Precinct report
Everything on file for this region, broken down by province, category and contractor.
Total projects
8,109
Total budget
₱197.7B
Average progress
94.2%
Completion rate
77.8%
Average risk score
44.2
Medium risk on average, out of 100
Flagged as unusual
618
7.6% of the region's projects
Risk mix
Exhibit A
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3,182 | ₱23.4B | 28.4 | 117 | 96.5% |
| Roads | 3,091 | ₱109B | 53.7 | 156 | 94.1% |
| Flood Control and Drainage | 706 | ₱34.6B | 57.7 | 40 | 92.9% |
| Bridges | 422 | ₱12.3B | 50.4 | 52 | 92.0% |
| Water Provision and Storage | 375 | ₱2.5B | 31.3 | 16 | 98.4% |
| OTHER | 187 | ₱9.5B | 79.3 | 124 | 83.6% |
| GAA 2025 SSP | 66 | ₱1.2B | 92.5 | 62 | 62.9% |
| GAA 2025 OO-1 | 52 | ₱2.7B | 92.5 | 40 | 52.8% |
| GAA 2025 OO-2 | 21 | ₱1.7B | 90.0 | 11 | 72.0% |
| Bridges, Roads | 7 | ₱837.7M | 69.2 | 0 | 79.8% |
Exhibit B
| Province / DEO | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 1,191 | ₱95.9B | 66.3 | 264 | 84.7% |
| Zamboanga del Sur 2nd DEO | 915 | ₱10B | 31.5 | 34 | 97.3% |
| Zamboanga del Sur 1st DEO | 894 | ₱14.2B | 41.6 | 27 | 96.7% |
| Zamboanga City 2nd DEO | 851 | ₱13.9B | 48.0 | 124 | 92.5% |
| Zamboanga Sibugay 2nd DEO | 818 | ₱10.5B | 37.0 | 23 | 97.0% |
| Zamboanga Sibugay 1st DEO | 782 | ₱13.6B | 41.9 | 22 | 92.2% |
| Zamboanga del Norte 1st DEO | 757 | ₱11.6B | 42.8 | 42 | 95.5% |
| Zamboanga del Norte 2nd DEO | 733 | ₱9.1B | 36.4 | 36 | 95.0% |
| Zamboanga del Norte 3rd DEO | 628 | ₱9.1B | 40.5 | 10 | 99.5% |
| Isabela City DEO | 404 | ₱6B | 42.1 | 15 | 99.0% |
| Zamboanga del Norte 4th DEO | 128 | ₱3.4B | 57.2 | 15 | 96.8% |
| Zamboanga City 1st DEO | 8 | ₱406.6M | 74.3 | 6 | 69.6% |
Exhibit C
Joint-venture projects count toward each partner.
Exhibit D · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25J00021PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) K1651+060.00 - K1653+244.03 | Region IX | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱109.1M | 83% | High risk96 | Flagged0.026 |
| 25J00104ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE | Region IX | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱153M | 79% | High risk96 | Flagged0.032 |
| 25J00037PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD), K1773+361.00 - K1775+181.00 | Region IX | BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE | On-Going | ₱107.2M | 31% | High risk96 | Flagged0.040 |
| 25JJ0028PREVENTIVE MAINTENANCE - SECONDARY ROADS ALONG SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD -(S01151MN) CHAINAGE 23548 - CHAINAGE 24284, CHAINAGE 24608 - CHAINAGE 26765, CHAINAGE 26793 - CHAINAGE 29000 | Zamboanga del Norte 4th DEO | BENRAM CONSTRUCTIONST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196) | On-Going | ₱83.8M | 97% | High risk95 | Flagged0.020 |
| 25JA0033CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT TIGBALABAG ELEM. SCHOOL, BRGY. TIGBALABAG, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ADZ ENGINEERING AND CONSTRUCTION | On-Going | ₱14.4M | 70% | High risk95 | Flagged0.024 |
| 25JA0027SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF DRAINAGE SYSTEM AT ADELAIDA HOMES TALON-TALON, BRGY. TALON-TALON, ZAMBOANGA CITY | Zamboanga City 2nd DEO | AKMS CONSTRUCTION | On-Going | ₱11.2M | 65% | High risk95 | Flagged0.026 |
| 25JE0012BIP- MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI- PURPOSE BUILDING, ZAMBOANGA DEL SUR | Zamboanga del Sur 1st DEO | KS AGAD CONSTRUCTION | On-Going | ₱14.8M | 84% | High risk95 | Flagged0.013 |
| 25JG0060MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TABINA, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ILMW CONSTRUCTION & ENTERPRISES | On-Going | ₱19.8M | 23% | High risk95 | Flagged0.036 |
| 25JB0059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239 INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROAD SIGNS, ROADWAY LIGHTING) ALONG PIÑAN - MUTIA RD - K1816+(-897) - K1839+409 | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱24.5M | 94% | High risk95 | Flagged0.012 |
| 25JB0061SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239 INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROAD SIGNS, ROADWAY LIGHTING) ALONG POLANCO-MACLEODES RD - K1828+(-225) - K1848+950 | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱24.5M | 97% | High risk95 | Flagged0.011 |
| 25JG0026BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF ROAD, PUROK YACAL - PUROK ACACIA, BARANGAY WALING-WALING, VINCENZO A. SAGUN, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱9.9M | 52% | High risk95 | Flagged0.027 |
| 25JB0048CONSTRUCTION OF MULTIPURPOSE BUILDING LINGASAD ELEMENTARY SCHOOL, BARANGAY LINGASAD, POLANCO, ZAMBOANGA DEL NORTE | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱14.8M | 48% | High risk95 | Flagged0.026 |
| 25J00036PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | On-Going | ₱78M | 50% | High risk95 | Flagged0.032 |
| 25JA0032CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT GUISAO ELEMENTARY SCHOOL, BRGY. GUISAO, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ADZ ENGINEERING AND CONSTRUCTION | On-Going | ₱9.5M | 60% | High risk95 | Flagged0.028 |
| 25J00243PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱72.1M | 91% | High risk94 | —-0.000 |
| 25JE0024REPLACEMENT OF PERMANENT WEAK BRIDGES TUKURAN BR. (B01196MN) ALONG LANAO- PAGADIAN- ZAMBOANGA CITY RD. TUKURAN, ZAMBOANGA DEL SUR | Zamboanga del Sur 1st DEO | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱57.8M | 3% | High risk94 | Flagged0.023 |
| 25JG0015ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY GAWIL TO BARANGAY BOLISONG, KUMALARANG, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱49M | 67% | High risk94 | Flagged0.023 |
| 25J00052NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (TUCURAN JCT - KAROMATAN JCT RD) | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱153M | 31% | High risk94 | Flagged0.028 |
| 25JB0076CONSTRUCTION OF EVACUATION CENTER IN RIZAL, ZAMBOANGA DEL NORTE | Zamboanga del Norte 1st DEO | YUBROS CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱4.8M | 31% | High risk94 | Flagged0.030 |
| 25J00107ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO - PA-GADIAN - ZAMBOANGA CITY RD) | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱91.3M | 18% | High risk94 | Flagged0.024 |
Exhibit E · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JK0004CONSTRUCTION OF ZAMBOANGA CITY R.T. LIM BOULEVARD, PACKAGE 1, ZAMBOANGA CITY | Zamboanga City 1st DEO | HHH DEVELOPER AND CONSTRUCTION | On-Going | ₱98.3M | 22% | High risk92 | Flagged0.083 |
| 24JA0161CONSTRUCTION OF WATER SYSTEM (LEVEL III), BARANGAY STA. MARIA TO MAMPANG, ZAMBOANGA CITY PHASE 1 | Zamboanga City 2nd DEO | ASAP GENERAL TRADING CONSTRUCTION & MAINTENANCEHHH DEVELOPER AND REAL ESTATE INC. | On-Going | ₱105.5M | 42% | High risk92 | Flagged0.077 |
| 24JA0163CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUTIK RIVER, (PUTIK SECTION), ZAMBOANGA CITY | Zamboanga City 2nd DEO | LAKEWOOD CONSTRUCTION COMPANY | On-Going | ₱88.1M | 34% | High risk90 | Flagged0.074 |
| 18J00148SANGA-SANGA AIRPORT DEVELOPMENT PROJECT, SANGA SANGA, BONGAO, TAWI-TAWI | Region IX | AL-SADIK CONSTRUCTION & ENTERPRISES, INC.VICENTE T. LAO CONSTRUCTION | On-Going | ₱320.9M | 65% | High risk63 | Flagged0.071 |
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE. | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24JA0147CONSTRUCTION OF 4STY12CL, PASONANCA NATIONAL HIGH SCHOOL, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Zamboanga City 2nd DEO | ATLANTIC ERECTORS, INC. | On-Going | ₱57.2M | 55% | High risk90 | Flagged0.069 |
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Zamboanga City 2nd DEO | LL CONSTRUCTIONTEDDIE CONSTRUCTION DEVELOPMENT, INC. | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 24JC0061CONSTRUCTION OF 4STY20CL, GALAS NHS, DIPOLOG CITY, ZAMBOANGA DEL NORTE | Zamboanga del Norte 2nd DEO | D' DREAMER DEVELOPMENT CORPORATIONABIB BUILDERS ENTERPRISE | On-Going | ₱53.6M | 32% | High risk88 | Flagged0.066 |
| 25JE0072CONCRETING OF BRGY. DEBOROK FMR, BRGY. DEBOROK, PAGADIAN, ZAMBOANGA DEL SUR, PAGADIAN CITY, ZAMBOANGA DEL SUR. | Zamboanga del Sur 1st DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱14.9M | 25% | High risk88 | Flagged0.065 |
| 24JA0176CONSTRUCTION OF DRAINAGE STRUCTURE AT TALON-TALON LOOP ROAD, BARANGAY TALON-TALON, ZAMBOANGA CITY | Zamboanga City 2nd DEO | AKMS CONSTRUCTION | On-Going | ₱28.9M | 67% | High risk89 | Flagged0.063 |
| 24JA0160CONSTRUCTION OF DRAINAGE STRUCTURE AT LUSTRE ROAD (SANTA CATALINA-ZONE IV) PACKAGE 1 ZAMBOANGA CITY | Zamboanga City 2nd DEO | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱38.6M | 70% | High risk88 | Flagged0.061 |
| 24J00260WESTERN MINDANAO STATE UNIVERSITY - CONSTRUCTION OF THREE (3) STOREY ACADEMIC BUILDING, WMSU IPIL CAMPUS | Region IX | MJMARI BUILDERS AND DEVELOPMENT CORPORATION (FORMERLY: MJMARI BUILDERS AND ENTERPRISES) | On-Going | ₱28M | 33% | High risk86 | Flagged0.061 |
| 24JG0075CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE II, VINCENZO SAGUN, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ILMW CONSTRUCTION & ENTERPRISES | On-Going | ₱19.8M | 37% | High risk87 | Flagged0.061 |
| 24JA0155REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD AT BARANGAY QUINIPUT, ZAMBOANGA CITY | Zamboanga City 2nd DEO | LL CONSTRUCTION | On-Going | ₱9.6M | 54% | High risk87 | Flagged0.061 |
| 24JA0171CONSTRUCTION OF DRAINAGE STRUCTURE AT TUGBUNGAN (MORNING BREEZE) TO BARANGAY TALON-TALON, PACKAGE 1, ZAMBOANGA CITY | Zamboanga City 2nd DEO | RCDG CONSTRUCTION CORPORATION | On-Going | ₱38.6M | 0% | High risk70 | Flagged0.061 |
| 24J00249CRISTINO M. PARAGAS MEMORIAL HOSPITAL, QUINIPUT, ZAMBOAN-GA CITY | Region IX | BENRAM CONSTRUCTION | On-Going | ₱144.8M | 18% | Medium risk58 | Flagged0.060 |
| 25JG0050CONCRETING OF BARANGAY TINA FMR, DUMALINAO, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱14.5M | 33% | High risk88 | Flagged0.060 |
| 23JA0080CONCRETING OF BRGY. VITALI FMR, BRGY. VITALI, ZAMBOANGA CITY | Zamboanga City 2nd DEO | JH CONSTRUCTION INC. | On-Going | ₱19.8M | 100% | High risk88 | Flagged0.060 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE. | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 25JE0071CONCRETING OF BRGY. SANTO ROSARIO FMR, BRGY. SANTO ROSARIO, RAMON MAGSAYSAY, ZAMBOANGA DEL SUR. | Zamboanga del Sur 1st DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱14.9M | 51% | High risk88 | Flagged0.058 |
Exhibit F · Evidence locker
Sorted by risk score.
| # | Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 401 | 24J00105SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY AYALA, ZAMBOANGA CITY | Region IX | RCDG CONSTRUCTION CORPORATIONJH CONSTRUCTION INC. | On-Going | ₱96.5M | 73% | High risk74 | —-0.011 |
| 402 | 20J00159CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES ACCESS ROAD AT SITIO ANULING, PAMUCUTAN TO STA. RITA IN SUPPORT OF HIGH VALUE CROPS (ABACA, CACAO, RUBBER AND COFFEE), UPPER LA PAZ, ZAMBOANGA CITY | Region IX | RCDG CONSTRUCTION CORPORATIONBENDIMIL CONSTRUCTION & DEVELOPMENT CORP. | On-Going | ₱167.4M | 100% | High risk74 | Flagged0.005 |
| 403 | 22J00057CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF UPPER TUNGAWAN FLOOD CONTROL STRUCTURE ALONG TUNGAWAN RIVER (PHASE IV), TUNGAWAN, ZAMBOANGA SIBUGAY | Region IX | 2M CONSTRUCTION & ENTERPRISES | On-Going | ₱105M | 81% | High risk74 | Flagged0.002 |
| 404 | 20J00035CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF UPPER TUNGAWAN FLOOD CONTROL ALONG TUNGAWAN RIVER (PHASE II), TUNGAWAN, ZAMBOANGA SIBUGAY | Region IX | MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION2M CONSTRUCTION & ENTERPRISES | On-Going | ₱99.6M | 100% | High risk74 | —-0.002 |
| 405 | 21J00018CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF UPPER TUNGAWAN FLOOD CONTROL ALONG TUNGAWAN RIVER (PHASE III), TUNGAWAN, ZAMBOANGA SIBUGAY | Region IX | 2M CONSTRUCTION & ENTERPRISES | On-Going | ₱103.9M | 100% | High risk74 | —-0.005 |
| 406 | 23J00041CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF UPPER TUNGAWAN FLOOD CONTROL STRUCTURE ALONG TUNGAWAN RIVER (PHASE V), TUNGAWAN, ZAMBOANGA SIBUGAY | Region IX | 2M CONSTRUCTION & ENTERPRISES | On-Going | ₱105.1M | 90% | High risk74 | —-0.010 |
| 407 | 25J00010CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG DIPOLOG RIVER, POBLACION NORTH SECTION, BARANGAY POBLACION NORTH, POLANCO, ZAMBOANGA DEL NORTE | Region IX | LONG ISLAND BUILDERS & CONSTRUCTIONDOMNPHIL CONSTRUCTION | On-Going | ₱153.7M | 95% | High risk74 | —-0.021 |
| 408 | 25J00009CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAYAWAN RIVER, DAPDAP BRIDGE UPSTREAM, POLANCO, ZAMBOANGA DEL NORTE | Region IX | LONG ISLAND BUILDERS & CONSTRUCTIONDOMNPHIL CONSTRUCTION | On-Going | ₱153.7M | 96% | High risk74 | —-0.021 |
| 409 | 24J00019CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DIPOLOG RIVER, (CONACON-GUINLES SECTION), POLANCO ZAMBOANGA DEL NORTE | Region IX | LONG ISLAND BUILDERS & CONSTRUCTIONDOMNPHIL CONSTRUCTION | Completed | ₱149.6M | 100% | High risk74 | —-0.054 |
| 410 | 24J00155CONSTRUCTION OF ROAD ALONG NRJ BARANGAY CAMUL - NRJ BARANGAY LUMBAYAO PACKAGE 2, ZAMBOANGA DEL NORTE | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | On-Going | ₱173.6M | 93% | High risk74 | —-0.018 |
| 411 | 21J00042WIDENING OF PERMANENT BRIDGES - LIMPAPA PARALLEL BRIDGE ALONG ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, LIMPAPA, ZAMBOANGA CITY | Region IX | A.T. DUMLAO CONSTRUCTION, INC. FORMERLYANDONI T. DHHH DEVELOPER AND CONSTRUCTION | On-Going | ₱144.4M | 100% | High risk74 | Flagged0.017 |
| 412 | 24J00005ROAD WIDENING - SECONDARY ROADS - ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD | Region IX | FIAT CONSTRUCTION SERVICESZAMBO J.A. BUILDERS | On-Going | ₱150.6M | 70% | High risk74 | —-0.016 |
| 413 | 17J00048CONSTRUCTION OF FLOOD CONTROL STRUCTURE (POBLACION SIDE) ALONG LAYAWAN RIVER, POLANCO, ZAMBOANGA DEL NORTE, BEG. OF PROJECT: 1 + 047.00, END OF PROJECT: 1 + 571.30, NET LENGTH: 524.30 LN.M. | Region IX | THREE W BUILDERS, INC. | Completed | ₱96.5M | 100% | High risk74 | —-0.028 |
| 414 | 24J00233CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MAGSAYSAY RIVER PHASE I RT LIM, ZAMBOANGA SIBUGAY | Zamboanga Sibugay 2nd DEO | BARILLO CONSTRUCTION AND ENTERPRISES | Completed | ₱95.5M | 100% | High risk74 | —-0.065 |
| 415 | 24JA0103FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BUSUGAN RIVER, SINUBONG, ZAMBOANGA CITY | Zamboanga City 2nd DEO | RCDG CONSTRUCTION CORPORATIONJH CONSTRUCTION INC. | On-Going | ₱96.4M | 90% | High risk74 | —-0.019 |
| 416 | 22J00073WIDENING OF PERMANENT BRIDGES - WIDENING OF SAN RAMON BRIDGE INCLUDING APPROACHES, ZAMBOANGA CITY | Region IX | BENDIMIL CONSTRUCTION & DEVELOPMENT CORP. | On-Going | ₱96.8M | 65% | High risk74 | Flagged0.012 |
| 417 | 23J00028CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION/ EXTENSION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (UPSTREAM), SIOCON, ZAMBOANGA DEL NORTE | Region IX | UNITEC BUILDER, INCORPORATED | On-Going | ₱105.1M | 100% | High risk74 | —-0.018 |
| 418 | 20J00030CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - EXTENSION OF FLOOD CONTROL STRUCTURE, ALONG SIOCON RIVER (UPSTREAM), SIOCON, ZAMBOANGA DEL NORTE | Region IX | UNITEC BUILDER, INCORPORATED | Completed | ₱99.2M | 100% | High risk74 | —-0.058 |
| 419 | 23J00063ROAD WIDENING - PRIMARY ROADS - PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | HHH DEVELOPER AND CONSTRUCTION | On-Going | ₱127.5M | 82% | High risk74 | —-0.020 |
| 420 | 18J00044CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - EXTENSION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (UPSTREAM), SIOCON, ZAMBOANGA DEL NORTE | Region IX | UNITEC BUILDER, INCORPORATED | Completed | ₱101.2M | 100% | High risk74 | —-0.061 |
| 421 | 23J00163REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - PAGADIAN CITY - ZAMBOANGA CITY RD - PACKAGE 3 | Region IX | RCDG CONSTRUCTION CORPORATIONHHH DEVELOPER AND CONSTRUCTION | On-Going | ₱144.6M | 70% | High risk74 | —-0.016 |
| 422 | 23J00169SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STUDS LIGHTS ALONG PAGADIAN CITY-ZAMBOANGA CITY RD, (LICOMO-PUTIK ROAD), ZAMBOANGA CITY | Region IX | RCDG CONSTRUCTION CORPORATIONHHH DEVELOPER AND CONSTRUCTION | On-Going | ₱144.6M | 85% | High risk74 | —-0.019 |
| 423 | 18J00021CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, CABALUAY - ZAMBOWOOD - MAMPANG SECTION, PACKAGE 2, INCLUDING RROW, ZAMBOANGA CITY | Region IX | ALRAF CONST. AND ENTERPRISES INC. (FORMERLY:ALRAF CONSTRUCTION & ENTERPRISES) | On-Going | ₱124.8M | 81% | High risk74 | Flagged0.007 |
| 424 | 20J00045CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROAD WIDENING ZAMBOANGA CITY DIVERSION ROAD, ZAMBOANGA CITY | Region IX | MIN CONSTRUCTION | Completed | ₱126.5M | 100% | High risk74 | —-0.055 |
| 425 | 18J00020CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, CABALUAY - ZAMBOWOOD - MAMPANG SECTION, PACKAGE 1, ZAMBOANGA CITY | Region IX | ALRAF CONST. AND ENTERPRISES INC. (FORMERLY:ALRAF CONSTRUCTION & ENTERPRISES) | Completed | ₱121M | 100% | High risk74 | —-0.065 |