | ₱193M | 100% | High risk69 | —-0.059 |
| 22F00051OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 5), PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱193M | 100% | High risk69 | —-0.060 |
| 22F00050OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 4), SAN FERNANDO-MINALABAC, CAMARINES SUR(2ND LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱482.5M | 100% | High risk68 | —-0.052 |
| 24F00131ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0476+979-K0477+097, BATO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱5.4M | 0% | High risk67 | —-0.008 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24F00437CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-LGU HOSPITALS-EASTERN BICOL MEDICAL CENTER, CATANDUANES, VIRAC, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱29.4M | 47% | High risk87 | Flagged0.051 |
| 24FN0093REHABILITATION OF DISASTER-RELATED INFRASTRACTURE AND OTHER FACILITIES - RELEASE OF FUNDS FOR THE REPAIR/REHABILITATION AND MAINTENANCE OF NABUA-BALATAN ROAD, ROAD SLIP K0489+000 - K0489+200 (R/S) | Region V | Camarines Sur 5th DEO | Completed | ₱39.4M | 100% | High risk85 | Flagged0.010 |
| 25F00211ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0402+874-K0404+000, K0404+202-K0404+352, K0404+586-K0405+856, LIBMANAN, CAMARINES SUR (2ND LE | Region V | Region V | On-Going | ₱35.3M | 31% | High risk93 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21FE0017OO1: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PAMPLONA-SAN FERNANDO BYPASS ROAD, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱28.5M | 100% | Medium risk52 | —-0.065 |
| 27 | 22FE0062OO1: NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - MILAOR-MINALABAC-PILI RD - K0435 + 140 - K0435 + 979 | Region V | Camarines Sur 2nd DEO | Completed | ₱22M | 100% | Medium risk52 | —-0.100 |
| 28 | 23FE0038CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - DALIPAY-SAN ANTONIO ROAD LEADING TO IT-BPO INDUSTRY, MILAOR, CAMARINES | Region V | Camarines Sur 2nd DEO | Completed | ₱19.4M | 100% | Medium risk52 | —-0.100 |
| 29 | 22FE0049CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CABUGAO ROAD, BRGY. CABUGAO, MILAOR, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱19.2M | 100% | Medium risk52 | —-0.101 |
| 30 | 22FE0045CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CAPUCNASAN ROAD, BRGY. CAPUCNASAN, MILAOR, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱19.2M | 100% | Medium risk52 | —-0.101 |
| 31 | 21FE0016LP: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - REHABILITATION OF SITIO TINAGO - CENTRO, CAMBALIDIO ROAD, BARANGAY CAMBALIDIO, LIBMANAN, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱24M | 100% | Medium risk52 | —-0.100 |
| 32 | 20FE0001OO1:ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS-DANAO-PASACAO RD-K0419+-632-K0419+242 | Region V | Camarines Sur 2nd DEO | Completed | ₱16.4M | 100% | Medium risk52 | —-0.099 |
| 33 | 24F00080ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0423+584-K0423+834, PAMPLONA, CAMARINES SUR (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱9.6M | 81% | Medium risk52 | —-0.066 |
| 34 | 21FE0008CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - DALIPAY-SAN ANTONIO ROAD LEADING TO IT-BPO INDUSTRY, MILAOR, CAMARINES S | Region V | Camarines Sur 2nd DEO | Completed | ₱4.8M | 100% | Medium risk52 | —-0.097 |
| 35 | 21FE0007CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - SAN ISIDRO-BAHAO ROAD LEADING TO BAHAO PORT, LIBMANAN, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱9.5M | 100% | Medium risk51 | —-0.099 |
| 36 | 25FE0001CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - DALIPAY-SAN ANTONIO ROAD LEADING TO IT-BPO INDUSTRY, MILAOR, CAMARINES S | Region V | Camarines Sur 2nd DEO | On-Going | ₱12.1M | 100% | Medium risk51 | —-0.076 |
| 37 | 23FE0083CSSP: BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF ROAD, BRGY. MALINAO, LIBMANAN, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱12.3M | 100% | Medium risk51 | —-0.101 |
| 38 | 23FE0084CSSP: BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF ROAD, BRGY. BAGAMELON, LIBMANAN, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱12.3M | 100% | Medium risk51 | —-0.099 |
| 39 | 24FH0021BRIDGE - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, TOKIO BRIDGE ALONG CATANDUANES CIRCUMFRENTIAL ROAD | Region V | Catanduanes DEO | On-Going | ₱14.5M | 94% | Medium risk51 | —-0.031 |
| 40 | 23FE0107CSSP: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR LEVEL 2 WATER SYSTEM AT BRGY. SAN RAMON, PAMPLONA, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱9.8M | 100% | Medium risk51 | —-0.065 |
| 41 | 23FE0110CSSP: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR LEVEL 2 WATER SYSTEM AT BRGY. USON-PADLOS, LIBMANAN, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱9.8M | 100% | Medium risk51 | —-0.065 |
| 42 | 23FD0029CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG LIBMANAN RIVER, BRGY. TAISAN SECTION, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱72.4M | 100% | Medium risk51 | —-0.082 |
| 43 | 24FD0020CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAGUIO, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.095 |
| 44 | 23FD0032CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG LIBMANAN RIVER, BRGY. TARA SECTION, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱72.4M | 100% | Medium risk50 | —-0.082 |
| 45 | 24FD0021CONSTRUCTION OF MULTI-PURPOSE BUILDING, SIMEON TYCANGCO NATIONAL HIGH SCHOOL, BARANGAY APAD, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.098 |
| 46 | 24FD0018CONSTRUCTION OF MULTI-PURPOSE BUILDING, BULAWAN JR., LUPI, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.098 |
| 47 | 23FE0095CSSP:BASIC INFRASTRUCTURE PROGRAM-EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES-CONSTRUCTION OF MULTI-PURPOSE BUILDING(EVACUATION CENTER),LGU COMPOUND,ZONE 2,BRGY TAMBO,PAMPLONA, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱14.8M | 100% | Medium risk49 | —-0.098 |
| 48 | 23F00055CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BAAO, CAMARINES SUR(PHASE 2), | Region V | Region V | On-Going | ₱4.8M | 47% | Medium risk48 | —-0.033 |
| 49 | 23FE0021(CLUSTERED PROJECTS) CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - A. CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN RAMON, PAMPLONA, CAMARINES SUR AND B. CONSTRUCTION OF MULTI-PURPOSE B | Region V | Camarines Sur 2nd DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.098 |
| 50 | 23FE0012CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SALVACION, PASACAO, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.098 |