- Description
- ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - PRIMARY ROADS-ASPHALT OVERLAY 100MM THK. OF PARANAQUE-SUCAT RD - K0019 + (-021) - K0019 + 000, K0019 + (-108) - K0019 + (-021), K0019 + (-155) - K0019 + (-108), K0019 + (-278) - K0019 + (-155), K0019 +
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Metro Manila 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2021 OO-1
- Infrastructure year
- 2021
- Start date
- Mar 31, 2021
- Completion date
- Jun 28, 2021
- Effective end date
- Jun 28, 2021
- Duration
- 89 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 14.45649, 121.03597