Precinct report
Everything on file for this region, broken down by province, category and contractor.
Total projects
8,109
Total budget
₱197.7B
Average progress
94.2%
Completion rate
77.8%
Average risk score
44.2
Medium risk on average, out of 100
Flagged as unusual
618
7.6% of the region's projects
Risk mix
Exhibit A
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3,182 | ₱23.4B | 28.4 | 117 | 96.5% |
| Roads | 3,091 | ₱109B | 53.7 | 156 | 94.1% |
| Flood Control and Drainage | 706 | ₱34.6B | 57.7 | 40 | 92.9% |
| Bridges | 422 | ₱12.3B | 50.4 | 52 | 92.0% |
| Water Provision and Storage | 375 | ₱2.5B | 31.3 | 16 | 98.4% |
| OTHER | 187 | ₱9.5B | 79.3 | 124 | 83.6% |
| GAA 2025 SSP | 66 | ₱1.2B | 92.5 | 62 | 62.9% |
| GAA 2025 OO-1 | 52 | ₱2.7B | 92.5 | 40 | 52.8% |
| GAA 2025 OO-2 | 21 | ₱1.7B | 90.0 | 11 | 72.0% |
| Bridges, Roads | 7 | ₱837.7M | 69.2 | 0 | 79.8% |
Exhibit B
| Province / DEO | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 1,191 | ₱95.9B | 66.3 | 264 | 84.7% |
| Zamboanga del Sur 2nd DEO | 915 | ₱10B | 31.5 | 34 | 97.3% |
| Zamboanga del Sur 1st DEO | 894 | ₱14.2B | 41.6 | 27 | 96.7% |
| Zamboanga City 2nd DEO | 851 | ₱13.9B | 48.0 | 124 | 92.5% |
| Zamboanga Sibugay 2nd DEO | 818 | ₱10.5B | 37.0 | 23 | 97.0% |
| Zamboanga Sibugay 1st DEO | 782 | ₱13.6B | 41.9 | 22 | 92.2% |
| Zamboanga del Norte 1st DEO | 757 | ₱11.6B | 42.8 | 42 | 95.5% |
| Zamboanga del Norte 2nd DEO | 733 | ₱9.1B | 36.4 | 36 | 95.0% |
| Zamboanga del Norte 3rd DEO | 628 | ₱9.1B | 40.5 | 10 | 99.5% |
| Isabela City DEO | 404 | ₱6B | 42.1 | 15 | 99.0% |
| Zamboanga del Norte 4th DEO | 128 | ₱3.4B | 57.2 | 15 | 96.8% |
| Zamboanga City 1st DEO | 8 | ₱406.6M | 74.3 | 6 | 69.6% |
Exhibit C
Joint-venture projects count toward each partner.
Exhibit D · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25J00021PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) K1651+060.00 - K1653+244.03 | Region IX | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱109.1M | 83% | High risk96 | Flagged0.026 |
| 25J00104ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE | Region IX | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱153M | 79% | High risk96 | Flagged0.032 |
| 25J00037PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD), K1773+361.00 - K1775+181.00 | Region IX | BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE | On-Going | ₱107.2M | 31% | High risk96 | Flagged0.040 |
| 25JJ0028PREVENTIVE MAINTENANCE - SECONDARY ROADS ALONG SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD -(S01151MN) CHAINAGE 23548 - CHAINAGE 24284, CHAINAGE 24608 - CHAINAGE 26765, CHAINAGE 26793 - CHAINAGE 29000 | Zamboanga del Norte 4th DEO | BENRAM CONSTRUCTIONST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196) | On-Going | ₱83.8M | 97% | High risk95 | Flagged0.020 |
| 25JA0033CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT TIGBALABAG ELEM. SCHOOL, BRGY. TIGBALABAG, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ADZ ENGINEERING AND CONSTRUCTION | On-Going | ₱14.4M | 70% | High risk95 | Flagged0.024 |
| 25JA0027SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF DRAINAGE SYSTEM AT ADELAIDA HOMES TALON-TALON, BRGY. TALON-TALON, ZAMBOANGA CITY | Zamboanga City 2nd DEO | AKMS CONSTRUCTION | On-Going | ₱11.2M | 65% | High risk95 | Flagged0.026 |
| 25JE0012BIP- MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI- PURPOSE BUILDING, ZAMBOANGA DEL SUR | Zamboanga del Sur 1st DEO | KS AGAD CONSTRUCTION | On-Going | ₱14.8M | 84% | High risk95 | Flagged0.013 |
| 25JG0060MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TABINA, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ILMW CONSTRUCTION & ENTERPRISES | On-Going | ₱19.8M | 23% | High risk95 | Flagged0.036 |
| 25JB0059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239 INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROAD SIGNS, ROADWAY LIGHTING) ALONG PIÑAN - MUTIA RD - K1816+(-897) - K1839+409 | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱24.5M | 94% | High risk95 | Flagged0.012 |
| 25JB0061SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239 INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROAD SIGNS, ROADWAY LIGHTING) ALONG POLANCO-MACLEODES RD - K1828+(-225) - K1848+950 | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱24.5M | 97% | High risk95 | Flagged0.011 |
| 25JG0026BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF ROAD, PUROK YACAL - PUROK ACACIA, BARANGAY WALING-WALING, VINCENZO A. SAGUN, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱9.9M | 52% | High risk95 | Flagged0.027 |
| 25JB0048CONSTRUCTION OF MULTIPURPOSE BUILDING LINGASAD ELEMENTARY SCHOOL, BARANGAY LINGASAD, POLANCO, ZAMBOANGA DEL NORTE | Zamboanga del Norte 1st DEO | A.I.YU BUILDERS & ENTERPRISES | On-Going | ₱14.8M | 48% | High risk95 | Flagged0.026 |
| 25J00036PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | Region IX | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | On-Going | ₱78M | 50% | High risk95 | Flagged0.032 |
| 25JA0032CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT GUISAO ELEMENTARY SCHOOL, BRGY. GUISAO, ZAMBOANGA CITY | Zamboanga City 2nd DEO | ADZ ENGINEERING AND CONSTRUCTION | On-Going | ₱9.5M | 60% | High risk95 | Flagged0.028 |
| 25J00243PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | On-Going | ₱72.1M | 91% | High risk94 | —-0.000 |
| 25JE0024REPLACEMENT OF PERMANENT WEAK BRIDGES TUKURAN BR. (B01196MN) ALONG LANAO- PAGADIAN- ZAMBOANGA CITY RD. TUKURAN, ZAMBOANGA DEL SUR | Zamboanga del Sur 1st DEO | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱57.8M | 3% | High risk94 | Flagged0.023 |
| 25JG0015ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY GAWIL TO BARANGAY BOLISONG, KUMALARANG, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱49M | 67% | High risk94 | Flagged0.023 |
| 25J00052NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (TUCURAN JCT - KAROMATAN JCT RD) | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱153M | 31% | High risk94 | Flagged0.028 |
| 25JB0076CONSTRUCTION OF EVACUATION CENTER IN RIZAL, ZAMBOANGA DEL NORTE | Zamboanga del Norte 1st DEO | YUBROS CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱4.8M | 31% | High risk94 | Flagged0.030 |
| 25J00107ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO - PA-GADIAN - ZAMBOANGA CITY RD) | Region IX | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱91.3M | 18% | High risk94 | Flagged0.024 |
Exhibit E · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JK0004CONSTRUCTION OF ZAMBOANGA CITY R.T. LIM BOULEVARD, PACKAGE 1, ZAMBOANGA CITY | Zamboanga City 1st DEO | HHH DEVELOPER AND CONSTRUCTION | On-Going | ₱98.3M | 22% | High risk92 | Flagged0.083 |
| 24JA0161CONSTRUCTION OF WATER SYSTEM (LEVEL III), BARANGAY STA. MARIA TO MAMPANG, ZAMBOANGA CITY PHASE 1 | Zamboanga City 2nd DEO | ASAP GENERAL TRADING CONSTRUCTION & MAINTENANCEHHH DEVELOPER AND REAL ESTATE INC. | On-Going | ₱105.5M | 42% | High risk92 | Flagged0.077 |
| 24JA0163CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUTIK RIVER, (PUTIK SECTION), ZAMBOANGA CITY | Zamboanga City 2nd DEO | LAKEWOOD CONSTRUCTION COMPANY | On-Going | ₱88.1M | 34% | High risk90 | Flagged0.074 |
| 18J00148SANGA-SANGA AIRPORT DEVELOPMENT PROJECT, SANGA SANGA, BONGAO, TAWI-TAWI | Region IX | AL-SADIK CONSTRUCTION & ENTERPRISES, INC.VICENTE T. LAO CONSTRUCTION | On-Going | ₱320.9M | 65% | High risk63 | Flagged0.071 |
| 24J00304FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUB-LIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUC-TURE, TUMAGA RIVER (TUGBUNGAN SECTION), PACKAGE 3A, ZAM-BOANGA CITY | Region IX | PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE. | On-Going | ₱105.9M | 0% | High risk82 | Flagged0.069 |
| 24JA0147CONSTRUCTION OF 4STY12CL, PASONANCA NATIONAL HIGH SCHOOL, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Zamboanga City 2nd DEO | ATLANTIC ERECTORS, INC. | On-Going | ₱57.2M | 55% | High risk90 | Flagged0.069 |
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Zamboanga City 2nd DEO | LL CONSTRUCTIONTEDDIE CONSTRUCTION DEVELOPMENT, INC. | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 24JC0061CONSTRUCTION OF 4STY20CL, GALAS NHS, DIPOLOG CITY, ZAMBOANGA DEL NORTE | Zamboanga del Norte 2nd DEO | D' DREAMER DEVELOPMENT CORPORATIONABIB BUILDERS ENTERPRISE | On-Going | ₱53.6M | 32% | High risk88 | Flagged0.066 |
| 25JE0072CONCRETING OF BRGY. DEBOROK FMR, BRGY. DEBOROK, PAGADIAN, ZAMBOANGA DEL SUR, PAGADIAN CITY, ZAMBOANGA DEL SUR. | Zamboanga del Sur 1st DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱14.9M | 25% | High risk88 | Flagged0.065 |
| 24JA0176CONSTRUCTION OF DRAINAGE STRUCTURE AT TALON-TALON LOOP ROAD, BARANGAY TALON-TALON, ZAMBOANGA CITY | Zamboanga City 2nd DEO | AKMS CONSTRUCTION | On-Going | ₱28.9M | 67% | High risk89 | Flagged0.063 |
| 24JA0160CONSTRUCTION OF DRAINAGE STRUCTURE AT LUSTRE ROAD (SANTA CATALINA-ZONE IV) PACKAGE 1 ZAMBOANGA CITY | Zamboanga City 2nd DEO | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱38.6M | 70% | High risk88 | Flagged0.061 |
| 24J00260WESTERN MINDANAO STATE UNIVERSITY - CONSTRUCTION OF THREE (3) STOREY ACADEMIC BUILDING, WMSU IPIL CAMPUS | Region IX | MJMARI BUILDERS AND DEVELOPMENT CORPORATION (FORMERLY: MJMARI BUILDERS AND ENTERPRISES) | On-Going | ₱28M | 33% | High risk86 | Flagged0.061 |
| 24JG0075CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE II, VINCENZO SAGUN, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | ILMW CONSTRUCTION & ENTERPRISES | On-Going | ₱19.8M | 37% | High risk87 | Flagged0.061 |
| 24JA0155REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD AT BARANGAY QUINIPUT, ZAMBOANGA CITY | Zamboanga City 2nd DEO | LL CONSTRUCTION | On-Going | ₱9.6M | 54% | High risk87 | Flagged0.061 |
| 24JA0171CONSTRUCTION OF DRAINAGE STRUCTURE AT TUGBUNGAN (MORNING BREEZE) TO BARANGAY TALON-TALON, PACKAGE 1, ZAMBOANGA CITY | Zamboanga City 2nd DEO | RCDG CONSTRUCTION CORPORATION | On-Going | ₱38.6M | 0% | High risk70 | Flagged0.061 |
| 24J00249CRISTINO M. PARAGAS MEMORIAL HOSPITAL, QUINIPUT, ZAMBOAN-GA CITY | Region IX | BENRAM CONSTRUCTION | On-Going | ₱144.8M | 18% | Medium risk58 | Flagged0.060 |
| 25JG0050CONCRETING OF BARANGAY TINA FMR, DUMALINAO, ZAMBOANGA DEL SUR | Zamboanga del Sur 2nd DEO | GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) | On-Going | ₱14.5M | 33% | High risk88 | Flagged0.060 |
| 23JA0080CONCRETING OF BRGY. VITALI FMR, BRGY. VITALI, ZAMBOANGA CITY | Zamboanga City 2nd DEO | JH CONSTRUCTION INC. | On-Going | ₱19.8M | 100% | High risk88 | Flagged0.060 |
| 24J00284CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 | Region IX | PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE. | On-Going | ₱96.2M | 62% | High risk81 | Flagged0.059 |
| 25JE0071CONCRETING OF BRGY. SANTO ROSARIO FMR, BRGY. SANTO ROSARIO, RAMON MAGSAYSAY, ZAMBOANGA DEL SUR. | Zamboanga del Sur 1st DEO | ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION | On-Going | ₱14.9M | 51% | High risk88 | Flagged0.058 |
Exhibit F · Evidence locker
Sorted by risk score.
| # | Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 351 | 18JI0072CONSTRUCTION OF BRIDGE AND ROAD APPROACHES, BRGY. CONCEPCION, ALICIA, Z.S | Zamboanga Sibugay 1st DEO | ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) | Completed | ₱44.9M | 100% | High risk75 | —-0.012 |
| 352 | 17JI0007ROAD WIDENING INCLUDING DRAINAGE ALONG JCT. IMELDA- ALICIA ROAD, K1766+550.40 - K1768+029 | Zamboanga Sibugay 1st DEO | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | Completed | ₱46.2M | 100% | High risk75 | —-0.023 |
| 353 | 17JI0018CONSTRUCTION/EXTENSION OF FLOOD CONTROL STRUCTURE ALONG SIBUGUEY RIVER, STA. 01+320 - STA. 01+841 UPSTREAM, BULAWAN, PAVAO, ZAMBOANGA SIBUGAY 1ST LD | Zamboanga Sibugay 1st DEO | RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R | Completed | ₱42M | 100% | High risk75 | —-0.025 |
| 354 | 21J00044CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ESPLANADE AT LIMPAPA RIVER, ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD (LIMPAPA BRIDGE SECTION) | Region IX | RCDG CONSTRUCTION CORPORATIONHHH DEVELOPER AND CONSTRUCTION | On-Going | ₱95.7M | 100% | High risk75 | —-0.006 |
| 355 | 23J00054CONSTRUCTION OF DETENTION TANK 1 WITH PUMPING STATION, ZAMBOANGA CITY (PHASE I) | Region IX | ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762) | On-Going | ₱104.8M | 59% | High risk75 | Flagged0.001 |
| 356 | 23J00055CONSTRUCTION OF DETENTION TANK 2, WATER TREATMENT PLANT FACILITIES WITH FLOODGATE AND PUMPING STATION 2, ZAMBOANGA CITY, CATCHMENT 1 (PHASE II) | Region IX | BENDIMIL CONSTRUCTION & DEVELOPMENT CORP. | On-Going | ₱115.6M | 60% | High risk75 | Flagged0.001 |
| 357 | 24J00008CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BUENAVISTA - BOLONG BY-PASS ROAD, PACKAGE 12, ZAMBOANGA CITY | Region IX | 2M CONSTRUCTION & ENTERPRISES | On-Going | ₱154.1M | 90% | High risk75 | —-0.022 |
| 358 | 23J00104CONSTRUCTION OF NEW BRIDGES - LIBA BRIDGE ALONG SINDANGAN-BAYOG-LAKEWOOD ROAD (PHASE II) | Region IX | VICTORIANO C. LIM CONSTRUCTION CORPORATION (FORMERLY: VICTORIANO C. LIM CONSTRUCTION) | On-Going | ₱144M | 54% | High risk75 | —-0.004 |
| 359 | 22J00075CONSTRUCTION OF FLYOVERS/ INTERCHANGES/ UNDERPASSES/ LONG SPAN BRIDGES - GOV. CAMINS/MCLL HIGHWAY AND VETERAN AVE. FLYOVER | Region IX | FREY-FIL CORPORATION (FORMERLY:FREYSSINET FILIPINA | On-Going | ₱127.8M | 26% | High risk75 | Flagged0.028 |
| 360 | 22J00078CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION (PACKAGE 1 & 2) | Region IX | PRIMETECH CONSTRUCTION AND TRADINGWTG CONSTRUCTION & DEVELOPMENT CORPORATION | On-Going | ₱113.2M | 60% | High risk75 | Flagged0.011 |
| 361 | 23JF0047CONSTRUCTION OF SHORELINE PROTECTION, BARANGAY LINGUISAN, TUNGAWAN, ZAMBOANGA SIBUGAY PACKAGE 1 | Zamboanga Sibugay 2nd DEO | RCDG CONSTRUCTION CORPORATIONHHH DEVELOPER AND CONSTRUCTION | On-Going | ₱144.6M | 97% | High risk75 | —-0.008 |
| 362 | 23JF0048CONSTRUCTION OF SHORELINE PROTECTION, BARANGAY PRESIDENT ROXAS, R.T. LIM, ZAMBOANGA SIBUGAY PACKAGE 1 | Zamboanga Sibugay 2nd DEO | ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958)HHH DEVELOPER AND REAL ESTATE INC. | On-Going | ₱144.7M | 98% | High risk75 | —-0.011 |
| 363 | 23J00173ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MANGUSU-MUTI COASTAL ROAD, PACKAGE 1, ZAMBOANGA CITY | Region IX | JAMARI CONSTRUCTION (FORMERLY FRAE CONSTRUCTION)ZAMBO J.A. BUILDERS | On-Going | ₱144.2M | 61% | High risk75 | —-0.011 |
| 364 | 25J00016CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (UPSTREAM), PACKAGE 6, SIOCON, ZAMBOANGA DEL NORTE | Region IX | BENRAM CONSTRUCTIONST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 40908) | On-Going | ₱149.5M | 41% | High risk75 | —-0.004 |
| 365 | 25JK0028CONSTRUCTION OF FLOOD MITIGATION PROJECT (PHASE 2) IN BARANGAY PASONANCA, ZAMBOANGA CITY | Zamboanga City 1st DEO | ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) | On-Going | ₱95M | 72% | High risk75 | —-0.017 |
| 366 | 24J00144SIPAG - FLOOD MITIGATION STRUCTURES - PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF WATER TREATMENT PLANT FACILITY WITH FLOODGATE & PUMPING STATION, CATCHMENT 1 (PHASE 2), ZAMBOANGA CITY | Region IX | BENDIMIL CONSTRUCTION & DEVELOPMENT CORP. | On-Going | ₱96.4M | 0% | High risk75 | Flagged0.005 |
| 367 | 20J00157CONSTRUCTION OF BY- PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD,(WEST COAST SECTION), ZAMBOANGA CITY | Region IX | UNITEC BUILDER, INCORPORATED | Completed | ₱141.8M | 100% | High risk75 | —-0.052 |
| 368 | 18J00007CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES, GOVERNOR CAMINS/MCLL HIGHWAY AND VETERANS AVENUE FLYOVER INCLUDING ROW, ZAMBOANGA CITY | Region IX | FREY-FIL CORPORATION (FORMERLY:FREYSSINET FILIPINA | On-Going | ₱233.3M | 57% | High risk75 | Flagged0.056 |
| 369 | 22J00088CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, PACKAGE 3, ZAMBOANGA CITY | Region IX | BENDIMIL CONSTRUCTION & DEVELOPMENT CORP. | On-Going | ₱94.6M | 19% | High risk75 | Flagged0.031 |
| 370 | 21J00052CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL AT TUMAGA RIVER BASIN, ZAMBOANGA CITY | Region IX | ROAD EDGE TRADING & DEVELOPMENT SERVICES | On-Going | ₱105.1M | 100% | High risk75 | —-0.003 |
| 371 | 20J00004CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY - PASS ROAD, (CULIANAN - PATALON SECTION), PACKAGE 3, ZAMBOANGA CITY | Region IX | RABBIT CONSTRUCTION & DEVELOPMENT CORPORATIONPRIMETECH CONSTRUCTION AND TRADING | Completed | ₱141.1M | 100% | High risk74 | —-0.050 |
| 372 | 23J00137CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TICTAPUL RIVER, BARANGAY TICTAPUL, ZAMBOANGA CITY | Region IX | RCDG CONSTRUCTION CORPORATIONHHH DEVELOPER AND CONSTRUCTION | On-Going | ₱130.2M | 81% | High risk74 | —-0.005 |
| 373 | 23J00073CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANICAHAN RIVER, MANICAHAN BR. SECTION (B00574MN) ALONG PAGADIAN CITY - ZAMBOANGA CITY ROAD (S01315MN), BARANGAY MANICAHAN, ZAMBOA | Region IX | ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)YN BUILDERS AND SUPPLY | On-Going | ₱96.5M | 91% | High risk74 | —-0.011 |
| 374 | 24J00034CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (DOWNSTREAM), SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 2 | Region IX | LONG ISLAND BUILDERS & CONSTRUCTION | On-Going | ₱137.9M | 100% | High risk74 | —-0.019 |
| 375 | 18J00022CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, CABALUAY - ZAMBOWOOD - MAMPANG SECTION, PACKAGE 3, INCLUDING RROW, ZAMBOANGA CITY | Region IX | ALRAF CONST. AND ENTERPRISES INC. (FORMERLY:ALRAF CONSTRUCTION & ENTERPRISES) | On-Going | ₱133.7M | 74% | High risk74 | Flagged0.011 |