- Description
- REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROAD, CALAMBA-STA. CRUZ-FAMY JCT ROAD K0096 + 376 TO K0096 + 487, CALAMBA-STA. CRUZ-FAMY JCT ROAD
- Category
- Roads
- Component categories
- Roads
- Category group
- Roads
- Province / DEO
- Laguna 1st DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 OO-1
- Infrastructure year
- 2022
- Start date
- Apr 11, 2022
- Completion date
- Nov 5, 2022
- Effective end date
- Nov 5, 2022
- Duration
- 208 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 14.31062, 121.46929