- Description
- OO 1: ENSURE SAFE AND RELIABLE NAT'L ROAD SYSTEM: NETWORK DEV'T: ROAD WIDENING-PRIMARY ROADS ALONG DAANG MAHARLIKA (LZ), K0309+000-K0309+467, K0314+000-K0314+208, K0317+000-K0317+245, K0335+000-K0336+000, CORDON, SAN ISIDRO, ECHAGUE, ISABELA
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Region II
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2018 OO-1
- Infrastructure year
- 2018
- Start date
- Apr 12, 2018
- Completion date
- Jun 28, 2019
- Effective end date
- Jun 28, 2019
- Duration
- 442 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 16.67742, 121.47311