- Description
- REHABILITATION OF EXISTING BANK ALONG LUCUNG RIVER, D/S OF CUTCUT BRIDGE (LEFT AND RIGHT BANK), STA. 8+416.00 TO STA. 8+682.70 - R/S, STA. 9+030.00 TO STA. 9+227.30 - L/S, CAPAS, TARLAC
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Tarlac 2nd DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 CSSP
- Infrastructure year
- 2022
- Start date
- Mar 26, 2022
- Completion date
- Feb 19, 2023
- Effective end date
- Feb 19, 2023
- Duration
- 330 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 15.32739, 120.59567