- Description
- REHABILITATION OF BUSALI FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, BILIRAN, BILIRAN (DOWNSTREAM: 124.44750°, 11.490833° - 124.448038°, 11.491473°;124.447222°, 11.49000° - 124.447484°, 11.490199°; 124.44750°, 11.490278° - 124.447791°, 11.490716°; 1
- Category
- Flood Control and Drainage
- Component categories
- Flood Control and Drainage
- Category group
- Flood Control and Drainage
- Province / DEO
- Biliran DEO
- Program
- Regular Infra
- Source of funds
- Regular Infra - GAA 2022 OO-2
- Infrastructure year
- 2022
- Start date
- Feb 21, 2022
- Completion date
- Aug 19, 2022
- Effective end date
- Aug 19, 2022
- Duration
- 179 days
- Is live
- No
- Is completed
- Yes
- Has satellite image
- Yes
- Citizen reports
- 0
- Coordinates
- 11.49438, 124.45265