Precinct report
Everything on file for this region, broken down by province, category and contractor.
Total projects
8,793
Total budget
₱315.2B
Average progress
96.0%
Completion rate
88.6%
Average risk score
38.3
Medium risk on average, out of 100
Flagged as unusual
507
5.8% of the region's projects
Risk mix
Exhibit A
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3,392 | ₱159.3B | 41.4 | 77 | 96.0% |
| Buildings and Facilities | 2,892 | ₱25B | 26.6 | 52 | 98.1% |
| Flood Control and Drainage | 1,201 | ₱94.9B | 48.0 | 122 | 94.5% |
| Bridges | 625 | ₱16.3B | 38.4 | 17 | 97.3% |
| Water Provision and Storage | 328 | ₱1.7B | 24.8 | 7 | 99.2% |
| GAA 2025 SSP | 140 | ₱4.8B | 92.5 | 120 | 72.0% |
| OTHER | 87 | ₱5.1B | 73.2 | 56 | 88.7% |
| GAA 2025 OO-1 | 74 | ₱3.7B | 89.1 | 45 | 74.0% |
| Bridges, Roads | 29 | ₱2.9B | 54.3 | 5 | 85.1% |
| GAA 2025 OO-2 | 25 | ₱1.5B | 89.4 | 6 | 74.9% |
Exhibit B
| Province / DEO | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Mindoro Oriental DEO | 1,268 | ₱21.7B | 33.3 | 34 | 97.7% |
| Romblon DEO | 1,117 | ₱39.6B | 41.0 | 56 | 97.9% |
| Region IV-B | 1,045 | ₱159.6B | 59.0 | 241 | 82.4% |
| Southern Mindoro DEO | 970 | ₱14.2B | 34.6 | 31 | 98.1% |
| Palawan 1st DEO | 960 | ₱13.5B | 33.1 | 38 | 98.0% |
| Palawan 2nd DEO | 958 | ₱14.4B | 33.0 | 46 | 97.9% |
| Mindoro Occidental DEO | 955 | ₱22.3B | 39.1 | 22 | 95.9% |
| Marinduque DEO | 917 | ₱21.2B | 37.5 | 22 | 98.8% |
| Palawan 3rd DEO | 603 | ₱8.7B | 30.6 | 17 | 98.7% |
Exhibit C
Joint-venture projects count toward each partner.
Exhibit D · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EH0163CONSTRUCTION OF ROAD, SITIO EAST MAAMBONG, BARANGAY MAGSAYSAY TO SITIO CAPDANG BARANGAY AGMANIC, STA. FE, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱140.2M | 69% | High risk96 | Flagged0.031 |
| 25EH0161CONSTRUCTION OF ROAD, SITIO MAGSUPOT TO SITIO ILAYA, BARANGAY CALAGONSAO, ALCANTARA, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱140.2M | 73% | High risk96 | Flagged0.029 |
| 25EH0080CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CANTINGAS, SAN FERNANDO, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱145.5M | 93% | High risk96 | Flagged0.024 |
| 25EH0087CONSTRUCTION OF ROAD, ODIONGAN ROAD LEADING TO TUGDAN AIRPORT, ODIONGAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱142.6M | 63% | High risk96 | Flagged0.035 |
| 25EH0088CONSTRUCTION OF ROAD, ALCANTARA TO ODIONGAN, ALCANTARA, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱142.7M | 63% | High risk96 | Flagged0.034 |
| 25EH0079CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CABANGAHAN BARANGAY CARMEN, SAN AGUSTIN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱145.5M | 100% | High risk96 | Flagged0.023 |
| 25EH0111CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER (PHASE 2), ODIONGAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱139.8M | 22% | High risk96 | Flagged0.043 |
| 25EH0110CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER, ODIONGAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱139.7M | 27% | High risk96 | Flagged0.042 |
| 25ED0041CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANSIHAN, CALAPAN CITY, ORIENTAL MINDORO | Mindoro Oriental DEO | SILVERWOLVES CONSTRUCTION CORPORATION | On-Going | ₱96.2M | 87% | High risk95 | Flagged0.018 |
| 25ED0109INSTALLATION OF STREET LIGHTS ALONG CALAPAN SOUTH ROAD K0007+400 -K0021+000, CALAPAN - NAUJAN, ORIENTAL MINDORO | Mindoro Oriental DEO | MG SAMIDAN CONSTRUCTION | Completed | ₱95.1M | 100% | High risk95 | —-0.008 |
| 25ED0015CONSTRUCTION OF ROAD DIKE, BARANGAY BAGONG BUHAY, NAUJAN, ORIENTAL MINDORO | Mindoro Oriental DEO | SILVERWOLVES CONSTRUCTION CORPORATION | On-Going | ₱95M | 71% | High risk95 | Flagged0.023 |
| 25ED0043CONSTRUCTION OF ROAD DIKE ALONG BAGTU RIVER, BARANGAY ARANGIN, NAUJAN, ORIENTAL MINDORO | Mindoro Oriental DEO | SILVERWOLVES CONSTRUCTION CORPORATION | On-Going | ₱109.2M | 54% | High risk95 | Flagged0.032 |
| 25EH0042CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, SITIO RIVERSIDE, BARANGAY TABOBO-AN, ODIONGAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱137.9M | 69% | High risk95 | Flagged0.031 |
| 25ED0016CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CAGUISIKAN, BARANGAY GUTAD, CALAPAN CITY, ORIENTAL MINDORO | Mindoro Oriental DEO | SILVERWOLVES CONSTRUCTION CORPORATIONLUX DRAGON CONSTRUCTION CORPORATION | On-Going | ₱96.6M | 40% | High risk95 | Flagged0.031 |
| 25EE0075CONSTRUCTION OF TARADUNGAN BRIDGE ALONG TAMARBONG-TARADUNGAN-ILAN-CAPAYAS ROAD ROXAS, PALAWAN | Palawan 1st DEO | JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY) | On-Going | ₱98.8M | 21% | High risk95 | Flagged0.053 |
| 25ED0147REHABILITATION OF ROAD, BARANGAY STA. ISABEL - BARANGAY TAWAGAN, CALAPAN CITY, ORIENTAL MINDORO | Mindoro Oriental DEO | UNIMAX STEEL STRUCTURE AND CONSTRUCTION CORP. | On-Going | ₱96.5M | 84% | High risk95 | Flagged0.019 |
| 25ED0108INSTALLATION OF STREET LIGHTS ALONG CALAPAN SOUTH ROAD K0047+200 - K0060+800, SOCORRO, ORIENTAL MINDORO | Mindoro Oriental DEO | MG SAMIDAN CONSTRUCTION | On-Going | ₱96.5M | 81% | High risk95 | Flagged0.021 |
| 25ED0114REHABILITATION OF SUGUI - PALHI ROAD, TIBAG - PACHOCA - WAWA ROAD, CALAPAN CITY, ORIENTAL MINDORO (PHASE 2) | Mindoro Oriental DEO | STX ENTERPRISES | On-Going | ₱96M | 57% | High risk95 | Flagged0.029 |
| 25EH0153CONSTRUCTION OF ROAD, SITIO PALATE TO BARANGAY PANIQUE, ODIONGAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱93.5M | 65% | High risk95 | Flagged0.026 |
| 25EH0154CONSTRUCTION OF ROAD, BARANGAY LAWAN TO BARANGAY SAN ISIDRO (PHASE 2), ALCANTARA, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱93.5M | 81% | High risk95 | Flagged0.021 |
Exhibit E · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23EE0137CONSTRUCTION OF BUSUANG TO CARAMAY FMR, CARAMAY, ROXAS, PALAWAN | Palawan 1st DEO | JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY) | On-Going | ₱14.9M | 0% | Medium risk59 | Flagged0.074 |
| 23EE0138CONSTRUCTION OF SITIO NALBOT TO ARADO FMR, POBLACION, TAYTAY, PALAWAN | Palawan 1st DEO | JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY) | On-Going | ₱14.9M | 0% | High risk60 | Flagged0.071 |
| 24EE0151CONSTRUCTION OF SCHOOL BUILDING, PAG-ASA ELEMENTARY SCHOOL BUILDING PAG-ASA, PALAWAN | Palawan 1st DEO | JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY) | On-Going | ₱49.7M | 81% | High risk86 | Flagged0.069 |
| 24EF0084CONST. OF SCHOOL BLDG., PUNANG ES BLDG. IN SOFRONIO ESPANOLA, PAL., SOFRONIO ESPANOLA, PAL. | Palawan 2nd DEO | KIR KONSTRUCTICON BUILDERS AND SUPPLY INC. (FORMERLY: KONSTRUCTION BUILDERS AND SUPPLY) | On-Going | ₱19.9M | 96% | High risk84 | Flagged0.068 |
| 24E00262CONCRETING OF SITIO LAMOT BABOY, BRGY. PINAGLABANAN FMR, QUEZON, PALAWAN | Region IV-B | IVY MICHELLE CONSTRUCTION AND TRADING INC. (FORMERLY:IVY MICHELLE TRADING & CONTRUCTION) | On-Going | ₱35M | 82% | High risk84 | Flagged0.067 |
| 23EE0139CONSTRUCTION OF SAN NICOLAS TO SITIO CANIOGAN FMR, CORON, PALAWAN | Palawan 1st DEO | JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY) | On-Going | ₱14.9M | 0% | Medium risk58 | Flagged0.064 |
| 24EH0170CONSTRUCTION OF STORM SURGE PROTECTION/CAUSEWAY ALONG POBLACION SEAPORT, ALCANTARA, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱144.8M | 87% | High risk90 | Flagged0.062 |
| 23EF0116CONSTRUCTION OF RIVERBANK PROTECTION RIVER CONTROL DIKE ALONG COLBY RIVER (RIGHT SIDE), RIZAL, PALAWAN | Palawan 2nd DEO | IVY MICHELLE CONSTRUCTION AND TRADING INC. (FORMERLY:IVY MICHELLE TRADING & CONTRUCTION) | On-Going | ₱96.5M | 95% | High risk64 | Flagged0.061 |
| 24EH0171CONSTRUCTION OF SHORE PROTECTION/CAUSEWAY POBLACION, ALCANTARA, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱141.9M | 86% | High risk90 | Flagged0.061 |
| 24E00226ROMBLON STATE UNIVERSITY- CONSTRUCTION OF THE HEALTH AND WELLNESS BUILDING, PHASE I, ODIONGAN, ROMBLON | Region IV-B | PERFORMANCE BUILDERS & DEVELOPERS CORPORATION | On-Going | ₱14.1M | 37% | High risk86 | Flagged0.057 |
| 23E00311ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG QUEZON-PUNTA BAJA ROAD, K0147+414-K0150+465, PALAWAN | Region IV-B | NEWINGTON BUILDERS, INC.(FOR: E. GARDIOLA CONSTRUC | On-Going | ₱202.6M | 66% | High risk66 | Flagged0.057 |
| 23E00306SUSTANABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF POBLACION-TAGUMPAY DIVERSION ROAD LEADING TO CORON CRUISE PORT, PACKAGE 1 | Region IV-B | MAC BUILDERS CORP. (FORMERLY: MAC BUILDERS DEVELOPMENT CORPORATION) | On-Going | ₱280.2M | 20% | High risk64 | Flagged0.057 |
| 24EH0179CONSTRUCTION OF LUMBANG WESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱130.4M | 100% | High risk90 | Flagged0.057 |
| 25EF0087CONST. OF PEDESTRIAN OVERPASS-PUERTO PRINCESA SOUTH ROAD K090+1075, NARRA, PALAWAN | Palawan 2nd DEO | L.D. DEMAALA CORPORATION | On-Going | ₱22.1M | 12% | High risk94 | Flagged0.056 |
| 24EE0144PACKAGE 2-CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDINGS IN:1. SAN FERNANDO NATIONAL HIGH SCHOOL, BARANGAY SAN FERNANDO2. DIAPILA NATIONAL HIGH SCHOOL, BARANGAY TENEGUIBAN, EL NIDO, PALAWAN | Palawan 1st DEO | E.V. VILLAOS TRADING & CONSTRUCTION | On-Going | ₱9.9M | 88% | High risk85 | Flagged0.055 |
| 25EB0117CONCRETING OF BRGY. SALVACION FMR, BRGY. SALVACION, RIZAL, OCCIDENTAL MINDORO | Mindoro Occidental DEO | MIGHTY DRAGON BUILDERS INC. | On-Going | ₱14.9M | 55% | High risk86 | Flagged0.055 |
| 25EG0014CONSTRUCTION OF ROAD, APORAWAN TO SITIO DAAN, 00+000.00 - 02+098.00, ABORLAN, PALAWAN | Palawan 3rd DEO | IVY MICHELLE CONSTRUCTION AND TRADING INC. (FORMERLY:IVY MICHELLE TRADING & CONTRUCTION) | On-Going | ₱103.4M | 29% | High risk95 | Flagged0.055 |
| 23E00310ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASDPHALT OVERLAY) ALONG PPSR JCT. (ABO-ABO)-QUEZON ROAD, K0139+568-K0142+730, PALAWAN | Region IV-B | NEWINGTON BUILDERS, INC.(FOR: E. GARDIOLA CONSTRUC | On-Going | ₱173.7M | 71% | High risk64 | Flagged0.055 |
| 25ED0210CONSTRUCTION OF SCHOOL BUILDING, ORIENTAL MINDORO NATIONAL HIGH SCHOOL, SAN VICENTE EAST, CALAPAN CITY, ORIENTAL MINDORO | Mindoro Oriental DEO | MIDR CONSTRUCTION AND SUPPLIES | On-Going | ₱19.3M | 60% | High risk87 | Flagged0.054 |
| 25EE0075CONSTRUCTION OF TARADUNGAN BRIDGE ALONG TAMARBONG-TARADUNGAN-ILAN-CAPAYAS ROAD ROXAS, PALAWAN | Palawan 1st DEO | JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY) | On-Going | ₱98.8M | 21% | High risk95 | Flagged0.053 |
Exhibit F · Evidence locker
Sorted by risk score.
| # | Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 526 | 25EH0055CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TABOBO-AN RIVER, ODIONGAN, ROMBLON | Romblon DEO | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION) | On-Going | ₱141.9M | 99% | High risk67 | —-0.029 |
| 527 | 23E00112SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF TUGDAN CAUSEWAY, ALCANTARA, TABLAS ISLAND, ROMBLON | Region IV-B | LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) | Completed | ₱241.2M | 100% | High risk67 | —-0.038 |
| 528 | 23E00117SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORO | Region IV-B | GREAT PACIFIC BUILDERS AND GEN. CONTRACTOR INC. ([REVOKED] 45914) | On-Going | ₱221.9M | 86% | High risk67 | Flagged0.004 |
| 529 | 24E00034FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF ROAD DIKE/ESPLANADE ALONG PANGALAAN RIVER (LEFT SIDE), NAUJAN, OR. MINDORO | Region IV-B | ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) | Completed | ₱289.5M | 100% | High risk67 | —-0.036 |
| 530 | 23E00119SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF SOUTHERN MINDORO COASTAL ROAD, BONGABONG, ORIENTAL MINDORO | Region IV-B | ANORE CONSTRUCTION | On-Going | ₱200.1M | 90% | High risk67 | Flagged0.004 |
| 531 | 24E00188FLOOD MANAGEMENT PROGRAM- CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD CONTROL STRUCTURE ALONG BANSUD RIVER (UPSTREAM), BANSUD, ORIENTAL MINDORO | Region IV-B | LE BRON CONSTRUCTION | On-Going | ₱186M | 89% | High risk67 | —-0.004 |
| 532 | 25EA0078BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (TOURIST REGISTRATION AND BANTAY DAGAT BUILDING), BARANGAY MANIWAYA, SANTA CRUZ, MARINDUQUE | Marinduque DEO | R.R. ENCABO CONSTRUCTORS INCORPORATED (FORMERLY RR | On-Going | ₱33.1M | 0% | High risk67 | —-0.002 |
| 533 | 23E00003CONSTRUCTION OF MISSING LINKS/NEW ROADS DR. DAMIAN REYES ROAD (BOAC SIDE), MARINDUQUE | Region IV-B | MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. | On-Going | ₱192.9M | 75% | High risk67 | Flagged0.000 |
| 534 | 17EH0116REPAIR/REHABILITATION/IMPROVEMENT OF CALAGONSAO RIVER CONTROL, ALCANTARA, ROMBLON | Romblon DEO | LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) | Completed | ₱83.8M | 100% | High risk67 | Flagged0.009 |
| 535 | 17E00062REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIP SLOPE COLLAPSE AND LANDSLIDE TABLAS CIRCUMFERENTIAL ROAD K0033+900-K0034+743.60, TABLAS, ROMBLON | Region IV-B | ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762) | Completed | ₱112M | 100% | High risk67 | —-0.041 |
| 536 | 23E00156CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, SITIO SILI, BRGY. METOLZA SECTION, NAUJAN, OR. MINDORO | Region IV-B | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION)MACROPRIME BUILDERS CORPORATION (FORMERLY: MORANTE BUILDERS & SUPPLY) | Completed | ₱289.5M | 100% | High risk67 | —-0.034 |
| 537 | 23E00157CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, SITIO CENTRO V, BRGY. METOLZA SECTION, NAUJAN, OR. MINDORO | Region IV-B | SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION)FGO CONSTRUCTION | Completed | ₱289.5M | 100% | High risk67 | —-0.034 |
| 538 | 17E00008CONCRETING OF ARMY ROAD (BAGUBAG-SORVILLE-GOZAR-BINAKAS) LEADING TO PAF GOZAR RADAR STATION IN MT. AMBULONG, BRGY. SORVILLE, STA. 2+745.80-STA.5+587.20; STA.6+242-STA.6+364, LUBANGISLAND, OCCIDENTAL MINDORO | Mindoro Occidental DEO | TOKWING CONSTRUCTION, CORP.(FOR; TOKWING CONSTRUC | Completed | ₱91.9M | 100% | High risk67 | —-0.030 |
| 539 | 23E00190SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON | Region IV-B | LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) | On-Going | ₱289.5M | 57% | High risk67 | Flagged0.019 |
| 540 | 25E00139CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF PILI RIVERSIDE PROTECTION STRUCTURE, DOWNSTREAM, POBLACION, SAN FERNANDO, ROMBLON | Region IV-B | YPR GEN. CONTRACTOR AND CONSTRUCTION SUPPLY INC. | On-Going | ₱144.7M | 94% | High risk67 | —-0.024 |
| 541 | 24E00141SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURE PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF TORRIJOS SHORE PROTECTION STRUCTURE, BRGY. POBLACION, TORRIJOS, MARINDUQUE | Region IV-B | HGG BUILDERS & SUPPLY | On-Going | ₱232.8M | 89% | High risk67 | —-0.000 |
| 542 | 17EH0120REPAIR/REHABILITATION/IMPROVEMENT OF PATOO RIVER CONTROL, PATOO, ODIONGAN, ROMBLON | Romblon DEO | ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196) | Completed | ₱84M | 100% | High risk67 | Flagged0.011 |
| 543 | 17EH0121REPAIR/REHABILITATION/IMPROVEMENT OF GABAWAN RIVER CONTROL, GABAWAN, ODIONGAN, ROMBLON | Romblon DEO | MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. | Completed | ₱83.6M | 100% | High risk67 | Flagged0.009 |
| 544 | 22E00165CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1 | Region IV-B | ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)STX ENTERPRISES | On-Going | ₱289.5M | 62% | High risk67 | Flagged0.022 |
| 545 | 17E00019IMPROVEMENT/WIDENING OF CORON-BUSUANGA ROAD, KO010+356.00-KO012+486; KO012+539.00-KO013+582.00, CORON, PALAWAN | Palawan 1st DEO | ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION) | Completed | ₱93.5M | 100% | High risk67 | —-0.024 |
| 546 | 23E00167BASIC INFRASTRUCTURE PROGRAM- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE AT SITIO TALIPANAN, STA. 015+460-STA. 015+660 IN BRGY. ANIN | Region IV-B | ARCONIC INC. | Completed | ₱163.3M | 100% | High risk67 | —-0.049 |
| 547 | 24E00097BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON | Region IV-B | LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) | On-Going | ₱297M | 90% | High risk67 | Flagged0.004 |
| 548 | 20EI0032CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BANGKAL RIVER CONTROL, BULALACAO, ORIENTAL MINDORO | Southern Mindoro DEO | SOSEP BUILDERS | Completed | ₱4.9M | 100% | High risk67 | —-0.043 |
| 549 | 17EH0114REPAIR/REHABILITATION/IMPROVEMENT OF MAGDIWANG RIVER CONTROL, MAGDIWANG, ROMBLON | Romblon DEO | LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION)MT. GUITING-GUITING CONSTRUCTION | Completed | ₱80.2M | 100% | High risk67 | Flagged0.008 |
| 550 | 23E00031SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ILVITA RIVERBANK PROTECTION WORKS ALONG AMNAY RIVER, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | ANORE CONSTRUCTION | Completed | ₱217.1M | 100% | High risk67 | —-0.038 |