Precinct report
Everything on file for this region, broken down by province, category and contractor.
Total projects
14,386
Total budget
₱406.4B
Average progress
92.7%
Completion rate
83.9%
Average risk score
45.9
Medium risk on average, out of 100
Flagged as unusual
336
2.3% of the region's projects
Risk mix
Exhibit A
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 5,821 | ₱138.9B | 43.4 | 98 | 92.1% |
| Roads | 4,028 | ₱82.7B | 43.8 | 9 | 93.7% |
| Flood Control and Drainage | 3,372 | ₱147.7B | 49.1 | 24 | 94.1% |
| Bridges | 446 | ₱12.6B | 45.0 | 7 | 91.4% |
| OTHER | 360 | ₱13.5B | 53.7 | 57 | 94.0% |
| GAA 2025 SSP | 184 | ₱5.7B | 90.2 | 125 | 66.6% |
| Water Provision and Storage | 104 | ₱402.4M | 26.7 | 1 | 98.1% |
| GAA 2025 OO-2 | 36 | ₱2.5B | 83.2 | 3 | 74.7% |
| GAA 2025 OO-1 | 31 | ₱1.9B | 89.5 | 11 | 68.2% |
| Bridges, Roads | 4 | ₱445.3M | 60.5 | 1 | 75.0% |
Exhibit B
| Province / DEO | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Metro Manila 1st DEO | 3,141 | ₱81B | 45.1 | 27 | 94.3% |
| Metro Manila 3rd DEO | 2,325 | ₱55.1B | 46.3 | 65 | 90.4% |
| Quezon City 1st DEO | 1,867 | ₱46.1B | 46.3 | 40 | 91.2% |
| North Manila DEO | 1,584 | ₱55B | 46.7 | 30 | 95.3% |
| Las Piñas-Muntinlupa DEO | 1,065 | ₱22.2B | 44.3 | 12 | 93.6% |
| Quezon City 2nd DEO | 1,053 | ₱27.3B | 44.6 | 24 | 93.7% |
| South Manila DEO | 1,053 | ₱26.5B | 43.8 | 21 | 94.6% |
| Metro Manila 2nd DEO | 1,048 | ₱24B | 46.5 | 17 | 92.4% |
| Malabon-Navotas DEO | 880 | ₱22.5B | 45.1 | 24 | 95.1% |
| National Capital Region | 370 | ₱46.7B | 56.8 | 76 | 71.9% |
Exhibit C
Joint-venture projects count toward each partner.
| Contractor | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| AARCON BUILDERS | 277 | ₱6B | 44.5 | 1 | 92.7% |
| TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) | 265 | ₱2.8B | 42.1 | 10 | 89.6% |
| IM CONSTRUCTION CORPORATION | 234 | ₱6.8B | 48.6 | 7 | 94.0% |
| ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) | 228 | ₱11B | 49.4 | 3 | 96.0% |
| ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196) | 218 | ₱10.4B | 48.8 | 1 | 95.9% |
| JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS | 210 | ₱4.4B | 46.0 | 9 | 92.4% |
| LE BRON CONSTRUCTION | 195 | ₱12.2B | 52.9 | 17 | 76.5% |
| B. VALENCERINA TRADING & CONSTRUCTION | 187 | ₱1.3B | 35.8 | 1 | 97.7% |
| FRAMECON BUILDERS | 184 | ₱2.9B | 45.2 | 5 | 86.2% |
| MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS | 171 | ₱8.6B | 51.3 | 2 | 94.3% |
| PHILIPPINE CHEMSTEEL INDUSTRIES, INC. | 169 | ₱4.8B | 46.5 | 1 | 99.5% |
| C.L. MORALES CONSTRUCTION AND TRADING | 155 | ₱1.7B | 41.3 | 0 | 90.3% |
| ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 40908) | 153 | ₱3B | 38.9 | 0 | 99.1% |
| E.L. TORRES CONSTRUCTION AND TRADING INC. (FORMERLY : E. L. TORRES CONSTRUCTION & TRADING | 142 | ₱3.6B | 47.0 | 1 | 93.9% |
| J. SIMEON CONSTRUCTION | 139 | ₱7.4B | 49.1 | 0 | 93.6% |
Exhibit D · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OE0077INSTALLATION OF SOLAR LED STREETLIGHTS AT A. RIVERA ST. - C000.00 TO C945.45, TAYUMAN ST. - K0007 + (-562.60) TO K0007 + 282 AND HERMOSA ST. - C000.00 TO C622.83, MANILA CITY | North Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱94.6M | 52% | High risk95 | Flagged0.023 |
| 25OE0068REHABILITATION OF DELPAN (MUELLE) PUMPING STATION, MANILA CITY | North Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱94.6M | 100% | High risk95 | Flagged0.007 |
| 25OG0097REHABILITATION OF ROAD, BARANGAY SAN ROQUE, QUEZON CITY | Quezon City 2nd DEO | TOPNOTCH CATALYST BUILDERS INC. | On-Going | ₱94.5M | 67% | High risk95 | Flagged0.018 |
| 25OE0076INSTALLATION OF SOLAR LED STREETLIGHTS AT QUIRICADA ST. - CHAINAGE 0 TO CHAINAGE 731.80, TAYUMAN ST. - K0007 + 299.0 TO K0008 + 000.00 AND MUELLE DELA INDUSTRIA ST. - K0003 + (-375) TO K0004 + 472, MANILA CITY | North Manila DEO | AL-AMEN BUILDERS | On-Going | ₱94.9M | 63% | High risk95 | Flagged0.021 |
| 25OH0046CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREET LIGHT ALONG NEW PANADEROS ST. FROM MANDALUYONG/MANILA BOUNDARY TO F. CALDERON ST., MANILA CITY | South Manila DEO | AL-AMEN BUILDERS | On-Going | ₱95.3M | 27% | High risk95 | Flagged0.028 |
| 25OH0100INSTALLATION OF SOLAR LED STREETLIGHTS WITHIN BARANGAYS 649 TO 828, PRES. QUIRINO AVE (FROM TAFT AVE. TO SOUTH SUPERHIGHWAY), SOUTH SUPERHIGHWAY (FROM ZOBEL ROXAS ST. TO P. QUIRINO AVE), P. FAURA ST. (SAN MARCELINO ST. TO ROXAS BLVD.), ESCODA ST. (FROM TA | South Manila DEO | AL-AMEN BUILDERS | On-Going | ₱145.2M | 40% | High risk95 | Flagged0.031 |
| 25OF0163REHABILITATION OF ROAD ALONG BARANGAY LAGRO, PACKAGE 1A, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱94.5M | 47% | High risk95 | Flagged0.026 |
| 25OB0353CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY WACKWACK PACKAGE 7, MANDALUYONG CITY | Metro Manila 1st DEO | VIRAC NRC CONSTRUCTION | On-Going | ₱97M | 55% | High risk95 | Flagged0.022 |
| 25OF0165REHABILITATION OF ROAD ALONG BARANGAY STA. MONICA, PACKAGE 1A, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱94.4M | 43% | High risk95 | Flagged0.026 |
| 25OF0157IMPROVEMENT OF DRAINAGE SYSTEMS AT BRGY. HOLY SPIRIT, QUEZON CITY | Quezon City 1st DEO | MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS | On-Going | ₱94.6M | 61% | High risk95 | Flagged0.022 |
| 25OE0083INSTALLATION OF SOLAR LED STREETLIGHTS ALONG NAGTAHAN FLYOVER (B03338LZ) AND MABINI BRIDGE (B01733LZ) INCLUDING APPROACHES, MANILA CITY | North Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱105.9M | 15% | High risk95 | Flagged0.037 |
| 25OH0047CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREETLIGHT WITHIN BRGY. 649 TO 828, RAILROAD ST (CHAINAGE 0 - 855), MURALLA ST (CHAINAGE 0 - 1355), GEN LUNA S | South Manila DEO | JIIK CONSTRUCTION SERVICES | On-Going | ₱143.1M | 49% | High risk95 | Flagged0.030 |
| 25OC0079CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY LA HUERTA,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129) | On-Going | ₱94.6M | 15% | High risk95 | Flagged0.037 |
| 25OC0129CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER MOUTH (NORTH SIDE), PHASE 2,PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | K84 CONSTRUCTION AND DEVELOPMENT CORPORATIONEGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) | On-Going | ₱94.6M | 18% | High risk95 | Flagged0.036 |
| 25OD0179REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BARANGAY 28 (PHASE 1), CALOOCAN CITY | Metro Manila 3rd DEO | AYLAN CONSTRUCTION & TRADING | On-Going | ₱48M | 51% | High risk95 | Flagged0.016 |
| 25OD0180REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BARANGAY 28 (PHASE 2), CALOOCAN CITY | Metro Manila 3rd DEO | AYLAN CONSTRUCTION & TRADING | On-Going | ₱48M | 58% | High risk95 | Flagged0.015 |
| 25OA0070CONSTRUCTION OF C-4 FLOOD GATE (PHASE 1), NAVOTAS CITY | Malabon-Navotas DEO | IM CONSTRUCTION CORPORATION | On-Going | ₱47.5M | 47% | High risk95 | Flagged0.016 |
| 25OF0162REHABILITATION OF ROAD ALONG BARANGAY BAGBAG, PACKAGE 1A, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱94.6M | 46% | High risk95 | Flagged0.026 |
| 25OF0136IMPROVEMENT OF ROADS AT BARANGAY LAGRO, QUEZON CITY | Quezon City 1st DEO | LE BRON CONSTRUCTION | On-Going | ₱97M | 51% | High risk95 | Flagged0.025 |
| 25OC0054CONSTRUCTION OF DRAINAGE MAIN ALONG ESTRELLA STREET FROM EDSA TOWARDS PASIG RIVER, BARANGAY GUADALUPE VIEJO,MAKATI CITY, METRO MANILA | Metro Manila 2nd DEO | TWO DIMENSION CONSTRUCTION | On-Going | ₱48.5M | 0% | High risk95 | Flagged0.028 |
Exhibit E · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23O00090PROPOSED DESIGN AND BUILD FOR THE CONSTRUCTION OF NEW FOOD AND DRUG ADMINISTRATION OFFICE | National Capital Region | KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱1.8B | 37% | High risk79 | Flagged0.087 |
| 20OG0117FUNDING REQUIREMENT FOR THE RESILIENCE INSTITUTE, U.P. DILIMAN, QUEZON CITY | Quezon City 2nd DEO | MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS | On-Going | ₱48.8M | 0% | High risk82 | Flagged0.082 |
| 19Z00038PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS) | National Capital Region | MSB VITUG CONSTRUCTIONMAC BUILDERS CORP. (FORMERLY: MAC BUILDERS DEVELOPMENT CORPORATION) | On-Going | ₱502.3M | 95% | High risk78 | Flagged0.078 |
| 23O00068CONSTRUCTION OF THE NBI MAIN BUILDING (PHASE I) | National Capital Region | ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762)TOPNOTCH CATALYST BUILDERS INC. | On-Going | ₱447.7M | 0% | Medium risk58 | Flagged0.071 |
| 18OG0133CONSTRUCTION OF FACULTY AND STAFF HOUSING, UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱193.3M | 0% | High risk65 | Flagged0.067 |
| 20O00077CONSTRUCTION OF BRIDGE ACROSS PARANAQUE RIVER ADJACENT TO THE PARANAQUE INTEGRATED TERMINAL EXCHANGE (PITX), DON GALO, PARANAQUE CITY | National Capital Region | J.H. PAJARA CONSTRUCTION CORPORATION | On-Going | ₱18.9M | 0% | Medium risk49 | Flagged0.066 |
| 23O00099CONSTRUCTION OF MULTI-PURPOSE BUILDING FOR JOINT-STAFF BILLETING | National Capital Region | SPIDERONE CONSTRUCTION COMPANY LTD. | On-Going | ₱609.5M | 0% | Medium risk57 | Flagged0.065 |
| 22O00090MANILA BAY REHABILITATION PROGRAM: CONSTRUCTION OF A SOLAR-POWERED SEWAGE TREATMENT PLANT ALONG THE LAS PIÑAS RIVER | National Capital Region | DRAGONHART CONSTRUCTION ENTERPRISE, INC.KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱199M | 76% | High risk77 | Flagged0.062 |
| 22O00113RENOVATION OF EXISTING FOOD AND DRUG ADMINISTRATION EXPERIMENTAL ANIMAL HOUSE (EAH) BUILDING TO BECOME VACCINE AND BIOLOGICAL TESTING LABORATORY | National Capital Region | MILES TRADING AND CONSTRUCTION | On-Going | ₱126.1M | 0% | Medium risk54 | Flagged0.062 |
| 18OG0140FUNDING FOR THE RESILIENCE INSTITUTE FOR DRRM, UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱388.1M | 39% | High risk65 | Flagged0.061 |
| 18OG0134REHABILITATION, RENOVATION, AND MODERNIZATION OF THE GONZALES HALL, UNIVERSITY LIBRARY, UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱401.9M | 48% | High risk64 | Flagged0.061 |
| 22O00092MANILA BAY REHABILITATION PROGRAM : CONSTRUCTION OF A SOLAR-POWERED STP - VITAS RIVER | National Capital Region | DRAGONHART CONSTRUCTION ENTERPRISE, INC.KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱222.9M | 88% | High risk77 | Flagged0.061 |
| 22O00091MANILA BAY REHABILITATION PROGRAM : CONSTRUCTION OF A SOLAR-POWERED STP - SAN JUAN RIVER | National Capital Region | DRAGONHART CONSTRUCTION ENTERPRISE, INC.KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱222.9M | 88% | High risk78 | Flagged0.061 |
| 20O00105CONSTRUCTION OF DRAINAGE SYSTEM/OUTFALL EXTENSION AT MANILA BAY | National Capital Region | PREMIUM MEGASTRUCTURES INC.DRAGONHART CONSTRUCTION ENTERPRISE, INC. | On-Going | ₱258.6M | 77% | High risk74 | Flagged0.057 |
| 24O00209CONSTRUCTION/COMPLETION OF NANGKA SUPER HEALTH CENTER | National Capital Region | JORDAN RIVER CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱5.8M | 0% | High risk80 | Flagged0.056 |
| 24O00207REPAIR/REHABILITATION OF CONCEPCION UNO SUPER HEALTH CENTER | National Capital Region | JORDAN RIVER CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱5.8M | 0% | High risk78 | Flagged0.056 |
| 24OA0086CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, NINOY AQUINO ELEMENTARY SCHOOL, MALABON CITY | Malabon-Navotas DEO | C.B. TAMPENGCO CONSTRUCTION & SUPPLY | On-Going | ₱42.9M | 51% | High risk74 | Flagged0.054 |
| 18O00026CONST. OF ONE UNIT TWELVE STOREY PNU CONVENTION AND TRAINING CENTER (PNUCTC) BUILDINGS (PHASE I) PNU COMPOUND, TAFT AVENUE, MANILA (PARTIAL CONSTRUCTION ONLY) | National Capital Region | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱226.1M | 70% | High risk64 | Flagged0.053 |
| 18OE0269CONSTRUCTION OF FOUR (4) STOREY TWENTY EIGHT (28) CLASSROOM SCHOOL BUILDING AT MABINI ELEMENTARY SCHOOL QUIAPO, MANILA CITY (BASED ON 2017 PLAN, REVISED 3-24-17) | North Manila DEO | SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC.G.F. FABIAN CONSTRUCTION | Completed | ₱221M | 100% | High risk71 | Flagged0.052 |
| 18OG0126CONSTRUCTION OF FACULTY CENTER (CAL), UP DILIMAN, QUEZON CITY | Quezon City 2nd DEO | FLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATIONM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT | On-Going | ₱576.9M | 88% | High risk65 | Flagged0.052 |
Exhibit F · Evidence locker
Sorted by risk score.
| # | Contract | Province / DEO | Contractor | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 601 | 25OE0064CONSTRUCTION OF RETARDING BASIN AT ESTERO DE BINONDO, PHASE II, MANILA CITY | North Manila DEO | EIGHT J'S CONSTRUCTION SERVICESJROSWELL CONSTRUCTION SERVICES | On-Going | ₱94.7M | 56% | High risk65 | —-0.036 |
| 602 | 24OB0185CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 1), TAGUIG CITY | Metro Manila 1st DEO | DAHL CONSTRUCTION CORP. (FORMERLY: DAHL CONSTRUCTION) | On-Going | ₱94.6M | 100% | High risk65 | —-0.044 |
| 603 | 25OB0130CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 2), TAGUIG CITY | Metro Manila 1st DEO | TOUGHBUILT CONSTRUCTION & TRADING, INC. | On-Going | ₱94.6M | 100% | High risk65 | —-0.051 |
| 604 | 25OE0029INSTALLATION OF BOOSTER PUMP AND ACCESSORIES ALONG ESTERO DELA REINA, MANILA CITY | North Manila DEO | EIGHT J'S CONSTRUCTION SERVICES4 J'S CONSTRUCTION SERVICES | Completed | ₱94.7M | 100% | High risk65 | —-0.075 |
| 605 | 25OB0125CONSTRUCTION OF SLOPE PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 15), TAGUIG CITY | Metro Manila 1st DEO | RVR3 CONSTRUCTION SUPPLY AND SERVICES | Completed | ₱94.5M | 100% | High risk65 | —-0.077 |
| 606 | 19OF0151CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG MARIKINA RIVER (STA. 19+550 TO 19+700), BRGY. BATASAN HILLS, QUEZON CITY | Quezon City 1st DEO | IM CONSTRUCTION CORPORATION | Completed | ₱95.1M | 100% | High risk65 | —-0.070 |
| 607 | 24OB0214CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 2) | Metro Manila 1st DEO | DAHL CONSTRUCTION CORP. (FORMERLY: DAHL CONSTRUCTION) | Completed | ₱125.8M | 100% | High risk65 | —-0.069 |
| 608 | 24OE0071CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ESTERO DE MAYPAJO, PACKAGE I, MANILA | North Manila DEO | DMLC BUILDERS | Completed | ₱113.1M | 100% | High risk65 | —-0.075 |
| 609 | 24O00228CONSTRUCTION OF THE PSC 2ND GUARD COMPANY BUILDING | National Capital Region | NBCDC CORP. | On-Going | ₱327.6M | 2% | High risk65 | Flagged0.048 |
| 610 | 25OE0052REHABILITATION OF DRAINAGE ALONG ZONE 58 - 67, MANILA CITY (PHASE IV) | North Manila DEO | GOLDEN J'S CONSTRUCTION SERVICES | On-Going | ₱93.9M | 16% | High risk65 | —-0.025 |
| 611 | 21OE0022REHABILITATION OF RCBC ALONG E. QUINTOS STREET CHAINAGE 000.00 -CHAINAGE 803.00, MANILA CITY | North Manila DEO | DL ENTERPRISES | Completed | ₱94M | 100% | High risk65 | —-0.077 |
| 612 | 24OF0136PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - QUIRINO HIGHWAY (S05621LZ) K0012 + 000 - K0014 + 316, QUEZON CITY | Quezon City 1st DEO | L.R. TIQUI BUILDERS, INC.M3 KONSTRACT CORPORATION (FORMERLY:MARGARITA CONSTRUCTION) | On-Going | ₱143.1M | 99% | High risk65 | —-0.044 |
| 613 | 24OB0329IMPROVEMENT OF NANGKA RIVER, MARIKINA CITY | Metro Manila 1st DEO | L.R. TIQUI BUILDERS, INC. | Completed | ₱94.5M | 100% | High risk65 | —-0.077 |
| 614 | 25OE0080REHABILITATION OF ROADS WITH DRAINAGE IMPROVEMENT WITHIN ZONE 25-40 (PHASE III), MANILA CITY | North Manila DEO | EIGHT J'S CONSTRUCTION SERVICESJIM AND JEM CONSTRUCTION SERVICES | On-Going | ₱141.9M | 70% | High risk65 | —-0.044 |
| 615 | 23O00061CONSTRUCTION OF PHILIPPINE CANCER CENTER, DILIMAN, QUEZON CITY | National Capital Region | KAEL CONSTRUCTION AND SUPPLY | On-Going | ₱675M | 20% | High risk65 | Flagged0.008 |
| 616 | 23OD0138CONSTRUCTION OF FLOOD CONTROL WALL ALONG SAPANG ALAT CREEK, STA. 3+296 TO 3+648, CALOOCAN CITY | Metro Manila 3rd DEO | AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129) | Completed | ₱94M | 100% | High risk65 | —-0.076 |
| 617 | 25OI0054CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MANGANGATE RIVER, MUNTINLUPA CITY | Las Piñas-Muntinlupa DEO | A.M. ORETA & CO., INC. | On-Going | ₱94.1M | 0% | High risk65 | —-0.020 |
| 618 | 25OI0078CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SOUTHVILLE 3, BARANGAY POBLACION, MUNTINLUPA CITY | Las Piñas-Muntinlupa DEO | A.M. ORETA & CO., INC. | On-Going | ₱94.6M | 86% | High risk65 | —-0.044 |
| 619 | 22O00003CONSTRUCTION OF LAGUNA LAKE HIGHWAY EXTENSION (PHASE 4), MUNTINLUPA CITY | National Capital Region | C.T. LEONCIO CONSTRUCTION & TRADING | Completed | ₱144.7M | 100% | High risk65 | —-0.074 |
| 620 | 21O00065CONSTRUCTION OF NEW CITY PROSECUTOR'S BUILDING, CITY HALL COMPOUND DILIMAN, QUEZON CITY | National Capital Region | 11-16 CONSTRUCTIONFLORIDABLANCA CONSTRUCTION AND DEVELOPMENT CORPORATION | On-Going | ₱144.7M | 100% | High risk65 | —-0.024 |
| 621 | 23OC0062CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (INSTALLATION OF BOOSTER PUMP) AND GROUNDSILL AT DON GALO RIVER NEAR MULTINATIONAL AVENUE, DISTRICT 2, PARAÑAQUE CITY, METRO MANILA | Metro Manila 2nd DEO | NEWBIG FOUR J CONSTRUCTION INC. (FORMERLY: FOUR J CONSTRUCTION) | Completed | ₱93.9M | 100% | High risk65 | —-0.072 |
| 622 | 23O00062CONSTRUCTION OF NATIONAL TOBACCO ADMINISTRATION BUILDING, QUEZON CITY (PHASE 2) | National Capital Region | HAWK KEY CONSTRUCTION AND GENERAL MERCHANDISE CORPORATIONC.B. GARAY PHILWIDE BUILDERS | Completed | ₱283.2M | 100% | High risk65 | —-0.051 |
| 623 | 25OH0058ORGANIZATIONAL OUTCOME 2: PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS / FLOOD MANAGEMENT PROGRAM / CONST./ MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS/ CONST. OF SLOPE PROTECTION STRUCTURE,PHASE 4, BASECO COMPOUND, PORT AREA,MANILA CITY | South Manila DEO | JELSIE CONSTRUCTION & SUPPLY | On-Going | ₱95M | 79% | High risk65 | —-0.044 |
| 624 | 23OE0199CONSTRUCTION OF RETENTION BASIN AT ESTERO DELA REINA (PHASE XV), TONDO, MANILA | North Manila DEO | G.F. FABIAN CONSTRUCTION | Completed | ₱94.8M | 100% | High risk65 | —-0.066 |
| 625 | 23OE0048CONSTRUCTION OF RETENTION BASIN AT ESTERO DELA REINA (PHASE XIV), TONDO, MANILA CITY | North Manila DEO | SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC.MANGEN TECHNO-BUILDERS INC. | Completed | ₱94.9M | 100% | High risk65 | —-0.074 |