- Description
- CONSTRUCTION OF LABASON RIVER CONTROL, POBLACION LABASON ZAMBOANGA DEL NORTE 3RD LD, RIGHT SIDE: BEG. OF PROJECT 0 + 000.00 END OF PROJECT 0 + 884.40 (572.88), EXCEPTION: 0 + 441.32 - 0 + 752.84, LEFT SIDE: BEG. OF PROJECT 0 + 540.00 END OF PROJECT 0 + 87
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Region IX
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2017 MFO-2
- Infrastructure year
- 2017
- Start date
- Apr 18, 2017
- Completion date
- Aug 7, 2018
- Effective end date
- Aug 7, 2018
- Duration
- 476 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- No
- Citizen reports
- 0
- Coordinates
- 8.06278, 122.51635