Precinct report
Everything on file for this region, broken down by province, category and contractor.
Total projects
14,386
Total budget
₱406.4B
Average progress
92.7%
Completion rate
83.9%
Average risk score
45.9
Medium risk on average, out of 100
Flagged as unusual
336
2.3% of the region's projects
Risk mix
Exhibit A
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 5,821 | ₱138.9B | 43.4 | 98 | 92.1% |
| Roads | 4,028 | ₱82.7B | 43.8 | 9 | 93.7% |
| Flood Control and Drainage | 3,372 | ₱147.7B | 49.1 | 24 | 94.1% |
| Bridges | 446 | ₱12.6B | 45.0 | 7 | 91.4% |
| OTHER | 360 | ₱13.5B | 53.7 | 57 | 94.0% |
| GAA 2025 SSP | 184 | ₱5.7B | 90.2 | 125 | 66.6% |
| Water Provision and Storage | 104 | ₱402.4M | 26.7 | 1 | 98.1% |
| GAA 2025 OO-2 | 36 | ₱2.5B | 83.2 | 3 | 74.7% |
| GAA 2025 OO-1 | 31 | ₱1.9B | 89.5 | 11 | 68.2% |
| Bridges, Roads | 4 | ₱445.3M | 60.5 | 1 | 75.0% |
Exhibit B
| Province / DEO | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Metro Manila 1st DEO | 3,141 | ₱81B | 45.1 | 27 | 94.3% |
| Metro Manila 3rd DEO | 2,325 | ₱55.1B | 46.3 | 65 | 90.4% |
| Quezon City 1st DEO | 1,867 | ₱46.1B | 46.3 | 40 | 91.2% |
| North Manila DEO | 1,584 | ₱55B | 46.7 | 30 | 95.3% |
| Las Piñas-Muntinlupa DEO | 1,065 | ₱22.2B | 44.3 | 12 | 93.6% |
| Quezon City 2nd DEO | 1,053 | ₱27.3B | 44.6 | 24 | 93.7% |
| South Manila DEO | 1,053 | ₱26.5B | 43.8 | 21 | 94.6% |
| Metro Manila 2nd DEO | 1,048 | ₱24B | 46.5 | 17 | 92.4% |
| Malabon-Navotas DEO | 880 | ₱22.5B | 45.1 | 24 | 95.1% |
| National Capital Region | 370 | ₱46.7B | 56.8 | 76 | 71.9% |
Exhibit C
Joint-venture projects count toward each partner.
| Contractor | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| AARCON BUILDERS | 277 | ₱6B | 44.5 | 1 | 92.7% |
| TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) | 265 | ₱2.8B | 42.1 | 10 | 89.6% |
| IM CONSTRUCTION CORPORATION | 234 | ₱6.8B | 48.6 | 7 | 94.0% |
| ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) | 228 | ₱11B | 49.4 | 3 | 96.0% |
| ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196) | 218 | ₱10.4B | 48.8 | 1 | 95.9% |
| JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS | 210 | ₱4.4B | 46.0 | 9 | 92.4% |
| LE BRON CONSTRUCTION | 195 | ₱12.2B | 52.9 | 17 | 76.5% |
| B. VALENCERINA TRADING & CONSTRUCTION | 187 | ₱1.3B | 35.8 | 1 | 97.7% |
| FRAMECON BUILDERS | 184 | ₱2.9B | 45.2 | 5 | 86.2% |
| MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS | 171 | ₱8.6B | 51.3 | 2 | 94.3% |
| PHILIPPINE CHEMSTEEL INDUSTRIES, INC. | 169 | ₱4.8B | 46.5 | 1 | 99.5% |
| C.L. MORALES CONSTRUCTION AND TRADING | 155 | ₱1.7B | 41.3 | 0 | 90.3% |
| ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 40908) | 153 | ₱3B | 38.9 | 0 | 99.1% |
| E.L. TORRES CONSTRUCTION AND TRADING INC. (FORMERLY : E. L. TORRES CONSTRUCTION & TRADING | 142 | ₱3.6B | 47.0 | 1 | 93.9% |
| J. SIMEON CONSTRUCTION | 139 | ₱7.4B | 49.1 | 0 | 93.6% |
Exhibit D · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OE0077INSTALLATION OF SOLAR LED STREETLIGHTS AT A. RIVERA ST. - C000.00 TO C945.45, TAYUMAN ST. - K0007 + (-562.60) TO K0007 + 282 AND HERMOSA ST. - C000.00 TO C622.83, MANILA CITY | North Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱94.6M | 52% | High risk95 | Flagged0.023 |
| 25OE0068REHABILITATION OF DELPAN (MUELLE) PUMPING STATION, MANILA CITY | North Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱94.6M | 100% | High risk95 | Flagged0.007 |
| 25OG0097REHABILITATION OF ROAD, BARANGAY SAN ROQUE, QUEZON CITY | Quezon City 2nd DEO | TOPNOTCH CATALYST BUILDERS INC. | On-Going | ₱94.5M | 67% | High risk95 | Flagged0.018 |
| 25OE0076INSTALLATION OF SOLAR LED STREETLIGHTS AT QUIRICADA ST. - CHAINAGE 0 TO CHAINAGE 731.80, TAYUMAN ST. - K0007 + 299.0 TO K0008 + 000.00 AND MUELLE DELA INDUSTRIA ST. - K0003 + (-375) TO K0004 + 472, MANILA CITY | North Manila DEO | AL-AMEN BUILDERS | On-Going | ₱94.9M | 63% | High risk95 | Flagged0.021 |
| 25OH0046CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREET LIGHT ALONG NEW PANADEROS ST. FROM MANDALUYONG/MANILA BOUNDARY TO F. CALDERON ST., MANILA CITY | South Manila DEO | AL-AMEN BUILDERS | On-Going | ₱95.3M | 27% | High risk95 | Flagged0.028 |
| 25OH0100INSTALLATION OF SOLAR LED STREETLIGHTS WITHIN BARANGAYS 649 TO 828, PRES. QUIRINO AVE (FROM TAFT AVE. TO SOUTH SUPERHIGHWAY), SOUTH SUPERHIGHWAY (FROM ZOBEL ROXAS ST. TO P. QUIRINO AVE), P. FAURA ST. (SAN MARCELINO ST. TO ROXAS BLVD.), ESCODA ST. (FROM TA | South Manila DEO | AL-AMEN BUILDERS | On-Going | ₱145.2M | 40% | High risk95 | Flagged0.031 |
| 25OF0163REHABILITATION OF ROAD ALONG BARANGAY LAGRO, PACKAGE 1A, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱94.5M | 47% | High risk95 | Flagged0.026 |
| 25OB0353CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY WACKWACK PACKAGE 7, MANDALUYONG CITY | Metro Manila 1st DEO | VIRAC NRC CONSTRUCTION | On-Going | ₱97M | 55% | High risk95 | Flagged0.022 |
| 25OF0165REHABILITATION OF ROAD ALONG BARANGAY STA. MONICA, PACKAGE 1A, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱94.4M | 43% | High risk95 | Flagged0.026 |
| 25OF0157IMPROVEMENT OF DRAINAGE SYSTEMS AT BRGY. HOLY SPIRIT, QUEZON CITY | Quezon City 1st DEO | MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS | On-Going | ₱94.6M | 61% | High risk95 | Flagged0.022 |
| 25OE0083INSTALLATION OF SOLAR LED STREETLIGHTS ALONG NAGTAHAN FLYOVER (B03338LZ) AND MABINI BRIDGE (B01733LZ) INCLUDING APPROACHES, MANILA CITY | North Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱105.9M | 15% | High risk95 | Flagged0.037 |
| 25OH0047CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREETLIGHT WITHIN BRGY. 649 TO 828, RAILROAD ST (CHAINAGE 0 - 855), MURALLA ST (CHAINAGE 0 - 1355), GEN LUNA S | South Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱143.1M | 49% | High risk95 | Flagged0.030 |
| 25OC0079CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY LA HUERTA,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129) | On-Going | ₱94.6M | 15% | High risk95 | Flagged0.037 |
| 25OC0129CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER MOUTH (NORTH SIDE), PHASE 2,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | K84 CONSTRUCTION AND DEVELOPMENT CORPORATIONEGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) | On-Going | ₱94.6M | 18% | High risk95 | Flagged0.036 |
| 25OD0179REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BARANGAY 28 (PHASE 1), CALOOCAN CITY | Metro Manila 3rd DEO | AYLAN CONSTRUCTION & TRADING | On-Going | ₱48M | 51% | High risk95 | Flagged0.016 |
| 25OD0180REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BARANGAY 28 (PHASE 2), CALOOCAN CITY | Metro Manila 3rd DEO | AYLAN CONSTRUCTION & TRADING | On-Going | ₱48M | 58% | High risk95 | Flagged0.015 |
| 25OA0070CONSTRUCTION OF C-4 FLOOD GATE (PHASE 1), NAVOTAS CITY | Malabon-Navotas DEO | IM CONSTRUCTION CORPORATION | On-Going | ₱47.5M | 47% | High risk95 | Flagged0.016 |
| 25OF0162REHABILITATION OF ROAD ALONG BARANGAY BAGBAG, PACKAGE 1A, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱94.6M | 46% | High risk95 | Flagged0.026 |
| 25OF0136IMPROVEMENT OF ROADS AT BARANGAY LAGRO, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱97M | 51% | High risk95 | Flagged0.025 |
| 25OC0054CONSTRUCTION OF DRAINAGE MAIN ALONG ESTRELLA STREET FROM EDSA TOWARDS PASIG RIVER, BARANGAY GUADALUPE VIEJO,MAKATI CITY, METRO MANILA | Metro Manila 2nd DEO | TWO DIMENSION CONSTRUCTION | On-Going | ₱48.5M | 0% | High risk95 | Flagged0.028 |
Exhibit E · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23O00090PROPOSED DESIGN AND BUILD FOR THE CONSTRUCTION OF NEW FOOD AND DRUG ADMINISTRATION OFFICE | National Capital Region | KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱1.8B | 37% | High risk79 | Flagged0.087 |
| 20OG0117FUNDING REQUIREMENT FOR THE RESILIENCE INSTITUTE, U.P. DILIMAN, QUEZON CITY | Quezon City 2nd DEO | MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS | On-Going | ₱48.8M | 0% | High risk82 | Flagged0.082 |
| 19Z00038PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS) | National Capital Region | MSB VITUG CONSTRUCTIONMAC BUILDERS CORP. (FORMERLY: MAC BUILDERS DEVELOPMENT CORPORATION) | On-Going | ₱502.3M | 95% | High risk78 | Flagged0.078 |
| 23O00068CONSTRUCTION OF THE NBI MAIN BUILDING (PHASE I) | National Capital Region | ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762)TOPNOTCH CATALYST BUILDERS INC. | On-Going | ₱447.7M | 0% | Medium risk58 | Flagged0.071 |
| 18OG0133CONSTRUCTION OF FACULTY AND STAFF HOUSING, UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱193.3M | 0% | High risk65 | Flagged0.067 |
| 20O00077CONSTRUCTION OF BRIDGE ACROSS PARANAQUE RIVER ADJACENT TO THE PARANAQUE INTEGRATED TERMINAL EXCHANGE (PITX), DON GALO, PARANAQUE CITY | National Capital Region | J.H. PAJARA CONSTRUCTION CORPORATION | On-Going | ₱18.9M | 0% | Medium risk49 | Flagged0.066 |
| 23O00099CONSTRUCTION OF MULTI-PURPOSE BUILDING FOR JOINT-STAFF BILLETING | National Capital Region | SPIDERONE CONSTRUCTION COMPANY LTD. | On-Going | ₱609.5M | 0% | Medium risk57 | Flagged0.065 |
| 22O00090MANILA BAY REHABILITATION PROGRAM: CONSTRUCTION OF A SOLAR-POWERED SEWAGE TREATMENT PLANT ALONG THE LAS PIÑAS RIVER | National Capital Region | DRAGONHART CONSTRUCTION ENTERPRISE, INC.KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱199M | 76% | High risk77 | Flagged0.062 |
| 22O00113RENOVATION OF EXISTING FOOD AND DRUG ADMINISTRATION EXPERIMENTAL ANIMAL HOUSE (EAH) BUILDING TO BECOME VACCINE AND BIOLOGICAL TESTING LABORATORY | National Capital Region | MILES TRADING AND CONSTRUCTION | On-Going | ₱126.1M | 0% | Medium risk54 | Flagged0.062 |
| 18OG0140FUNDING FOR THE RESILIENCE INSTITUTE FOR DRRM, UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱388.1M | 39% | High risk65 | Flagged0.061 |
| 18OG0134REHABILITATION, RENOVATION, AND MODERNIZATION OF THE GONZALES HALL, UNIVERSITY LIBRARY, UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱401.9M | 48% | High risk64 | Flagged0.061 |
| 22O00092MANILA BAY REHABILITATION PROGRAM : CONSTRUCTION OF A SOLAR-POWERED STP - VITAS RIVER | National Capital Region | DRAGONHART CONSTRUCTION ENTERPRISE, INC.KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱222.9M | 88% | High risk77 | Flagged0.061 |
| 22O00091MANILA BAY REHABILITATION PROGRAM : CONSTRUCTION OF A SOLAR-POWERED STP - SAN JUAN RIVER | National Capital Region | DRAGONHART CONSTRUCTION ENTERPRISE, INC.KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱222.9M | 88% | High risk78 | Flagged0.061 |
| 20O00105CONSTRUCTION OF DRAINAGE SYSTEM/OUTFALL EXTENSION AT MANILA BAY | National Capital Region | PREMIUM MEGASTRUCTURES INC.DRAGONHART CONSTRUCTION ENTERPRISE, INC. | On-Going | ₱258.6M | 77% | High risk74 | Flagged0.057 |
| 24O00209CONSTRUCTION/COMPLETION OF NANGKA SUPER HEALTH CENTER | National Capital Region | JORDAN RIVER CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱5.8M | 0% | High risk80 | Flagged0.056 |
| 24O00207REPAIR/REHABILITATION OF CONCEPCION UNO SUPER HEALTH CENTER | National Capital Region | JORDAN RIVER CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱5.8M | 0% | High risk78 | Flagged0.056 |
| 24OA0086CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, NINOY AQUINO ELEMENTARY SCHOOL, MALABON CITY | Malabon-Navotas DEO | C.B. TAMPENGCO CONSTRUCTION & SUPPLY | On-Going | ₱42.9M | 51% | High risk74 | Flagged0.054 |
| 18O00026CONST. OF ONE UNIT TWELVE STOREY PNU CONVENTION AND TRAINING CENTER (PNUCTC) BUILDINGS (PHASE I) PNU COMPOUND, TAFT AVENUE, MANILA (PARTIAL CONSTRUCTION ONLY) | National Capital Region | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱226.1M | 70% | High risk64 | Flagged0.053 |
| 18OE0269CONSTRUCTION OF FOUR (4) STOREY TWENTY EIGHT (28) CLASSROOM SCHOOL BUILDING AT MABINI ELEMENTARY SCHOOL QUIAPO, MANILA CITY (BASED ON 2017 PLAN, REVISED 3-24-17) | North Manila DEO | SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC.G.F. FABIAN CONSTRUCTION | Completed | ₱221M | 100% | High risk71 | Flagged0.052 |
| 18OG0126CONSTRUCTION OF FACULTY CENTER (CAL), UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱576.9M | 88% | High risk65 | Flagged0.052 |
Exhibit F · Evidence locker
Sorted by risk score.
| # | Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 25OC0137CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | C.B. TAMPENGCO CONSTRUCTION & SUPPLY | On-Going | ₱19.4M | 5% | High risk93 | Flagged0.030 |
| 77 | 25OD0151REHABILITATION OF ROAD IN BARANGAY 177, CALOOCAN CITY | Metro Manila 3rd DEO | DARCY & ANNA BUILDERS & TRADING | On-Going | ₱28.9M | 34% | High risk93 | Flagged0.019 |
| 78 | 25OB0374CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY BAGONG SILANG, MANDALUYONG CITY, PHASE | Metro Manila 1st DEO | VIRAC NRC CONSTRUCTION | On-Going | ₱19.4M | 77% | High risk93 | Flagged0.008 |
| 79 | 25OA0031REHABILITATION OF ROAD, BANGUS ST., BARANGAY NBBS DAGAT-DAGATAN, NAVOTAS CITY | Malabon-Navotas DEO | TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) | On-Going | ₱14.4M | 83% | High risk93 | Flagged0.005 |
| 80 | 25OC0078CONSTRUCTION OF DRAINAGE SYSTEM (PHASE 2), BARANGAY STO. NIÑO,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | K84 CONSTRUCTION AND DEVELOPMENT CORPORATIONEGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) | On-Going | ₱68.1M | 92% | High risk93 | Flagged0.008 |
| 81 | 25OD0295CONSTRUCTION OF REINFORED CONCRETE BOX CULVERT ALONG 8TH STREET, CALOOCAN CITY (PHASE 2) | Metro Manila 3rd DEO | NOVA VENTUS CONSTRUCTION INC. | On-Going | ₱25.9M | 30% | High risk93 | Flagged0.018 |
| 82 | 25OD0071CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), AMPARO ROTONDA (PHASE 2), BARANGAY 179, CALOOCAN CITY | Metro Manila 3rd DEO | JOSE CRIS BUILDERS | On-Going | ₱50.7M | 8% | High risk93 | Flagged0.028 |
| 83 | 25OC0084REHABILITATION OF DRAINAGE SYSTEM AT STO. NINO STREET PHASE 2, BARANGAY MOONWALK,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | GRAC-TA BUILDERS | On-Going | ₱14.4M | 100% | High risk93 | —-0.001 |
| 84 | 25OC0072CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BF HOMES,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | GRAC-TA BUILDERS | On-Going | ₱9.9M | 100% | High risk93 | —-0.001 |
| 85 | 25OG0117REHABILITATION OF DRAINAGE SYSTEM, BRGY. WHITE PLAINS, QUEZON CITY | Quezon City 2nd DEO | LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR) | On-Going | ₱19.4M | 0% | High risk93 | Flagged0.028 |
| 86 | 25OD0041CONSTRUCTION OF ROAD AND DRAINAGE, BARANGAY 64, 65, 66, 67, CALOOCAN CITY | Metro Manila 3rd DEO | LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR) | On-Going | ₱14.4M | 74% | High risk93 | Flagged0.007 |
| 87 | 25OD0060CONSTRUCTION OF ROAD AND DRAINAGE ALONG 9TH STREET, BARANGAY 103, 101, 96, 93 & 92, CALOOCAN CITY | Metro Manila 3rd DEO | NOVA VENTUS CONSTRUCTION INC. | Completed | ₱26.4M | 100% | High risk93 | —-0.032 |
| 88 | 25OC0125REHABILITATION OF DRAINAGE SYSTEM AT LOPEZ VILLAGE (PHASE 2), BARANGAY SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | G.F. ROVERO MERCHANDISING | On-Going | ₱14.4M | 63% | High risk93 | Flagged0.015 |
| 89 | 25OF0205CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAUYO (KABAHAGI), QUEZON CITY | Quezon City 1st DEO | JE-JEI BUILDERS AND SUPPLY | On-Going | ₱19.4M | 86% | High risk93 | Flagged0.007 |
| 90 | 25OB0382CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING INCLUDING COVERED WALKWAY, STP AND ELECTRICAL FACILITIES AT MANDALUYONG COLLEGE OF SCIENCE AND TECHNOLOGY, MANDALUYONG CITY | Metro Manila 1st DEO | VIRAC NRC CONSTRUCTION | On-Going | ₱14.6M | 92% | High risk93 | Flagged0.001 |
| 91 | 25OE0125CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 198, ZONE 18, MANILA CITY | North Manila DEO | MACSTRENGTH CONSTRUCTION | On-Going | ₱14.6M | 55% | High risk93 | Flagged0.014 |
| 92 | 25OI0107REHABILITATION OF ROAD INCLUDING DRAINAGE AT BARANGAY PULANGLUPA 2, LAS PINAS CITY | Las Piñas-Muntinlupa DEO | MRJR CONSTRUCTION & TRADING | On-Going | ₱19.4M | 81% | High risk93 | Flagged0.010 |
| 93 | 25OC0136CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN DIONISIO,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | KING EIGHT BUILDERS AND SUPPLY | On-Going | ₱19.4M | 48% | High risk93 | Flagged0.019 |
| 94 | 25OF0198DRAINAGE IMPROVEMENT AND CONCRETING OF ROAD AT TORRES, BARANGAY TANDANG SORA, QUEZON CITY | Quezon City 1st DEO | C.E.M. CONSTRUCTION, INC. | On-Going | ₱19.2M | 54% | High risk93 | Flagged0.017 |
| 95 | 25OF0048CONSTRUCTION OF CONCRETE ROAD WITH DRAINAGE AT TIERRA BELLA, BARANGAY CULIAT, QUEZON CITY | Quezon City 1st DEO | C.E.M. CONSTRUCTION, INC. | On-Going | ₱38.8M | 16% | High risk93 | Flagged0.024 |
| 96 | 25OH0095RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-LAURA BR. (B01328LZ) ALONG LAURA ST | South Manila DEO | ANORE CONSTRUCTION | On-Going | ₱48.5M | 100% | High risk93 | —-0.022 |
| 97 | 25OH0094RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-SAN ANDRES BR. ALONG SN ANDRES ST. | South Manila DEO | ANORE CONSTRUCTION | On-Going | ₱48.5M | 100% | High risk93 | —-0.022 |
| 98 | 25OI0072REHABILITATION OF ROAD INCLUDING DRAINAGE, PULANGLUPA 2, LAS PINAS CITY LONE DISTRICT | Las Piñas-Muntinlupa DEO | RNN CONSTRUCTION CORPORATION (FORMERLY RNN CONSTRU | On-Going | ₱12.6M | 52% | High risk92 | Flagged0.017 |
| 99 | 25OD0037REHABILITATION OF ROAD AND DRAINAGE SYSTEM ALONG LIBIS ESPINA STREET, BARANGAYS. 14 AND 16, (PHASE 3), CALOOCAN CITY | Metro Manila 3rd DEO | DREAMWORX BUILDER & TRADING, INC. | On-Going | ₱9.6M | 34% | High risk92 | Flagged0.017 |
| 100 | 25OD0375CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3) | Metro Manila 3rd DEO | WAWAO BUILDERS | On-Going | ₱23.9M | 16% | High risk92 | Flagged0.025 |