Precinct report
Everything on file for this region, broken down by province, category and contractor.
Total projects
8,109
Total budget
₱197.7B
Average progress
94.2%
Completion rate
77.8%
Average risk score
44.2
Medium risk on average, out of 100
Flagged as unusual
618
7.6% of the region's projects
Risk mix
Exhibit A
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3,182 | ₱23.4B | 28.4 | 117 | 96.5% |
| Roads | 3,091 | ₱109B | 53.7 | 156 | 94.1% |
| Flood Control and Drainage | 706 | ₱34.6B | 57.7 | 40 | 92.9% |
| Bridges | 422 | ₱12.3B | 50.4 | 52 | 92.0% |
| Water Provision and Storage | 375 | ₱2.5B | 31.3 | 16 | 98.4% |
| OTHER | 187 | ₱9.5B | 79.3 | 124 | 83.6% |
| GAA 2025 SSP | 66 | ₱1.2B | 92.5 | 62 | 62.9% |
| GAA 2025 OO-1 | 52 | ₱2.7B | 92.5 | 40 | 52.8% |
| GAA 2025 OO-2 | 21 | ₱1.7B | 90.0 | 11 | 72.0% |
| Bridges, Roads | 7 | ₱837.7M | 69.2 | 0 | 79.8% |
Exhibit B
| Province / DEO | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 1,191 | ₱95.9B | 66.3 | 264 | 84.7% |
| Zamboanga del Sur 2nd DEO | 915 | ₱10B | 31.5 | 34 | 97.3% |
| Zamboanga del Sur 1st DEO | 894 | ₱14.2B | 41.6 | 27 | 96.7% |
| Zamboanga City 2nd DEO | 851 | ₱13.9B | 48.0 | 124 | 92.5% |
| Zamboanga Sibugay 2nd DEO | 818 | ₱10.5B | 37.0 | 23 | 97.0% |
| Zamboanga Sibugay 1st DEO | 782 | ₱13.6B | 41.9 | 22 | 92.2% |
| Zamboanga del Norte 1st DEO | 757 | ₱11.6B | 42.8 | 42 | 95.5% |
| Zamboanga del Norte 2nd DEO | 733 | ₱9.1B | 36.4 | 36 | 95.0% |
| Zamboanga del Norte 3rd DEO | 628 | ₱9.1B | 40.5 | 10 | 99.5% |
| Isabela City DEO | 404 | ₱6B | 42.1 | 15 | 99.0% |
| Zamboanga del Norte 4th DEO | 128 | ₱3.4B | 57.2 | 15 | 96.8% |
| Zamboanga City 1st DEO | 8 | ₱406.6M | 74.3 | 6 | 69.6% |
Exhibit C
Joint-venture projects count toward each partner.
Exhibit D · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25J00021PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) K1651+060.00 - K1653+244.03 | Region IX | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱109.1M | 83% | High risk96 | Flagged0.026 |
| 25J00104ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE | Region IX | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱153M | 79% | High risk96 | Flagged0.032 |
| 25J00037PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD), K1773+361.00 - K1775+181.00 | Region IX | BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE | On-Going | ₱107.2M | 31% | High risk96 | Flagged0.040 |
| 25JJ0028PREVENTIVE MAINTENANCE - SECONDARY ROADS ALONG SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD -(S01151MN) CHAINAGE 23548 - CHAINAGE 24284, CHAINAGE 24608 - CHAINAGE 26765, CHAINAGE 26793 - CHAINAGE 29000 | Zamboanga del Norte 4th DEO | BENRAM CONSTRUCTIONST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196) | On-Going | ₱83.8M | 97% | High risk95 | Flagged0.020 |
| 25JA0033CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT TIGBALABAG ELEM. SCHOOL, BRGY. TIGBALABAG, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ADZ ENGINEERING AND CONSTRUCTION | On-Going | ₱14.4M | 70% | High risk95 | Flagged0.024 |
| 25JA0027SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF DRAINAGE SYSTEM AT ADELAIDA HOMES TALON-TALON, BRGY. TALON-TALON, ZAMBOANGA CITY | Zamboanga City 2nd DEO | AKMS CONSTRUCTION | On-Going | ₱11.2M | 65% | High risk95 | Flagged0.026 |
| 25JE0012BIP- MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI- PURPOSE BUILDING, ZAMBOANGA DEL SUR | Zamboanga del Sur 1st DEO | KS AGAD CONSTRUCTION | On-Going | ₱14.8M | 84% | High risk95 | Flagged0.013 |
| 25JG0060MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TABINA, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ILMW CONSTRUCTION & ENTERPRISES | On-Going | ₱19.8M | 23% | High risk95 | Flagged0.036 |
| 25JB0059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239 INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROAD SIGNS, ROADWAY LIGHTING) ALONG PIÑAN - MUTIA RD - K1816+(-897) - K1839+409 | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱24.5M | 94% | High risk95 | Flagged0.012 |
| 25JB0061SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239 INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROAD SIGNS, ROADWAY LIGHTING) ALONG POLANCO-MACLEODES RD - K1828+(-225) - K1848+950 | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱24.5M | 97% | High risk95 | Flagged0.011 |
| 25JG0026BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF ROAD, PUROK YACAL - PUROK ACACIA, BARANGAY WALING-WALING, VINCENZO A. SAGUN, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱9.9M | 52% | High risk95 | Flagged0.027 |
| 25JB0048CONSTRUCTION OF MULTIPURPOSE BUILDING LINGASAD ELEMENTARY SCHOOL, BARANGAY LINGASAD, POLANCO, ZAMBOANGA DEL NORTE | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱14.8M | 48% | High risk95 | Flagged0.026 |
| 25J00036PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | On-Going | ₱78M | 50% | High risk95 | Flagged0.032 |
| 25JA0032CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT GUISAO ELEMENTARY SCHOOL, BRGY. GUISAO, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ADZ ENGINEERING AND CONSTRUCTION | On-Going | ₱9.5M | 60% | High risk95 | Flagged0.028 |
| 25J00243PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱72.1M | 91% | High risk94 | —-0.000 |
| 25JE0024REPLACEMENT OF PERMANENT WEAK BRIDGES TUKURAN BR. (B01196MN) ALONG LANAO- PAGADIAN- ZAMBOANGA CITY RD. TUKURAN, ZAMBOANGA DEL SUR | Zamboanga del Sur 1st DEO | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱57.8M | 3% | High risk94 | Flagged0.023 |
| 25JG0015ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY GAWIL TO BARANGAY BOLISONG, KUMALARANG, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱49M | 67% | High risk94 | Flagged0.023 |
| 25J00052NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (TUCURAN JCT - KAROMATAN JCT RD) | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱153M | 31% | High risk94 | Flagged0.028 |
| 25JB0076CONSTRUCTION OF EVACUATION CENTER IN RIZAL, ZAMBOANGA DEL NORTE | Zamboanga del Norte 1st DEO | YUBROS CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱4.8M | 31% | High risk94 | Flagged0.030 |
| 25J00107ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO - PA-GADIAN - ZAMBOANGA CITY RD) | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱91.3M | 18% | High risk94 | Flagged0.024 |
Exhibit E · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JK0004CONSTRUCTION OF ZAMBOANGA CITY R.T. LIM BOULEVARD, PACKAGE 1, ZAMBOANGA CITY | Zamboanga City 1st DEO | HHH DEVELOPER AND CONSTRUCTION | On-Going | ₱98.3M | 22% | High risk92 | Flagged0.083 |
| 24JA0161CONSTRUCTION OF WATER SYSTEM (LEVEL III), BARANGAY STA. MARIA TO MAMPANG, ZAMBOANGA CITY PHASE 1 | Zamboanga City 2nd DEO | ASAP GENERAL TRADING CONSTRUCTION & MAINTENANCEHHH DEVELOPER AND REAL ESTATE INC. | On-Going | ₱105.5M | 42% | High risk92 | Flagged0.077 |
| 24JA0163CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUTIK RIVER, (PUTIK SECTION), ZAMBOANGA CITY | Zamboanga City 2nd DEO | LAKEWOOD CONSTRUCTION COMPANY | On-Going | ₱88.1M | 34% | High risk90 | Flagged0.074 |
| 18J00148SANGA-SANGA AIRPORT DEVELOPMENT PROJECT, SANGA SANGA, BONGAO, TAWI-TAWI | Region IX | AL-SADIK CONSTRUCTION & ENTERPRISES, INC.VICENTE T. LAO CONSTRUCTION | On-Going | ₱320.9M | 65% | High risk63 | Flagged0.071 |
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE. | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24JA0147CONSTRUCTION OF 4STY12CL, PASONANCA NATIONAL HIGH SCHOOL, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Zamboanga City 2nd DEO | ATLANTIC ERECTORS, INC. | On-Going | ₱57.2M | 55% | High risk90 | Flagged0.069 |
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Zamboanga City 2nd DEO | LL CONSTRUCTIONTEDDIE CONSTRUCTION DEVELOPMENT, INC. | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 24JC0061CONSTRUCTION OF 4STY20CL, GALAS NHS, DIPOLOG CITY, ZAMBOANGA DEL NORTE | Zamboanga del Norte 2nd DEO | D' DREAMER DEVELOPMENT CORPORATIONABIB BUILDERS ENTERPRISE | On-Going | ₱53.6M | 32% | High risk88 | Flagged0.066 |
| 25JE0072CONCRETING OF BRGY. DEBOROK FMR, BRGY. DEBOROK, PAGADIAN, ZAMBOANGA DEL SUR, PAGADIAN CITY, ZAMBOANGA DEL SUR. | Zamboanga del Sur 1st DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱14.9M | 25% | High risk88 | Flagged0.065 |
| 24JA0176CONSTRUCTION OF DRAINAGE STRUCTURE AT TALON-TALON LOOP ROAD, BARANGAY TALON-TALON, ZAMBOANGA CITY | Zamboanga City 2nd DEO | AKMS CONSTRUCTION | On-Going | ₱28.9M | 67% | High risk89 | Flagged0.063 |
| 24JA0160CONSTRUCTION OF DRAINAGE STRUCTURE AT LUSTRE ROAD (SANTA CATALINA-ZONE IV) PACKAGE 1 ZAMBOANGA CITY | Zamboanga City 2nd DEO | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱38.6M | 70% | High risk88 | Flagged0.061 |
| 24J00260WESTERN MINDANAO STATE UNIVERSITY - CONSTRUCTION OF THREE (3) STOREY ACADEMIC BUILDING, WMSU IPIL CAMPUS | Region IX | MJMARI BUILDERS AND DEVELOPMENT CORPORATION (FORMERLY: MJMARI BUILDERS AND ENTERPRISES) | On-Going | ₱28M | 33% | High risk86 | Flagged0.061 |
| 24JG0075CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE II, VINCENZO SAGUN, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ILMW CONSTRUCTION & ENTERPRISES | On-Going | ₱19.8M | 37% | High risk87 | Flagged0.061 |
| 24JA0155REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD AT BARANGAY QUINIPUT, ZAMBOANGA CITY | Zamboanga City 2nd DEO | LL CONSTRUCTION | On-Going | ₱9.6M | 54% | High risk87 | Flagged0.061 |
| 24JA0171CONSTRUCTION OF DRAINAGE STRUCTURE AT TUGBUNGAN (MORNING BREEZE) TO BARANGAY TALON-TALON, PACKAGE 1, ZAMBOANGA CITY | Zamboanga City 2nd DEO | RCDG CONSTRUCTION CORPORATION | On-Going | ₱38.6M | 0% | High risk70 | Flagged0.061 |
| 24J00249CRISTINO M. PARAGAS MEMORIAL HOSPITAL, QUINIPUT, ZAMBOAN-GA CITY | Region IX | BENRAM CONSTRUCTION | On-Going | ₱144.8M | 18% | Medium risk58 | Flagged0.060 |
| 25JG0050CONCRETING OF BARANGAY TINA FMR, DUMALINAO, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱14.5M | 33% | High risk88 | Flagged0.060 |
| 23JA0080CONCRETING OF BRGY. VITALI FMR, BRGY. VITALI, ZAMBOANGA CITY | Zamboanga City 2nd DEO | JH CONSTRUCTION INC. | On-Going | ₱19.8M | 100% | High risk88 | Flagged0.060 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE. | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 25JE0071CONCRETING OF BRGY. SANTO ROSARIO FMR, BRGY. SANTO ROSARIO, RAMON MAGSAYSAY, ZAMBOANGA DEL SUR. | Zamboanga del Sur 1st DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱14.9M | 51% | High risk88 | Flagged0.058 |
Exhibit F · Evidence locker
Sorted by risk score.
| # | Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 826 | 24J00086CONSTRUCTION OF ROAD, BARANGAY LAHI, MAIMBUNG, SULU | Region IX | AL-SADIK CONSTRUCTION & ENTERPRISES, INC. | On-Going | ₱34.6M | 100% | High risk69 | —-0.012 |
| 827 | 24JB0052PREVENTIVE MAINTENANCE DIPOLOG-OROQUIETA NATIONAL ROAD (SO1316MN) K1797+681-K1797+999, K1798+996-K1800+470, (SO1062MN) CHAINAGE 58- CHAINAGE 208 | Zamboanga del Norte 1st DEO | VICENTE T. LAO CONSTRUCTION | Completed | ₱120.4M | 100% | High risk69 | —-0.072 |
| 828 | 21J00063CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BALUCOT-LOWER USUGAN-TUNGAWAN BY-PASS ROAD | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱97M | 100% | High risk69 | —-0.013 |
| 829 | 24JA0153WIDENING OF PUTIK-LUNZURAN ROAD, ZAMBOANGA CITY PACKAGE 1 | Zamboanga City 2nd DEO | ASAP GENERAL TRADING CONSTRUCTION & MAINTENANCELL CONSTRUCTION | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 830 | 24JA0152CONSTRUCTION OF TETUAN-SANTA CATALINA ROAD (ESTRADA SECTION), ZAMBOANGA CITY PHASE 1 | Zamboanga City 2nd DEO | LAKEWOOD CONSTRUCTION COMPANY | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 831 | 21J00021NETWORK DEVELOPMENT - CONSTRUCTION OF BYPASS AND DIVERSION ROADS - AIRPORT - TURNO - SINAMAN BYPASS ROAD, ZAMBOANGA DEL NORTE | Region IX | DIPOLOG TOP CONSTRUCTION & DEVT. CORP | On-Going | ₱95.8M | 100% | High risk69 | —-0.018 |
| 832 | 22J00002ROAD WIDENING - PRIMARY ROADS - DIPOLOG - SINDANGAN - LILOY ROAD | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱97.8M | 90% | High risk69 | —-0.017 |
| 833 | 20J00161REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS DIPOLOG-POLANCO-PIÑAN-JCT OROQUIETA ROAD | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION | Completed | ₱118.1M | 100% | High risk69 | —-0.073 |
| 834 | 24JA0156CONSTRUCTION OF LUMAYANG-PASONANCA ROAD PACKAGE 2, ZAMBOANGA CITY | Zamboanga City 2nd DEO | RJLP CONSTRUCTION AND SUPPLIESATLANTIC ERECTORS, INC. | On-Going | ₱67.5M | 41% | High risk69 | Flagged0.022 |
| 835 | 23JA0110CONCRETING OF ROAD, BARANGAY TOLOSA, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ASAP GENERAL TRADING CONSTRUCTION & MAINTENANCEHHH DEVELOPER AND REAL ESTATE INC. | On-Going | ₱67.2M | 65% | High risk69 | Flagged0.024 |
| 836 | 24J00110ROAD WIDENING-PRIMARY ROADS LANAO-PAGADIAN CITY-ZAMBOANGA CITY RD (S01328MN) | Region IX | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱110.4M | 68% | High risk69 | —-0.028 |
| 837 | 18J00006CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BYPASS ROAD INCLUDING ROW, BRIDGE, AND SLOPE PROTECTION, ZAMBOANGA CITY | Region IX | ALRAF CONST. AND ENTERPRISES INC. (FORMERLY:ALRAF CONSTRUCTION & ENTERPRISES)MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. | Completed | ₱190.9M | 100% | High risk69 | —-0.011 |
| 838 | 21J00024ROAD WIDENING - PRIMARY ROADS - SINDANGAN - LILOY ROAD | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | Completed | ₱102.1M | 100% | High risk69 | —-0.073 |
| 839 | 23J00114PREVENTIVE MAINTENANCE - SECONDARY ROAD ROMANDIER - CAMP ANDRES - TANDUH BATO ROAD | Region IX | ZHEREB CONSTRUCTION | Completed | ₱10.4M | 100% | High risk69 | —-0.041 |
| 840 | 25J00077ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) - K1770 + 590 - K1771 + 576, K1774 + 000 - K1774 + 320 | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | On-Going | ₱74.4M | 4% | High risk69 | Flagged0.003 |
| 841 | 20J00162WIDENING OF PERMANENT BRIDGES - POLO PARALLEL BRIDGE ALONG JCT. POLO - DAPITAN PARK NATIONAL ROAD (PHASE II) | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION | Completed | ₱178M | 100% | High risk69 | —-0.025 |
| 842 | 25J00024PREVENTIVE MAINTENANCE - PRIMARY ROADS, MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) K1711+000.00 - K1712+810.00, K1712+810 - K 1712+834.00 | Region IX | BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE | On-Going | ₱96M | 59% | High risk69 | —-0.009 |
| 843 | 20J00058CONST./IMPROVEMENT OF ACCESS ROAD LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, SITIO BOBONAO, ILAYA-BURGOS-TAMION-DIWA-AN ROAD IN SUPPORT TO COPRA INDUSTRY, DAPITAN CITY, ZAMBOANGA DEL NORTE | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱113.1M | 100% | High risk69 | —-0.012 |
| 844 | 24JD0004ROAD WIDENING - SECONDARY ROADS, LILOY - SIOCON RD K1987 + 500 - K1990 + 484, ZAMBOANGA DEL NORTE | Zamboanga del Norte 3rd DEO | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱120.9M | 98% | High risk69 | —-0.035 |
| 845 | 25J00063ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | Region IX | DL ENTERPRISES | On-Going | ₱159.8M | 6% | High risk69 | Flagged0.018 |
| 846 | 18J00046RECONSTRUCTION FROM PAVED TO CONCRETE - RIZAL - DAKAK - DAPITAN COASTAL LOOP ROAD, (S01038MN), ZAMBOANGA DEL NORTE, STA. 1820+000.00 - STA. 1820+938.26, STA. 1841+984.00 - STA. 1842+993.53, STA. 1856+984.00 - STA. 1859+430.00, NET LENGTH: 8.79 LANE KM/4,3 | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | Completed | ₱152.5M | 100% | High risk69 | —-0.064 |
| 847 | 18J00037CONSTRUCTION OF CONCRETE ROAD AND ROAD SLOPE PROTECTION STRUCTURE BALIGUIAN COASTAL ROAD, JUNCTION BALIGUIAN - KAUSWAGAN - MAMAD SECTION, ZAMBOANGA DEL NORTE, 2ND DEO, K2043+170.00 - K2044+410.00, K2044+810.00 - K2046+464.00, NET LENGTH: 5.79 LANE KM/2,8 | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | Completed | ₱280.6M | 100% | High risk69 | —-0.042 |
| 848 | 20J00020ROAD WIDENING - PRIMARY ROADS DIPOLOG - PUNTA - DANSULLAN - SERGIO OSMEÑA - ZAMBOANGA DEL NORTE/SUR BOUNDARY SO1056MN | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION | Completed | ₱117.7M | 100% | High risk69 | —-0.073 |
| 849 | 23J00009REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DIPOLOG - SINDANGAN - LILOY ROAD | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱97.4M | 94% | High risk68 | —-0.030 |
| 850 | 20J00019PREVENTIVE MAINTENANCE - SECONDARY ROADS ASPHALT OVERLAY OF SINDANGAN - SIAYAN - DUMINGAG - MAHAYAG ROAD, SINDANGAN - SIAYAN SECTION | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | Completed | ₱101.4M | 100% | High risk68 | —-0.073 |