Contractor dossier
45 projects on file, including joint ventures this contractor is part of.
Total projects
45
Total budget
₱2.5B
Average progress
87.3%
Completion rate
66.7%
Below 70%
Average risk score
51.2
Medium risk on average, out of 100
Flagged as unusual
6
13.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 40 | ₱2.4B | 51.8 | 5 | 87.0% |
| Region IV-A | 3 | ₱56.9M | 46.1 | 0 | 100.0% |
| National Capital Region | 2 | ₱35.6M | 47.4 | 1 | 73.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 24 | ₱1.2B | 45.4 | 0 | 88.1% |
| Buildings and Facilities | 14 | ₱851.3M | 46.2 | 1 | 82.0% |
| OTHER | 4 | ₱251.8M | 78.4 | 4 | 97.1% |
| GAA 2025 OO-1 | 3 | ₱176.5M | 84.6 | 1 | 91.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EA0077ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG-BALANACAN PORT RD - K0008 + (-147) - K0009 + 000, K0009 + 585 - K0010 + 228 | Region IV-B | Marinduque DEO | On-Going | ₱101M | 74% | High risk93 | Flagged0.008 |
| 25EE0062PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) SECONDARY ROADS ALONG PUERTO PRINCESA NORTH ROAD, K0115+063 - K0115+905, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱34.4M | 100% | High risk81 | —-0.012 |
| 25EE0063PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) SECONDARY ROADS ALONG ROXAS DIVERSION ROAD, K0134+(-711) - K0134+264, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱41.1M | 100% | High risk80 | —-0.013 |
| 24EA0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG - BALANACAN PORT RD - K0013+000 - K0013+168, K0013+642 - K0014+203, K0014+317 - K0015+335 | Region IV-B | Marinduque DEO | On-Going | ₱56.9M | 100% | High risk80 | Flagged0.010 |
| 24EA0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0037+687 - K0039+000 | Region IV-B | Marinduque DEO | On-Going | ₱75M | 100% | High risk79 | Flagged0.004 |
| 24EA0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0000+000 - K0001+000, K0003+264 - K0004+000, K0027+786-K0028+930 | Region IV-B | Marinduque DEO | On-Going | ₱80.7M | 96% | High risk79 | Flagged0.011 |
| 24EE0128PACKAGE III-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS:1. CONSTRUCTION OF ROAD, ZONE IV. BRGY. ITANGIL, DUMARAN2. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM NATIONAL HIGHWAY LEADING TO DULI BEACH, EL NIDO3. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LE | Region IV-B | Palawan 1st DEO | On-Going | ₱39.2M | 92% | High risk76 | Flagged0.015 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21O00138CONSTRUCTION OF MANDAMUS OFFICE | National Capital Region | National Capital Region | On-Going | ₱30.7M | 47% | Medium risk47 | Flagged0.021 |
| 24EE0128PACKAGE III-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS:1. CONSTRUCTION OF ROAD, ZONE IV. BRGY. ITANGIL, DUMARAN2. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM NATIONAL HIGHWAY LEADING TO DULI BEACH, EL NIDO3. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LE | Region IV-B | Palawan 1st DEO | On-Going | ₱39.2M | 92% | High risk76 | Flagged0.015 |
| 24EA0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0000+000 - K0001+000, K0003+264 - K0004+000, K0027+786-K0028+930 | Region IV-B | Marinduque DEO | On-Going | ₱80.7M | 96% | High risk79 | Flagged0.011 |
| 24EA0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG - BALANACAN PORT RD - K0013+000 - K0013+168, K0013+642 - K0014+203, K0014+317 - K0015+335 | Region IV-B | Marinduque DEO | On-Going | ₱56.9M | 100% | High risk80 | Flagged0.010 |
| 25EA0077ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG-BALANACAN PORT RD - K0008 + (-147) - K0009 + 000, K0009 + 585 - K0010 + 228 | Region IV-B | Marinduque DEO | On-Going | ₱101M | 74% | High risk93 | Flagged0.008 |
| 24EA0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0037+687 - K0039+000 | Region IV-B | Marinduque DEO | On-Going | ₱75M | 100% | High risk79 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 20DH0008ROAD WIDENING ALONG CALAMBA-STA. CRUZ-FAMY JCT. ROAD (S06099LZ), K0105 + 894 TO K0106 + 464, PAKIL, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱27.6M | 100% | Medium risk46 | —-0.093 |
| 27 | 20DH0010ROAD WIDENING ALONG MAJAYJAY-LUCBAN ROAD (S01679LZ), K0121 + 810 TO K0122 + 259, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱17.9M | 100% | Medium risk46 | —-0.106 |
| 28 | 20DH0012PREVENTIVE MAINTENANCE ALONG KALAYAAN POBLACION ROAD CHAINAGE 000, CHAINAGE 304, CHAINAGE 311-CHAINAGE 889, KALAYAAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱11.4M | 100% | Medium risk46 | —-0.109 |
| 29 | 23EE0071PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG PUERTO PRINCESA NORTH ROAD, K0211+(-700)-K0211+786 TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱48.8M | 100% | Medium risk45 | —-0.073 |
| 30 | 24EE0147PREVENTIVE MAINTENANCE (ASPHALT OVERLAY)-SECONDARY ROADS ALONG PUERTO PRINCESA NORTH ROAD, K0199+000 - K0200+435 TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱50.4M | 100% | Medium risk45 | —-0.072 |
| 31 | 23EG0037CONSTRUCTION OF DPWH PALAWAN 3RD DEO ANNEX BUILDING, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱57.9M | 100% | Medium risk45 | —-0.055 |
| 32 | 21E00023CONSTRUCTION OF BUILDING OF PRESIDENTIAL MANAGEMENT STAFF (PMS)-OFFICE OF THE PRESIDENT (OP) INTEGRATED OPERATIONS AND SERVICES CONTINUITY (IOSC) IN BARANGAY STA. MONICA, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | Completed | ₱48.2M | 100% | Medium risk43 | —-0.057 |
| 33 | 23EE0070PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG PUERTO PRINCESA NORTH ROAD, K0082+(-216)-K0082+735 ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱35.3M | 100% | Medium risk40 | —-0.072 |
| 34 | 23E00100CONSTRUCTION OF BUILDING OF PRESIDENTIAL MANAGEMENT STAFF (PMS)- OFFICE OF THE PRESIDENT (OP) INTEGRATED OPERATIONS AND SERVICE CONTINUITY (IOSC) IN BRGY. STA. MONICA, PHASE IV, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱33.5M | 29% | Medium risk40 | —-0.002 |
| 35 | 21E00068VIILP- CONSTRUCTION OF BUILDING OF PRESIDENTIAL MANAGEMENT STAFF (PMS)-OFFICE OF THE PRESIDENT (OP) INTEGRATED OPERATIONS AND SERVICE CONTINUITY (IOSC) PHASE II, BRGY. SANTA MONICA, PUERTO PRINCESA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱33.8M | 100% | Medium risk39 | —-0.065 |
| 36 | 23EE0076PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG PUERTO PRINCESA NORTH ROAD, K0113+000-K0113+332 ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱22.2M | 100% | Medium risk39 | —-0.073 |
| 37 | 23EE0069PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG ROXAS DIVERSION ROAD, K0138+ (-385)- K0138+300 ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱22.5M | 100% | Medium risk39 | —-0.074 |
| 38 | 24EG0069PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0023+760 - K0023+947, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱17.4M | 100% | Medium risk39 | —-0.070 |
| 39 | 24EG0065PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0016+000 - K0016+187, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱17.4M | 100% | Medium risk39 | —-0.073 |
| 40 | 24EG0068PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0016+650 - K0016+837, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱17.4M | 100% | Medium risk39 | —-0.073 |
| 41 | 24EG0064PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0015+807 - K0015+994, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱17.4M | 100% | Medium risk39 | —-0.073 |
| 42 | 24EG0067PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0016+400 - K0016+ 586, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱17.4M | 100% | Medium risk39 | —-0.073 |
| 43 | 24EG0066PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0016+200 - K0016+385, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱17.4M | 100% | Medium risk39 | —-0.073 |
| 44 | 22E00049CONSTRUCTION OF BUILDING OF PRESIDENTIAL MANAGEMENT STAFF (PMS) - OFFICE OF THE PRESIDENT (OP) INTEGRATED OPERATIONS AND SERVICE CONTINUITY (IOSC), BRGY. STA. MONICA, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | Completed | ₱28.9M | 100% | Medium risk39 | —-0.067 |
| 45 | 24EG0070CONSTRUCTION (COMPLETION) OF DPWH PALAWAN 3RD DEO ANNEX BUILDING, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱24.5M | 100% | Medium risk37 | —-0.067 |