Contractor dossier
80 projects on file, including joint ventures this contractor is part of.
Total projects
80
Total budget
₱2.3B
Average progress
99.9%
Completion rate
97.5%
Average risk score
32.7
Medium risk on average, out of 100
Flagged as unusual
1
1.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 78 | ₱2.1B | 32.0 | 0 | 100.0% |
| Region XI | 2 | ₱182.5M | 59.9 | 1 | 96.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 37 | ₱1.3B | 37.4 | 1 | 99.8% |
| Buildings and Facilities | 23 | ₱88.4M | 18.7 | 0 | 100.0% |
| Flood Control and Drainage | 18 | ₱857.5M | 39.7 | 0 | 100.0% |
| Bridges | 1 | ₱6M | 52.2 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱9.8M | 34.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17CF0176NETWORK DEVELOPMENT OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE - TERTIARY, GAPAN - FORT MAGSAYSAY RD, K0105+600.90 - K0106+091, K0116+688 - K0118+725, K0118+841- K0119+850 | Region III | Nueva Ecija 2nd DEO | Completed | ₱22.2M | 100% | High risk67 | —-0.070 |
| 20CF0046ASSET PRESERVATION -REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - BANGAD FORT MAGSAYSAY ROAD, K0134+305 - K0135+650.60, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱23.4M | 100% | High risk66 | —-0.068 |
| 16CE0261OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, CABANATUAN CITY-CARMEN ROAD, KO129+570-KO130+000; KO135+542-KO135+941; KO138+000-KO141+000 | Region III | Nueva Ecija 1st DEO | Completed | ₱34.1M | 100% | High risk65 | —-0.069 |
| 17CF0064NETWORK DEVELOPMENT IMPROVEMENT/WIDENING OF NATIONAL ROAD ALONG NUEVA ECIJA-AURORA ROAD, K0120 + 474.90-K0121+597.00,K0136+748.14-K0137+827.65 | Region III | Nueva Ecija 2nd DEO | Completed | ₱31.6M | 100% | High risk65 | —-0.068 |
| 23LA0123CONSTRUCTION OF DRAINAGE STRUCTURE ALONG SURIGAO-DAVAO COASTAL ROAD (S01376MN), DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | On-Going | ₱94.8M | 99% | High risk64 | Flagged0.028 |
| 16CE0281CONSTRUCTION OF REVETMENT, BRGY. TABULAC, SAN JOSE CITY, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱27.9M | 100% | High risk64 | —-0.061 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23CE0025ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, NUEVA ECIJA - PANGASINAN RD K0146+000 - K0146+403, K0148+012 - K0148+850 | Region III | Nueva Ecija 1st DEO | Completed | ₱53.9M | 100% | Medium risk36 | —-0.101 |
| 27 | 21CE0062NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ALIAGA - GUIMBA DIVERSION ROAD, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱48M | 100% | Medium risk35 | —-0.102 |
| 28 | 20CE0086NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ALIAGA - GUIMBA DIVERSION ROAD, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱48.8M | 100% | Medium risk35 | —-0.101 |
| 29 | 22CE0009CONSTRUCTION OF ROAD IN BARANGAYS NAGPANDAYAN TO AGCANO, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱48.9M | 100% | Medium risk35 | —-0.101 |
| 30 | 18CF0066CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF SLOPE PROTECTION ALONG PAMPANGA RIVER FLOOD CONTROL, PALAYAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱47.5M | 100% | Medium risk35 | —-0.091 |
| 31 | 23CF0113CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. COMMUNAL, CABANATUAN, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱9.8M | 100% | Medium risk35 | —-0.068 |
| 32 | 21CF0016CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL COMPOUND), BARANGAY III, LAUR, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.104 |
| 33 | 22CE0093CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CASSANOVA CREEK, BRGY. NAGPANDAYAN, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱67.6M | 100% | Medium risk34 | —-0.084 |
| 34 | 19CF0131CONCRETING OF PULONG UWAY LOCAL ROAD (PHASE I), PALAYAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱43.9M | 100% | Medium risk33 | —-0.102 |
| 35 | 20CE0186CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BRGY. PUNCAN, CARRANGLAN (ALONG TALAVERA RIVER), NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱19M | 100% | Medium risk33 | —-0.087 |
| 36 | 23CF0024ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - NUEVA ECIJA-AURORA RD - K0119+460.00-K0120+020.00, K0124+225.70-K0124+600.00, K0126+247.00-K0126+297.70, K0126+769.70-K0126+827.70, K0127+067.70-K0127+134.40, K0127+210.40-K0127+338.7 | Region III | Nueva Ecija 2nd DEO | Completed | ₱30.6M | 100% | Medium risk33 | —-0.103 |
| 37 | 22CF0047OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - JCT TABLANG - GABALDON RD - K0137+811 - K0138+173, K0138+271 - K0139+994, K0140+678 - K0140+684, K0146+075 - K0147+305 | Region III | Nueva Ecija 2nd DEO | Completed | ₱21.9M | 100% | Medium risk32 | —-0.104 |
| 38 | 23CF0104CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) PHASE 1, BRGY. IMELDA, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.104 |
| 39 | 22CE0160NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LZ) K0140+994 - K0141+423 | Region III | Nueva Ecija 1st DEO | Completed | ₱28.8M | 100% | Medium risk32 | —-0.101 |
| 40 | 23CF0056CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ISLA, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱5M | 100% | Medium risk32 | —-0.106 |
| 41 | 22CF0097CONSTRUCTION OF ABUNDO COMPLEX ROAD (PHASE 1), SPECIAL FORCES REGIMENT (AIRBORNE) PA, FORT RAMON MAGSAYSAY, PALAYAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱14.7M | 100% | Medium risk32 | —-0.105 |
| 42 | 20CE0177CONCRETING OF LOCAL ROAD (PHASE 2), BRGY. WEST POBLACION, PANTABANGAN, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱12.4M | 100% | Medium risk32 | —-0.103 |
| 43 | 17CE0144CONSTRUCTION OF MULTI-PURPOSE BUILDING, AGUPALO ESTE, LUPAO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱1.9M | 100% | Medium risk31 | —-0.072 |
| 44 | 21CF0043CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CORONEL RIVER FLOOD CONTROL, STA. 0+000-STA.0+800.00, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱35.9M | 100% | Medium risk31 | —-0.090 |
| 45 | 20CF0068CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG PAMPANGA RIVER, BRGY. PINAGBAYANAN, LAUR, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱19.4M | 100% | Medium risk31 | —-0.092 |
| 46 | 22CE0111NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - MUÑOZ - LUPAO RD K0164+382 - K0164+529 | Region III | Nueva Ecija 1st DEO | Completed | ₱8.9M | 100% | Medium risk31 | —-0.103 |
| 47 | 20CF0117CONCRETING OF ROAD, BRGY. BAGTING, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱7.3M | 100% | Medium risk31 | —-0.104 |
| 48 | 20CF0118CONCRETING OF ROAD, BRGY. BAGONG SIKAT, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱8.4M | 100% | Medium risk31 | —-0.104 |
| 49 | 22CF0058ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - VALDEFUENTE - FORTALEZA RD - K0120+(-857.00)-K0120+790.00 | Region III | Nueva Ecija 2nd DEO | Completed | ₱12.8M | 100% | Medium risk30 | —-0.105 |
| 50 | 19CF0049CONSTRUCTION OF CONCRETE PAVEMENTS, MALATE, PALAYAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk30 | —-0.100 |